TASK NAME COST Materials Labour Machinaries/ Equipment Duration

Stump RM 38,141.40 8 days


- 1 Operator Excavator
Excavation RM 729.00 10 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Pour lean concrete RM 598.40 3 days
Plywood Formwork 2 labour Nail, hammer
Install formwork RM 9,391.20 7 days
Rebar 1 labour (bender) End plier's cutter, chain block, steel hook, measuring tape,
Install bar reinforcement RM 22,622.80 7 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Concreting RM 4,800.00 5 days

Ground Beam RM 90,377.60 8 days


- 1 Operator Excavator
Excavation RM 1,263.60 5 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Pour lean concrete RM 2,543.20 5 days
Plywood Formwork 2 labour Nail, hammer
Install formwork RM 38,656.80 8 days
Rebar 1 labour (bender) End plier's cutter, chain block, steel hook, measuring tape,
Install bar reinforcement RM 24,874.00 8 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Concreting RM 23,040.00 4 days

Ground Slab RM 193,383.60 12 days


- 1 Operator Excavator
Excavation RM 7,290.00 5 days
Cement, Anti-Termite Treatment 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Anti-termite tx spray & pour lean concrete RM 22,739.20 7 days
plolyethylene DPM 2 labour Trowel, scrapper
Install damp proof membrane RM 15,321.60 2 days
Plywood Formwork 2 labour Nail, hammer
Install formwork RM 18,454.80 5 days
Rebar 1 labour (bender) End plier's cutter, chain block, steel hook, measuring tape,
Install bar reinforcement RM 50,163.60 12 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Concreting RM 79,414.40 8 days

Apron Slab RM 40,107.20 7 days


- 1 Operator Excavator
Excavation RM 972.00 5 days
agrregate 2 labour Shovel
Pour hardcore mix RM 1,936.00 3 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Pour lean concrete RM 3,291.20 5 days
Plywood Formwork 2 labour Nail, hammer
Install formwork RM 13,540.80 7 days
Rebar 1 labour (bender) End plier's cutter, chain block, steel hook, measuring tape,
Install bar reinforcement RM 8,282.40 7 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Concreting RM 12,084.80 5 days

FRAME RM 173,009.20 21 days

Column RM 43,032.00 14 days


Plywood 2 labour Nail, hammer
Install formwork RM 2,402.40 9 days
Rebar 1 labour (bender) End plier's cutter, chain block, stell hook, measuring tape
Install bar reinforcement RM 25,092.00 14 days
Cement 1 operator, 2 labour Concrete Mixer Truck, shovel, wheelbarrow
Concreting RM 15,537.60 9 days

Roof Beam RM 86,918.00 21 days


Plywood 2 labour Nail, hammer
Install formwork RM 38,596.80 21 days
Rebar 1 labour (bender) End plier's cutter, chain block, stell hook, measuring tape
Install bar reinforcement RM 24,745.20 14 days
Cement 1 operator, 2 labour Concrete Mixer Truck, shovel, wheelbarrow
Concreting RM 23,576.00 9 days

Coping RM 43,059.20 14 days


Plywood 2 labour Nail, hammer
Install formwork RM 22,440.00 14 days
Rebar 1 labour (bender) End plier's cutter, chain block, stell hook, measuring tape
Install bar reinforcement RM 12,199.20 14 days
Cement 1 operator, 2 labour Concrete Mixer Truck, shovel, wheelbarrow
Concreting RM 8,420.00 9 days