TASK NAME COST Materials Labour Machinaries/ Equipment Duration

Sump, manhole & drainage system RM 23,250.79 30 days


PVC pipes, Manhole Cover, Cement 2 labour Pressure gauge, Flow meter
Sump, manhole and pipes installation with allowance for testing RM 23,250.79 35 days

External Finishes RM 108,663.10 14 days

External Ceiling Finishes RM 11,593.40 7 days


Cement Board (panel) 2 labour Hammer drill, Power saw, screws
Install cement board RM 11,593.40 8 days

External Wall Finishes RM 78,890.50 14 days


Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Plastering and painting RM 57,674.50 16 days
Drywall mud 1 labour Trowels, Mud Pans
Apply skim coat RM 21,216.00 9 days

External Floor Finishes RM 18,179.20 14 days


Cement, floor hardener 2 labour Trowels, Wheelbarrows,
Pave cement-sand trowel finish with floor hardener RM 18,179.20 16 days

Gates RM 23,406.09 7 days


Gate panels, frame, hinges, handles, gate 1 operator, 2 labour Post hole digger, backhoe
Supply and install gates RM 23,406.09 stops 8 days
Turf/Sod, Fertilizer 2 labour Wheelbarrow, Rake
Spot Turfing RM 2,287.85 16 days

PLOT F (4 CORNER UNITS, 10 INTERMEDIATE UNITS) RM 2,506,286.24 35 days

PILING WORKS RM 178,816.44 35 days


- 2 labour Lorry/Truck
Mobilisation of piling equipment RM 3,022.73 3 days

Precast Concrete Square Piles RM 175,634.62 35 days


- 1 operator, 2 labour Vibratory Hammer
Supply and deliver initial and extension piles RM 132,746.40 6 days
- 1 operator, 2 labour Vibratory Hammer
Handle, transport and pitch into driving position for initial and extension piles RM 3,759.00 30 days
- 1 operator, 2 labour Vibratory Hammer
Driving pile RM 23,842.80 30 days
- 2 labour (welder) Welding Machine
Butt weld connection RM 10,740.00 30 days
- 1 operator, 1 labor Jack Hammer or Circular Saw
Cutting-Off Piles RM 3,114.60 6 days
- 1 operator, 2 labour Drop hammer
Testing pile RM 1,431.82 35 days
Document 1 labour -
Piling Records RM 159.09 35 days

BUILDING WORKS RM 2,327,469.80 30 days

SUBSTRUCTURE & SUPERSTRUCTURE RM 1,042,348.20 30 days

WBLFF RM 472,679.60 12 days

Pile Cap RM 55,302.80 7 days


- 1 Operator Excavator
Excavation RM 850.50 6 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Pour lean concrete RM 691.90 4 days
Plywood Formwork 2 labour Nail, hammer
Install formwork RM 15,724.80 8 days
Rebar 1 labour (bender) End plier's cutter, chain block, steel hook, measuring tape,
Install bar reinforcement RM 15,635.60 8 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Concreting RM 22,400.00 6 days

Stump RM 44,282.00 8 days


- 1 Operator Excavator
Excavation including backfilling RM 850.50 12 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Pour lean concrete RM 691.90 4 days
Plywood Formwork 2 labour Nail, hammer
Install formwork RM 10,920.00 8 days
Rebar 1 labour (bender) End plier's cutter, chain block, steel hook, measuring tape,
Install bar reinforcement RM 26,219.60 8 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Concreting RM 5,600.00 6 days

Ground Beam RM 105,136.00 8 days


- 1 Operator Excavator
Excavation RM 1,458.00 6 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Pour lean concrete RM 2,954.60 6 days
Plywood Formwork 2 labour Nail, hammer
Install formwork RM 44,826.60 9 days
Rebar 1 labour (bender) End plier's cutter, chain block, steel hook, measuring tape,
Install bar reinforcement RM 29,016.80 9 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Concreting RM 26,880.00 5 days