TASK NAME COST

Letter of Award RM 0.00


PRELIMINARIES & GENERAL RM 405,990.70
Mobilisation and clearing of rubbish/ or debris RM 3,618.00
Contractor's superintendence/ site management RM 41,055.00
Performance bond RM 61,053.00
Contractor's all risk RM 54,270.00
Workmen compensation RM 16,280.90
Final cleaning/ or clearing before handling over RM 7,635.00
Initial drawings/ Shop drawings and As-Built drawings RM 31,510.00
Temporary office and storage RM 32,561.80
Work schedule/ Work programme RM 0.00
Compliance of relevant authority requirements at site RM 904.00
Temporary water, lighting and electrical supply RM 1,266.00
Site meeting and progress weekly report RM 19,808.00
CIDB levy RM 2,713.00
Existing services RM 37,989.00
Mobilisation and demobilisation RM 6,512.00
Signboard RM 26,049.00
Temporary hoarding board RM 6,210.00
Fee with relevant authorities RM 10,698.00
PLOT A (4 CORNER UNITS & 8 INTERMEDIATE UNITS) RM 2,168,746.89
PILING WORKS RM 155,773.74
Mobilisation of piling equipment RM 2,590.91
Precast Concrete Square Piles RM 153,046.47
Supply and deliver initial and extension piles RM 115,689.60
Handle, transport and pitch into driving position for initial and extension piles RM 3,276.00
Driving pile RM 20,779.20
Butt weld connection RM 9,360.00
Cutting-Off Piles RM 2,714.40
Testing pile RM 1,227.27
Piling Records RM 136.36
BUILDING WORKS RM 1,777,464.00
SUBSTRUCTURE & SUPERSTRUCTURE RM 904,344.80
WBLFF RM 409,552.80
Pile Cap RM 47,543.00
Excavation RM 729.00
Pour lean concrete RM 598.40
Install formwork RM 13,540.80
Install bar reinforcement RM 13,474.80
Concreting RM 19,200.00
Stump RM 38,141.40
Excavation RM 729.00
Pour lean concrete RM 598.40
Install formwork RM 9,391.20
Install bar reinforcement RM 22,622.80
Concreting RM 4,800.00
Ground Beam RM 90,377.60
Excavation RM 1,263.60
Pour lean concrete RM 2,543.20
Install formwork RM 38,656.80
Install bar reinforcement RM 24,874.00
Concreting RM 23,040.00
Ground Slab RM 193,383.60
Excavation RM 7,290.00
Anti-termite tx spray & pour lean concrete RM 22,739.20
Install damp proof membrane RM 15,321.60
Install formwork RM 18,454.80
Install bar reinforcement RM 50,163.60
Concreting RM 79,414.40
Apron Slab RM 40,107.20
Excavation RM 972.00
Pour hardcore mix RM 1,936.00
Pour lean concrete RM 3,291.20
Install formwork RM 13,540.80
Install bar reinforcement RM 8,282.40
Concreting RM 12,084.80
FRAME RM 173,009.20
Column RM 43,032.00
Install formwork RM 2,402.40
Install bar reinforcement RM 25,092.00
Concreting RM 15,537.60
Roof Beam RM 86,918.00
Install formwork RM 38,596.80
Install bar reinforcement RM 24,745.20
Concreting RM 23,576.00
Coping RM 43,059.20
Install formwork RM 22,440.00
Install bar reinforcement RM 12,199.20
Concreting RM 8,420.00
ROOF CONSTRUCTION RM 321,782.80
Roof Truss RM 59,400.00
Install roof truss c/w accessories RM 59,400.00
Roof Covering RM 198,611.20
Install roof covering c/w accessories RM 198,611.20
Rainwater Gutter and Goods RM 63,771.60
Install rainwater gutter and goods c/w accessories RM 63,771.60
ARCHITECTURAL WORKS RM 873,119.20
Bricklaying RM 253,001.20
External Wall RM 126,388.00
Bricklaying including DPC RM 126,388.00
Internal Wall RM 126,613.20
Bricklaying including DPC RM 126,613.20
Shower wall niche RM 7,200.00
Install formwork RM 2,400.00
Install bar reinforcement RM 2,400.00
Concreting RM 2,400.00
Reinforced concrete counter top RM 6,480.00
Install formwork RM 2,160.00
Install bar reinforcement RM 2,160.00
Concreting RM 2,160.00
Door RM 90,704.00
Installation of lintol RM 10,880.00
Supply and install door frame RM 13,500.00
Supply and install door including lockset RM 66,324.00
Window RM 63,184.00
Installation of lintol RM 4,000.00
Supply and install windows c/w accessories RM 59,184.00
Internal Finishes RM 452,550.00
Internal Ceiling Finishes RM 48,263.20
Installing plasterboard RM 29,859.20
Apply sealant RM 18,404.00
Internal Wall Finishes including wall niche RM 211,052.40
Plastering and painting RM 160,461.60
Screeding and tiling RM 50,590.80
Reinforced concrete counter top RM 4,320.00
Plastering and painting RM 2,160.00
Screeding and tiling RM 2,160.00
Sanitary Appliances RM 72,900.80
Install sanitary appliances RM 72,900.80
Internal Floor Finishes RM 116,013.60
Screeding and tiling RM 116,013.60
EXTERNAL WORKS WITHIN BOUNDARY RM 235,509.15
Bricklaying RM 99,156.84
Fencing RM 53,389.50
Bricklaying including reinforcement RM 53,389.50
SESCO Compartment RM 14,517.40
Bricklaying including reinforcement RM 14,517.40
Refuse Chamber & Mailbox Compartment RM 31,249.94
Bricklaying including reinforcement RM 31,249.94
Sump, manhole & drainage system RM 19,929.25
Sump, manhole and pipes installation with allowance for testing RM 19,929.25
External Finishes RM 94,399.68
External Ceiling Finishes RM 10,207.60
Install cement board RM 10,207.60
External Wall Finishes RM 68,140.88
Plastering and painting RM 49,784.88
Apply skim coat RM 18,356.00
External Floor Finishes RM 16,051.20
Pave cement-sand trowel finish with floor hardener RM 16,051.20
Gates RM 20,062.36
Supply and install gates RM 20,062.36
Spot Turfing RM 1,961.02
PLOT B (4 CORNER UNITS & 8 INTERMEDIATE UNITS) RM 2,168,746.89
PILING WORKS RM 155,773.74
Mobilisation of piling equipment RM 2,590.91
Precast Concrete Square Piles RM 153,046.47
Supply and deliver initial and extension piles RM 115,689.60
Handle, transport and pitch into driving position for initial and extension piles RM 3,276.00
Driving pile RM 20,779.20
Butt weld connection RM 9,360.00
Cutting-Off Piles RM 2,714.40
Testing pile RM 1,227.27
Piling Records RM 136.36
BUILDING WORKS RM 1,777,464.00
SUBSTRUCTURE & SUPERSTRUCTURE RM 904,344.80
WBLFF RM 409,552.80
Pile Cap RM 47,543.00
Excavation RM 729.00
Pour lean concrete RM 598.40
Install formwork RM 13,540.80
Install bar reinforcement RM 13,474.80
Concreting RM 19,200.00
Stump RM 38,141.40
Excavation including backfilling RM 729.00
Pour lean concrete RM 598.40
Install formwork RM 9,391.20
Install bar reinforcement RM 22,622.80
Concreting RM 4,800.00
Ground Beam RM 90,377.60
Excavation RM 1,263.60
Pour lean concrete RM 2,543.20
Install formwork RM 38,656.80
Install bar reinforcement RM 24,874.00
Concreting RM 23,040.00
Ground Slab RM 193,383.60
Excavation RM 7,290.00
Anti-termite tx spray & pour lean concrete RM 22,739.20
Install damp proof membrane RM 15,321.60
Install formwork RM 18,454.80
Install bar reinforcement RM 50,163.60
Concreting RM 79,414.40
Apron Slab RM 40,107.20
Excavation RM 972.00
Pour hardcore mix RM 1,936.00
Pour lean concrete RM 3,291.20
Install formwork RM 13,540.80
Install bar reinforcement RM 8,282.40
Concreting RM 12,084.80
FRAME RM 173,009.20
Column RM 43,032.00
Install formwork RM 2,402.40
Install bar reinforcement RM 25,092.00
Concreting RM 15,537.60
Roof Beam RM 86,918.00
Install formwork RM 38,596.80
Install bar reinforcement RM 24,745.20
Concreting RM 23,576.00
Coping RM 43,059.20
Install formwork RM 22,440.00
Install bar reinforcement RM 12,199.20
Concreting RM 8,420.00
ROOF CONSTRUCTION RM 321,782.80
Roof Truss RM 59,400.00
Install roof truss c/w accessories RM 59,400.00
Roof Covering RM 198,611.20
Install roof covering c/w accessories RM 198,611.20
Rainwater Gutter and Goods RM 63,771.60
Install rainwater gutter and goods c/w accessories RM 63,771.60
ARCHITECTURAL WORKS RM 873,119.20
Bricklaying RM 253,001.20
External Wall RM 126,388.00
Bricklaying including DPC RM 126,388.00
Internal Wall RM 126,613.20
Bricklaying including DPC RM 126,613.20
Shower wall niche RM 7,200.00
Install formwork RM 2,400.00
Install bar reinforcement RM 2,400.00
Concreting RM 2,400.00
Reinforced concrete counter top RM 6,480.00
Install formwork RM 2,160.00
Install bar reinforcement RM 2,160.00
Concreting RM 2,160.00
Door RM 90,704.00
Installation of lintol RM 10,880.00
Supply and install door frame RM 13,500.00
Supply and install door including lockset RM 66,324.00
Window RM 63,184.00
Installation of lintol RM 4,000.00
Supply and install windows c/w accessories RM 59,184.00
Internal Finishes RM 452,550.00
Internal Ceiling Finishes RM 48,263.20
Installing plasterboard RM 29,859.20
Apply sealant RM 18,404.00
Internal Wall Finishes including wall niche RM 211,052.40
Plastering and painting RM 160,461.60
Screeding and tiling RM 50,590.80
Reinforced concrete counter top RM 4,320.00
Plastering and painting RM 2,160.00
Screeding and tiling RM 2,160.00
Sanitary Appliances RM 72,900.80
Install sanitary appliances RM 72,900.80
Internal Floor Finishes RM 116,013.60
Screeding and tiling RM 116,013.60
EXTERNAL WORKS WITHIN BOUNDARY RM 235,509.15
Bricklaying RM 99,156.84
Fencing RM 53,389.50
Bricklaying including reinforcement RM 53,389.50
SESCO Compartment RM 14,517.40
Bricklaying including reinforcement RM 14,517.40
Refuse Chamber & Mailbox Compartment RM 31,249.94
Bricklaying including reinforcement RM 31,249.94
Sump, manhole & drainage system RM 19,929.25
Sump, manhole and pipes installation with allowance for testing RM 19,929.25
External Finishes RM 94,399.68
External Ceiling Finishes RM 10,207.60
Install cement board RM 10,207.60
External Wall Finishes RM 68,140.88
Plastering and painting RM 49,784.88
Apply skim coat RM 18,356.00
External Floor Finishes RM 16,051.20
Pave cement-sand trowel finish with floor hardener RM 16,051.20
Gates RM 20,062.36
Supply and install gates RM 20,062.36
Spot Turfing RM 1,961.02
PLOT C (2 CORNER UNITS, 14 INTERMEDIATE UNITS, 2 END UNITS) RM 3,169,252.53
PILING WORKS RM 216,143.02
Mobilisation of piling equipment RM 3,886.36
Precast Concrete Square Piles RM 212,052.11
Supply and deliver initial and extension piles RM 160,185.60
Handle, transport and pitch into driving position for initial and extension piles RM 4,536.00
Driving pile RM 28,771.20
Butt weld connection RM 12,960.00
Cutting-Off Piles RM 3,758.40
Testing pile RM 1,840.91
Piling Records RM 204.55
BUILDING WORKS RM 2,604,255.40
SUBSTRUCTURE & SUPERSTRUCTURE RM 1,314,601.40
WBLFF RM 595,730.40
Pile Cap RM 68,647.80
Excavation RM 1,069.20
Pour lean concrete RM 860.20
Install formwork RM 19,437.60
Install bar reinforcement RM 19,280.80
Concreting RM 28,000.00
Stump RM 55,535.00
Excavation including backfilling RM 1,069.20
Pour lean concrete RM 860.20
Install formwork RM 13,759.20
Install bar reinforcement RM 32,646.40
Concreting RM 7,200.00
Ground Beam RM 134,652.80
Excavation RM 1,846.80
Pour lean concrete RM 3,777.40
Install formwork RM 57,166.20
Install bar reinforcement RM 37,302.40
Concreting RM 34,560.00
Ground Slab RM 193,383.60
Excavation RM 7,290.00
Anti-termite tx spray & pour lean concrete RM 22,739.20
Install damp proof membrane RM 15,321.60
Install formwork RM 18,454.80
Install bar reinforcement RM 50,163.60
Concreting RM 79,414.40
Apron Slab RM 40,107.20
Excavation RM 972.00
Pour hardcore mix RM 1,936.00
Pour lean concrete RM 3,291.20
Install formwork RM 13,540.80
Install bar reinforcement RM 8,282.40
Concreting RM 12,084.80
FRAME RM 241,820.80
Column RM 63,717.60
Install formwork RM 3,385.20
Install bar reinforcement RM 37,026.00
Concreting RM 23,306.40
Roof Beam RM 123,797.00
Install formwork RM 54,753.60
Install bar reinforcement RM 35,363.40
Concreting RM 33,680.00
Coping RM 54,306.20
Install formwork RM 28,498.80
Install bar reinforcement RM 14,861.40
Concreting RM 10,946.00
ROOF CONSTRUCTION RM 373,538.60
Roof Truss RM 68,850.00
Install roof truss c/w accessories RM 68,850.00
Roof Covering RM 230,145.40
Install roof covering c/w accessories RM 230,145.40
Rainwater Gutter and Goods RM 74,543.20
Install rainwater gutter and goods c/w accessories RM 74,543.20
ARCHITECTURAL WORKS RM 1,289,654.00
Bricklaying RM 379,023.40
External Wall RM 188,800.00
Bricklaying including DPC RM 188,800.00
Internal Wall RM 190,223.40
Bricklaying including DPC RM 190,223.40
Shower wall niche RM 10,800.00
Install formwork RM 3,600.00
Install bar reinforcement RM 3,600.00
Concreting RM 3,600.00
Reinforced concrete counter top RM 9,720.00
Install formwork RM 3,240.00
Install bar reinforcement RM 3,240.00
Concreting RM 3,240.00
Door RM 135,656.00
Installation of lintol RM 15,920.00
Supply and install door frame RM 20,250.00
Supply and install door including lockset RM 99,486.00
Window RM 90,784.00
Installation of lintol RM 5,680.00
Supply and install windows c/w accessories RM 85,104.00
Internal Finishes RM 663,670.60
Internal Ceiling Finishes RM 69,935.20
Installing plasterboard RM 43,275.20
Apply sealant RM 26,660.00
Internal Wall Finishes including wall niche RM 312,249.60
Plastering and painting RM 236,363.40
Screeding and tiling RM 75,886.20
Reinforced concrete counter top RM 6,480.00
Plastering and painting RM 3,240.00
Screeding and tiling RM 3,240.00
Sanitary Appliances RM 109,051.20
Install sanitary appliances RM 109,051.20
Internal Floor Finishes RM 165,954.60
Screeding and tiling RM 165,954.60
EXTERNAL WORKS WITHIN BOUNDARY RM 348,854.11
Bricklaying RM 148,735.24
Fencing RM 80,084.25
Bricklaying including reinforcement RM 80,084.25
SESCO Compartment RM 21,776.09
Bricklaying including reinforcement RM 21,776.09
Refuse Chamber & Mailbox Compartment RM 46,874.90
Bricklaying including reinforcement RM 46,874.90
Sump, manhole & drainage system RM 29,893.87
Sump, manhole and pipes installation with allowance for testing RM 29,893.87
External Finishes RM 137,189.92
External Ceiling Finishes RM 14,365.00
Install cement board RM 14,365.00
External Wall Finishes RM 100,389.72
Plastering and painting RM 73,453.72
Apply skim coat RM 26,936.00
External Floor Finishes RM 22,435.20
Pave cement-sand trowel finish with floor hardener RM 22,435.20
Gates RM 30,093.55
Supply and install gates RM 30,093.55
Spot Turfing RM 2,941.53
PLOT D (2 CORNER UNITS, 14 INTERMEDIATE UNITS, 2 END UNITS) RM 3,169,252.53
PILING WORKS RM 216,143.02
Mobilisation of piling equipment RM 3,886.36
Precast Concrete Square Piles RM 212,052.11
Supply and deliver initial and extension piles RM 160,185.60
Handle, transport and pitch into driving position for initial and extension piles RM 4,536.00
Driving pile RM 28,771.20
Butt weld connection RM 12,960.00
Cutting-Off Piles RM 3,758.40
Testing pile RM 1,840.91
Piling Records RM 204.55
BUILDING WORKS RM 2,604,255.40
SUBSTRUCTURE & SUPERSTRUCTURE RM 1,314,601.40
WBLFF RM 595,730.40
Pile Cap RM 68,647.80
Excavation RM 1,069.20
Pour lean concrete RM 860.20
Install formwork RM 19,437.60
Install bar reinforcement RM 19,280.80
Concreting RM 28,000.00
Stump RM 55,535.00
Excavation including backfilling RM 1,069.20
Pour lean concrete RM 860.20
Install formwork RM 13,759.20
Install bar reinforcement RM 32,646.40
Concreting RM 7,200.00
Ground Beam RM 134,652.80
Excavation RM 1,846.80
Pour lean concrete RM 3,777.40
Install formwork RM 57,166.20
Install bar reinforcement RM 37,302.40
Concreting RM 34,560.00
Ground Slab RM 193,383.60
Excavation RM 7,290.00
Anti-termite tx spray & pour lean concrete RM 22,739.20
Install damp proof membrane RM 15,321.60
Install formwork RM 18,454.80
Install bar reinforcement RM 50,163.60
Concreting RM 79,414.40
Apron Slab RM 40,107.20
Excavation RM 972.00
Pour hardcore mix RM 1,936.00
Pour lean concrete RM 3,291.20
Install formwork RM 13,540.80
Install bar reinforcement RM 8,282.40
Concreting RM 12,084.80
FRAME RM 241,820.80
Column RM 63,717.60
Install formwork RM 3,385.20
Install bar reinforcement RM 37,026.00
Concreting RM 23,306.40
Roof Beam RM 123,797.00
Install formwork RM 54,753.60
Install bar reinforcement RM 35,363.40
Concreting RM 33,680.00
Coping RM 54,306.20
Install formwork RM 28,498.80
Install bar reinforcement RM 14,861.40
Concreting RM 10,946.00
ROOF CONSTRUCTION RM 373,538.60
Roof Truss RM 68,850.00
Install roof truss c/w accessories RM 68,850.00
Roof Covering RM 230,145.40
Install roof covering c/w accessories RM 230,145.40
Rainwater Gutter and Goods RM 74,543.20
Install rainwater gutter and goods c/w accessories RM 74,543.20
ARCHITECTURAL WORKS RM 1,289,654.00
Bricklaying RM 379,023.40
External Wall RM 188,800.00
Bricklaying including DPC RM 188,800.00
Internal Wall RM 190,223.40
Bricklaying including DPC RM 190,223.40
Shower wall niche RM 10,800.00
Install formwork RM 3,600.00
Install bar reinforcement RM 3,600.00
Concreting RM 3,600.00
Reinforced concrete counter top RM 9,720.00
Install formwork RM 3,240.00
Install bar reinforcement RM 3,240.00
Concreting RM 3,240.00
Door RM 135,656.00
Installation of lintol RM 15,920.00
Supply and install door frame RM 20,250.00
Supply and install door including lockset RM 99,486.00
Window RM 90,784.00
Installation of lintol RM 5,680.00
Supply and install windows c/w accessories RM 85,104.00
Internal Finishes RM 663,670.60
Internal Ceiling Finishes RM 69,935.20
Installing plasterboard RM 43,275.20
Apply sealant RM 26,660.00
Internal Wall Finishes including wall niche RM 312,249.60
Plastering and painting RM 236,363.40
Screeding and tiling RM 75,886.20
Reinforced concrete counter top RM 6,480.00
Plastering and painting RM 3,240.00
Screeding and tiling RM 3,240.00
Sanitary Appliances RM 109,051.20
Install sanitary appliances RM 109,051.20
Internal Floor Finishes RM 165,954.60
Screeding and tiling RM 165,954.60
EXTERNAL WORKS WITHIN BOUNDARY RM 348,854.11
Bricklaying RM 148,735.24
Fencing RM 80,084.25
Bricklaying including reinforcement RM 80,084.25
SESCO Compartment RM 21,776.09
Bricklaying including reinforcement RM 21,776.09
Refuse Chamber & Mailbox Compartment RM 46,874.90
Bricklaying including reinforcement RM 46,874.90
Sump, manhole & drainage system RM 29,893.87
Sump, manhole and pipes installation with allowance for testing RM 29,893.87
External Finishes RM 137,189.92
External Ceiling Finishes RM 14,365.00
Install cement board RM 14,365.00
External Wall Finishes RM 100,389.72
Plastering and painting RM 73,453.72
Apply skim coat RM 26,936.00
External Floor Finishes RM 22,435.20
Pave cement-sand trowel finish with floor hardener RM 22,435.20
Gates RM 30,093.55
Supply and install gates RM 30,093.55
Spot Turfing RM 2,941.53
PLOT E (2 CORNER UNITS, 10 INTERMEDIATE UNITS) RM 2,506,286.24
PILING WORKS RM 178,816.44
Mobilisation of piling equipment RM 3,022.73
Precast Concrete Square Piles RM 175,634.62
Supply and deliver initial and extension piles RM 132,746.40
Handle, transport and pitch into driving position for initial and extension piles RM 3,759.00
Driving pile RM 23,842.80
Butt weld connection RM 10,740.00
Cutting-Off Piles RM 3,114.60
Testing pile RM 1,431.82
Piling Records RM 159.09
BUILDING WORKS RM 2,327,469.80
SUBSTRUCTURE & SUPERSTRUCTURE RM 1,042,348.20
WBLFF RM 472,679.60
Pile Cap RM 55,302.80
Excavation RM 850.50
Pour lean concrete RM 691.90
Install formwork RM 15,724.80
Install bar reinforcement RM 15,635.60
Concreting RM 22,400.00
Stump RM 44,282.00
Excavation including backfilling RM 850.50
Pour lean concrete RM 691.90
Install formwork RM 10,920.00
Install bar reinforcement RM 26,219.60
Concreting RM 5,600.00
Ground Beam RM 105,136.00
Excavation RM 1,458.00
Pour lean concrete RM 2,954.60
Install formwork RM 44,826.60
Install bar reinforcement RM 29,016.80
Concreting RM 26,880.00
Ground Slab RM 193,383.60
Excavation RM 7,290.00
Anti-termite tx spray & pour lean concrete RM 22,739.20
Install damp proof membrane RM 15,321.60
Install formwork RM 18,454.80
Install bar reinforcement RM 50,163.60
Concreting RM 79,414.40
Apron Slab RM 40,107.20
Excavation RM 972.00
Pour hardcore mix RM 1,936.00
Pour lean concrete RM 3,291.20
Install formwork RM 13,540.80
Install bar reinforcement RM 8,282.40
Concreting RM 12,084.80
FRAME RM 196,130.00
Column RM 50,110.80
Install formwork RM 2,730.00
Install bar reinforcement RM 29,253.60
Concreting RM 18,127.20
Roof Beam RM 99,211.00
Install formwork RM 43,982.40
Install bar reinforcement RM 28,284.60
Concreting RM 26,944.00
Coping RM 46,808.20
Install formwork RM 24,459.60
Install bar reinforcement RM 13,086.60
Concreting RM 9,262.00
ROOF CONSTRUCTION RM 373,538.60
Roof Truss RM 68,850.00
Install roof truss c/w accessories RM 68,850.00
Roof Covering RM 230,145.40
Install roof covering c/w accessories RM 230,145.40
Rainwater Gutter and Goods RM 74,543.20
Install rainwater gutter and goods c/w accessories RM 74,543.20
ARCHITECTURAL WORKS RM 1,011,830.80
Bricklaying RM 295,008.60
External Wall RM 147,192.00
Bricklaying including DPC RM 147,192.00
Internal Wall RM 147,816.60
Bricklaying including DPC RM 147,816.60
Shower wall niche RM 8,400.00
Install formwork RM 2,800.00
Install bar reinforcement RM 2,800.00
Concreting RM 2,800.00
Reinforced concrete counter top RM 7,560.00
Install formwork RM 2,520.00
Install bar reinforcement RM 2,520.00
Concreting RM 2,520.00
Door RM 105,688.00
Installation of lintol RM 12,560.00
Supply and install door frame RM 15,750.00
Supply and install door including lockset RM 77,378.00
Window RM 72,384.00
Installation of lintol RM 4,560.00
Supply and install windows c/w accessories RM 67,824.00
Internal Finishes RM 522,790.20
Internal Ceiling Finishes RM 55,487.20
Installing plasterboard RM 34,331.20
Apply sealant RM 21,156.00
Internal Wall Finishes including wall niche RM 244,784.80
Plastering and painting RM 185,762.20
Screeding and tiling RM 59,022.60
Reinforced concrete counter top RM 5,040.00
Plastering and painting RM 2,520.00
Screeding and tiling RM 2,520.00
Sanitary Appliances RM 84,817.60
Install sanitary appliances RM 84,817.60
Internal Floor Finishes RM 132,660.60
Screeding and tiling RM 132,660.60
EXTERNAL WORKS WITHIN BOUNDARY RM 273,290.80
Bricklaying RM 115,682.97
Fencing RM 62,287.75
Bricklaying including reinforcement RM 62,287.75
SESCO Compartment RM 16,936.96
Bricklaying including reinforcement RM 16,936.96
Refuse Chamber & Mailbox Compartment RM 36,458.26
Bricklaying including reinforcement RM 36,458.26
Sump, manhole & drainage system RM 23,250.79
Sump, manhole and pipes installation with allowance for testing RM 23,250.79
External Finishes RM 108,663.10
External Ceiling Finishes RM 11,593.40
Install cement board RM 11,593.40
External Wall Finishes RM 78,890.50
Plastering and painting RM 57,674.50
Apply skim coat RM 21,216.00
External Floor Finishes RM 18,179.20
Pave cement-sand trowel finish with floor hardener RM 18,179.20
Gates RM 23,406.09
Supply and install gates RM 23,406.09
Spot Turfing RM 2,287.85
PLOT F (4 CORNER UNITS, 10 INTERMEDIATE UNITS) RM 2,506,286.24
PILING WORKS RM 178,816.44
Mobilisation of piling equipment RM 3,022.73
Precast Concrete Square Piles RM 175,634.62
Supply and deliver initial and extension piles RM 132,746.40
Handle, transport and pitch into driving position for initial and extension piles RM 3,759.00
Driving pile RM 23,842.80
Butt weld connection RM 10,740.00
Cutting-Off Piles RM 3,114.60
Testing pile RM 1,431.82
Piling Records RM 159.09
BUILDING WORKS RM 2,327,469.80
SUBSTRUCTURE & SUPERSTRUCTURE RM 1,042,348.20
WBLFF RM 472,679.60
Pile Cap RM 55,302.80
Excavation RM 850.50
Pour lean concrete RM 691.90
Install formwork RM 15,724.80
Install bar reinforcement RM 15,635.60
Concreting RM 22,400.00
Stump RM 44,282.00
Excavation including backfilling RM 850.50
Pour lean concrete RM 691.90
Install formwork RM 10,920.00
Install bar reinforcement RM 26,219.60
Concreting RM 5,600.00
Ground Beam RM 105,136.00
Excavation RM 1,458.00
Pour lean concrete RM 2,954.60
Install formwork RM 44,826.60
Install bar reinforcement RM 29,016.80
Concreting RM 26,880.00
Ground Slab RM 193,383.60
Excavation RM 7,290.00
Anti-termite tx spray & pour lean concrete RM 22,739.20
Install damp proof membrane RM 15,321.60
Install formwork RM 18,454.80
Install bar reinforcement RM 50,163.60
Concreting RM 79,414.40
Apron Slab RM 40,107.20
Excavation RM 972.00
Pour hardcore mix RM 1,936.00
Pour lean concrete RM 3,291.20
Install formwork RM 13,540.80
Install bar reinforcement RM 8,282.40
Concreting RM 12,084.80
FRAME RM 196,130.00
Column RM 50,110.80
Install formwork RM 2,730.00
Install bar reinforcement RM 29,253.60
Concreting RM 18,127.20
Roof Beam RM 99,211.00
Install formwork RM 43,982.40
Install bar reinforcement RM 28,284.60
Concreting RM 26,944.00
Coping RM 46,808.20
Install formwork RM 24,459.60
Install bar reinforcement RM 13,086.60
Concreting RM 9,262.00
ROOF CONSTRUCTION RM 373,538.60
Roof Truss RM 68,850.00
Install roof truss c/w accessories RM 68,850.00
Roof Covering RM 230,145.40
Install roof covering c/w accessories RM 230,145.40
Rainwater Gutter and Goods RM 74,543.20
Install rainwater gutter and goods c/w accessories RM 74,543.20
ARCHITECTURAL WORKS RM 1,011,830.80
Bricklaying RM 295,008.60
External Wall RM 147,192.00
Bricklaying including DPC RM 147,192.00
Internal Wall RM 147,816.60
Bricklaying including DPC RM 147,816.60
Shower wall niche RM 8,400.00
Install formwork RM 2,800.00
Install bar reinforcement RM 2,800.00
Concreting RM 2,800.00
Reinforced concrete counter top RM 7,560.00
Install formwork RM 2,520.00
Install bar reinforcement RM 2,520.00
Concreting RM 2,520.00
Door RM 105,688.00
Installation of lintol RM 12,560.00
Supply and install door frame RM 15,750.00
Supply and install door including lockset RM 77,378.00
Window RM 72,384.00
Installation of lintol RM 4,560.00
Supply and install windows c/w accessories RM 67,824.00
Internal Finishes RM 522,790.20
Internal Ceiling Finishes RM 55,487.20
Installing plasterboard RM 34,331.20
Apply sealant RM 21,156.00
Internal Wall Finishes including wall niche RM 244,784.80
Plastering and painting RM 185,762.20
Screeding and tiling RM 59,022.60
Reinforced concrete counter top RM 5,040.00
Plastering and painting RM 2,520.00
Screeding and tiling RM 2,520.00
Sanitary Appliances RM 84,817.60
Install sanitary appliances RM 84,817.60
Internal Floor Finishes RM 132,660.60
Screeding and tiling RM 132,660.60
EXTERNAL WORKS WITHIN BOUNDARY RM 273,290.80
Bricklaying RM 115,682.97
Fencing RM 62,287.75
Bricklaying including reinforcement RM 62,287.75
SESCO Compartment RM 16,936.96
Bricklaying including reinforcement RM 16,936.96
Refuse Chamber & Mailbox Compartment RM 36,458.26
Bricklaying including reinforcement RM 36,458.26
Sump, manhole & drainage system RM 23,250.79
Sump, manhole and pipes installation with allowance for testing RM 23,250.79
External Finishes RM 108,663.10
External Ceiling Finishes RM 11,593.40
Install cement board RM 11,593.40
External Wall Finishes RM 78,890.50
Plastering and painting RM 57,674.50
Apply skim coat RM 21,216.00
External Floor Finishes RM 18,179.20
Pave cement-sand trowel finish with floor hardener RM 18,179.20
Gates RM 23,406.09
Supply and install gates RM 23,406.09
Spot Turfing RM 2,287.85
Handover RM 0.00
Materials Labour Machinaries/ Equipment
Fri 1/12/24 Fri 1/12/24 -

- 1 skilled worker and 2 helper Lorry and Truck


- 2 Supervisor -
- - -
Insurance certificate - -
Insurance certificate - -
Insurance certificate 1 operator Lorry and Truck
- - -
- 1 operator Truck
- - -
- - -
- - -
- 2 skilled worker truck lorry crane
- - -
Document - -
- - -
- 1 operator lorry truck crane excavator
1 operator Crane
1 operator Truck

- 2 labour Lorry/Truck

- 1 operator, 2 labour Vibratory Hammer


- 1 operator, 2 labour Vibratory Hammer
- 1 operator, 2 labour Vibratory Hammer
- 2 labour (welder) Welding Machine
- 1 operator, 1 labor Jack Hammer or Circular Saw
- 1 operator, 2 labour Drop hammer
Document 1 labour -

- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement, Anti-Termite 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Treatment
plolyethylene DPM 2 labour Wheelbarrow
Trowel, scrapper
Plywood Formwork 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
agrregate 2 labour Shovel
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow

Plywood 2 labour Nail, hammer


Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow

Roof truss 3 labours Nail, hammer

Roof covering 2 skilled labours Nail, hammer, screwdiver

Rainwater gutter and 1 skilled labour Nail, hammer, screwdiver


goods

Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp
- proof course (helper)
Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp proof course (helper)
Plywood 1 operator, 1 skilled labour Nail, Hammer
Rebar 1 skilled labour and 2 labour End plier's cutter, chain block, stell
Cement (helper)
1 skilled labour and 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
Plywood 1 skilled labour and 1 labour Nail, hammer
Rebar (helper)
2 skilled labour End plier's cutter, chain block, stell
Cement 2 general worker hook, measuring
Concrete tape shovel,
Mixer Truck,
- wheelbarrow
timber 2 labour Nail, hammer
hardwood timber 1 carpenter Nail, hammer,screwdriver
harwood timber, key lock 2 labour Nail, hammer,screwdriver
stainless steel
timber 2 labour Nail, hammer
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver

plasterboard 1 skilled labour plasterboard lifter, hoist, trolley,


silicon sealant 2 labour screwdriver,sander
Sealant finishers and sealant gun

Cement, paint 1 skilled labour Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Cement, paint 1 skilled worker Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

sanitary item 1 skilled labour screwdriver

cement, tile 2 skilled labour level screed, tile trowler, grout saws

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

PVC pipes, Manhole 3 labours Pressure gauge, Flow meter


Cover, Cement

Cement Board (panel) 2 labour Hammer drill, Power saw, screws

Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Drywall mud 1 labour Trowels, Mud Pans

Cement, floor hardener 2 labour Trowels, Wheelbarrows,

Gate panels, frame, 1 operator, 2 labour Post hole digger, backhoe


hinges, handles,
Turf/Sod, gate
Fertilizer 2 labor Wheelbarrow, Rake
stops
- 2 labour Lorry/Truck

- 1 operator, 2 labour Vibratory Hammer


- 1 operator, 2 labour Vibratory Hammer
- 1 operator, 2 labour Vibratory Hammer
- 2 labour (welder) Welding Machine
- 1 operator, 1 labor Jack Hammer or Circular Saw
- 1 operator, 2 labour Drop hammer
Document 1 labour -

- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
- 2 labour Wheelbarrow
Hammer
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement, Anti-Termite 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Treatment
plolyethylene DPM 2 labour Wheelbarrow
Trowel, scrapper
Plywood Formwork 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
agrregate 2 labour Shovel
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow

Roof truss 3 labours Nail, hammer

Roof covering 2 skilled labours Nail, hammer, screwdiver

Rainwater gutter and 1 skilled labour Nail, hammer, screwdiver


goods

Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp
- proof course (helper)
Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp proof course (helper)
Plywood 1 operator, 1 skilled labour Nail, hammer
Rebar End plier's cutter, chain block, stell
Cement hook, measuring
1 skilled labour and 2 labour Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 2 labour End plier's cutter, chain block, stell
Cement hook, measuring
1 skilled labour and 1 labour Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
timber 2 labour Nail, hammer
hardwood timber 1 carpenter Nail, hammer,screwdriver
harwood timber, key lock 2 labour Nail, hammer,screwdriver
stainless steel
timber 2 labour Nail, hammer
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver

plasterboard 1 skilled labour plasterboard lifter, hoist, trolley,


silicon sealant 2 labour screwdriver,sander
Sealant finishers and sealant gun

Cement, paint 1 skilled labour Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws
Cement, paint 1 skilled worker Trowel,scraper, paint brush
cement, tile 2 labour level screed, tile trowler, grout saws

Sanitary item 1 skilled labour screwdriver

cement, tile 1 skilled labour level screed, tile trowler, grout saws

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

PVC pipes, Manhole 2 labour Pressure gauge, Flow meter


Cover, Cement

Cement Board (panel) 2 labour Hammer drill, Power saw, screws

Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Drywall mud 1 labour Trowels, Mud Pans

Cement, floor hardener 2 labour Trowels, Wheelbarrows,

Gate panels, frame, 1 operator, 2 labour Post hole digger, backhoe


hinges, handles,
Turf/Sod, gate
Fertilizer 2 labor Wheelbarrow, Rake
stops

- 2 labour Lorry/Truck

- 1 operator, 2 labour Vibratory Hammer


- 1 operator, 2 labour Vibratory Hammer
- 1 operator, 2 labour Vibratory Hammer
- 2 labour (welder) Welding Machine
- 1 operator, 1 labor Jack Hammer or Circular Saw
- 1 operator, 2 labour Drop hammer
Document 1 labour -

- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement, Anti-Termite 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Treatment
plolyethylene DPM 2 labour Wheelbarrow
Trowel, scrapper
Plywood Formwork 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
agrregate 2 labour Shovel
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
- Wheelbarrow

Plywood 2 labour Nail, hammer


Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow

Roof truss 3 labours Nail, hammer

Roof covering 2 skilled labours Nail, hammer, screwdiver

Rainwater gutter and 1 skilled labour Nail, hammer, screwdiver


goods
Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp
- proof course (helper)
Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp proof course (helper)
Plywood 1 operator, 1 skilled labour Nail, hammer
Rebar End plier's cutter, chain block, stell
Cement 1 skilled labour and 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 2 labour End plier's cutter, chain block, stell
Cement 1 skilled labour and 1 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
timber 2 labour Nail, hammer
hardwood timber 1 carpenter Nail, hammer,screwdriver
harwood timber, key lock 2 labour Nail, hammer,screwdriver
stainless steel
timber 2 labour Nail, hammer
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver

plasterboard 1 skilled labour plasterboard lifter, hoist, trolley,


silicon sealant 2 labour screwdriver,sander
Sealant finishers and sealant gun

Cement, paint 1 skilled labour Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Cement, paint 1 skilled worker Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Sanitary item 1 skilled labour screwdriver

cement, tile 1 skilled labour level screed, tile trowler, grout saws

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

PVC pipes, Manhole 2 labour Pressure gauge, Flow meter


Cover, Cement

Cement Board (panel) 2 labour Hammer drill, Power saw, screws

Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Drywall mud 1 labour Trowels, Mud Pans

Cement, floor hardener 2 labour Trowels, Wheelbarrows,

Gate panels, frame, 1 operator, 2 labour Post hole digger, backhoe


hinges, handles,
Turf/Sod, gate
Fertilizer 2 labor Wheelbarrow, Rake
stops

- 2 labour Lorry/Truck

- 1 operator, 2 labour Vibratory Hammer


- 1 operator, 2 labour Vibratory Hammer
- 1 operator, 2 labour Vibratory Hammer
- 2 labour (welder) Welding Machine
- 1 operator, 1 labor Jack Hammer or Circular Saw
- 1 operator, 2 labour Drop hammer
Document 1 labour -

- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement, Anti-Termite 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Treatment
plolyethylene DPM 2 labour Wheelbarrow
Trowel, scrapper
Plywood Formwork 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
agrregate 2 labour Shovel
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow

Plywood 2 labour Nail, hammer


Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow

Roof truss 3 labours Nail, hammer

Roof covering 2 skilled labours Nail, hammer, screwdiver

Rainwater gutter and 1 skilled labour Nail, hammer, screwdiver


goods

Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp
- proof course (helper)
Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp proof course (helper)
Plywood 1 operator, 1 skilled labour Nail, hammer
Rebar End plier's cutter, chain block, stell
Cement hook, measuring
1 skilled labour and 2 labour Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 2 labour End plier's cutter, chain block, stell
Cement hook, measuring
1 skilled labour and 1 labour Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
timber 2 labour Nail, hammer
hardwood timber 1 carpenter Nail, hammer,screwdriver
harwood timber, key lock 2 labour Nail, hammer,screwdriver
stainless steel
timber 2 labour Nail, hammer
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver

plasterboard 1 skilled labour plasterboard lifter, hoist, trolley,


screwdriver,sander
silicon sealant 2 labour Sealant finishers and sealant gun

Cement, paint 1 skilled labour Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Cement, paint 1 skilled worker Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Sanitary item 1 skilled labour screwdriver

cement, tile 1 skilled labour level screed, tile trowler, grout saws

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

PVC pipes, Manhole 2 labour Pressure gauge, Flow meter


Cover, Cement

Cement Board (panel) 2 labour Hammer drill, Power saw, screws

Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Drywall mud 1 labour Trowels, Mud Pans

Cement, floor hardener 2 labour Trowels, Wheelbarrows,

Gate panels, frame, 1 operator, 2 labour Post hole digger, backhoe


hinges, handles,
Turf/Sod, gate
Fertilizer 2 labour Wheelbarrow, Rake
stops

- 2 labour Lorry/Truck

- 1 operator, 2 labour Vibratory Hammer


- 1 operator, 2 labour Vibratory Hammer
- 1 operator, 2 labour Vibratory Hammer
- 2 labour (welder) Welding Machine
- 1 operator, 1 labor Jack Hammer or Circular Saw
- 1 operator, 2 labour Drop hammer
Document 1 labour -

- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement, Anti-Termite 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Treatment
plolyethylene DPM 2 labour Wheelbarrow
Trowel, scrapper
Plywood Formwork 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
agrregate 2 labour Shovel
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow

Plywood 2 labour Nail, hammer


Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow

Roof truss 3 labours Nail, hammer

Roof covering 2 skilled labours Nail, hammer, screwdiver


Rainwater gutter and 1 skilled labour Nail, hammer, screwdiver
goods

Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp
- proof course (helper)
Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp proof course (helper)
Plywood 1 operator, 1 skilled labour Nail, hammer
Rebar End plier's cutter, chain block, stell
Cement 1 skilled labour and 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 2 labour End plier's cutter, chain block, stell
Cement hook, measuring
1 skilled labour and 1 labour Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
timber 2 labour Nail, hammer
hardwood timber 1 carpenter Nail, hammer,screwdriver
harwood timber, key lock 2 labour Nail, hammer,screwdriver
stainless steel
timber 2 labour Nail, hammer
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver

plasterboard 1 skilled labour plasterboard lifter, hoist, trolley,


silicon sealant 2 labour screwdriver,sander
Sealant finishers and sealant gun

Cement, paint 1 skilled labour Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Cement, paint 1 skilled worker Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Sanitary item 1 skilled labour screwdriver

cement, tile 1 skilled labour level screed, tile trowler, grout saws

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

PVC pipes, Manhole 2 labour Pressure gauge, Flow meter


Cover, Cement
Cement Board (panel) 2 labour Hammer drill, Power saw, screws

Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Drywall mud 1 labour Trowels, Mud Pans

Cement, floor hardener 2 labour Trowels, Wheelbarrows,

Gate panels, frame, 1 operator, 2 labour Post hole digger, backhoe


hinges, handles,
Turf/Sod, gate
Fertilizer 2 labour Wheelbarrow, Rake
stops

- 2 labour Lorry/Truck

- 1 operator, 2 labour Vibratory Hammer


- 1 operator, 2 labour Vibratory Hammer
- 1 operator, 2 labour Vibratory Hammer
- 2 labour (welder) Welding Machine
- 1 operator, 1 labor Jack Hammer or Circular Saw
- 1 operator, 2 labour Drop hammer
Document 1 labour -

- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
Wheelbarrow
- 1 Operator Excavator
Cement, Anti-Termite 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Treatment
plolyethylene DPM 2 labour Wheelbarrow
Trowel, scrapper
Plywood Formwork 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
hook, measuring tape,
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Wheelbarrow
- 1 Operator Excavator
agrregate 2 labour Shovel
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel,
Plywood Formwork 2 labour Wheelbarrow
Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, steel
Cement 1 Operator, 2 labour hook, measuring
Concrete tape, Shovel,
Mixer Truck,
- 2 labour Wheelbarrow
Hammer

Plywood 2 labour Nail, hammer


Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 1 labour (bender) End plier's cutter, chain block, stell
Cement 1 operator, 2 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
wheelbarrow

Roof truss 3 labours Nail, hammer

Roof covering 2 skilled labours Nail, hammer, screwdiver

Rainwater gutter and 1 skilled labour Nail, hammer, screwdiver


goods

Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp
- proof course (helper)
Brick, mortar and DPC 1 skilled labour and 2 labour Trowel,brick hammer
damp proof course (helper)
Plywood 1 operator, 1 skilled labour Nail, hammer
Rebar End plier's cutter, chain block, stell
Cement hook, measuring
1 skilled labour and 2 labour Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
Plywood 2 labour Nail, hammer
Rebar 2 labour End plier's cutter, chain block, stell
Cement 1 skilled labour and 1 labour hook, measuring
Concrete tape shovel,
Mixer Truck,
(helper) wheelbarrow
timber 2 labour Nail, hammer
hardwood timber 1 carpenter Nail, hammer,screwdriver
harwood timber, key lock 2 labour Nail, hammer,screwdriver
stainless steel
timber 2 labour Nail, hammer
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver

plasterboard 1 skilled labour plasterboard lifter, hoist, trolley,


silicon sealant 2 labour screwdriver,sander
Sealant finishers and sealant gun

Cement, paint 1 skilled labour Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Cement, paint 1 skilled worker Trowel,scraper, paint brush


cement, tile 2 labour level screed, tile trowler, grout saws

Sanitary item 1 skilled labour screwdriver

cement, tile 1 skilled labour level screed, tile trowler, grout saws

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel

PVC pipes, Manhole 2 labour Pressure gauge, Flow meter


Cover, Cement

Cement Board (panel) 2 labour Hammer drill, Power saw, screws

Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Drywall mud 1 labour Trowels, Mud Pans

Cement, floor hardener 2 labour Trowels, Wheelbarrows,

Gate panels, frame, 1 operator, 2 labour Post hole digger, backhoe


hinges, handles,
Turf/Sod, gate
Fertilizer 2 labour Wheelbarrow, Rake
stops
- - -
Duration
-
20 days
5 days
10 days
5 days
5 days
5 days
7 days
10 days
10 days
10 days
10 days
10 days
10 days
5 days
10 days
5 days
10 days
10 days
5 days
35 days
35 days
2 days
35 days
5 days
30 days
30 days
30 days
5 days
35 days
35 days
30 days
30 days
12 days
7 days
5 days
3 days
7 days
7 days
5 days
8 days?
10 days
3 days
7 days
7 days
5 days
8 days
5 days
5 days
8 days
8 days
4 days
12 days
5 days
7 days
2 days
5 days
12 days
8 days
7 days
5 days
3 days
5 days
7 days
7 days
5 days
21 days
14 days
9 days
14 days
9 days
21 days
21 days
14 days
9 days
14 days
14 days
14 days
9 days
14 days
14 days
14 days
14 days
14 days
7 days
7 days
21 days
18 days
18 days
18 days
14 days
14 days
3 days
3 days
3 days
3 days
5 days
5 days
5 days
5 days
21 days
4 days
7 days
21 days
7 days
4 days
7 days
14 days
7 days
7 days
4 days
14 days
14 days
11 days
7 days
7 days
5 days
7 days
7 days
14 days
14 days
30 days
21 days
18 days
18 days
21 days
21 days
21 days
21 days
30 days
30 days
14 days
7 days
7 days
14 days
14 days
7 days
14 days
14 days
7 days
7 days
14 days
35 days
35 days
2 days
35 days
5 days
30 days
30 days
30 days
5 days
35 days
35 days
30 days?
30 days?
12 days?
7 days
5 days
3 days
7 days
7 days
5 days
8 days?
10 days
3 days
7 days
7 days
5 days
8 days
5 days
5 days
8 days
8 days
4 days
12 days
5 days
7 days
2 days
5 days
12 days
8 days
7 days
5 days
3 days
5 days
7 days
7 days
5 days
21 days
14 days
9 days
14 days
9 days
21 days
21 days
14 days
9 days
14 days
14 days
14 days
9 days
30 days
14 days
14 days
14 days
14 days
30 days
30 days
21 days
18 days
18 days
18 days
14 days
14 days
3 days
3 days
3 days
3 days
5 days
5 days
5 days
5 days
21 days
4 days
7 days
21 days
7 days
4 days
7 days
14 days
7 days
7 days
4 days
14 days
14 days
11 days
7 days
7 days
5 days
7 days
7 days
14 days
14 days
30 days
21 days
18 days
18 days
21 days
21 days
21 days
21 days
30 days
30 days
14 days
7 days
7 days
14 days
14 days
7 days
14 days
14 days
7 days
7 days
14 days
45 days
35 days
3 days
35 days
8 days
30 days
30 days
30 days
8 days
35 days
35 days
45 days?
45 days?
18 days?
11 days
8 days
5 days
11 days
11 days
8 days
8 days?
15 days
5 days
11 days
11 days
8 days
12 days
8 days
8 days
12 days
12 days
8 days
12 days
5 days
7 days
2 days
5 days
12 days
8 days
7 days
5 days
3 days
5 days
7 days
7 days
5 days
25 days
18 days
14 days
18 days
14 days
25 days
25 days
20 days
14 days
25 days
25 days
20 days
14 days
30 days
14 days
16 days
14 days
16 days
30 days
35 days
25 days
25 days
25 days
25 days
20 days
20 days
5 days
5 days
5 days
5 days
10 days
10 days
10 days
10 days
21 days
6 days
11 days
21 days
15 days
6 days
15 days
20 days
11 days
11 days
6 days
20 days
20 days
15 days
11 days
11 days
8 days
11 days
11 days
20 days
20 days
30 days
30 days
25 days
25 days
30 days
30 days
30 days
30 days
30 days
30 days
20 days
11 days
11 days
20 days
20 days
11 days
20 days
20 days
11 days
11 days
20 days
45 days?
35 days
3 days
35 days
8 days
30 days
30 days
30 days
8 days
35 days
35 days
45 days
45 days
18 days
11 days
8 days
5 days
11 days
11 days
8 days
8 days
15 days
5 days
11 days
11 days
8 days
12 days
8 days
8 days
12 days
12 days
8 days
12 days
5 days
7 days
2 days
5 days
12 days
8 days
7 days
5 days
3 days
5 days
7 days
7 days
5 days
25 days
18 days
14 days
18 days
14 days
25 days
25 days
20 days
14 days
25 days
25 days
20 days
14 days
30 days
14 days
16 days
14 days
16 days
30 days
35 days
25 days
25 days
25 days
25 days
20 days
20 days
5 days
5 days
5 days
5 days
10 days
10 days
10 days
10 days
21 days
6 days
11 days
21 days
15 days
6 days
15 days
20 days
11 days
11 days
6 days
20 days
20 days
15 days
11 days
11 days
8 days
11 days
11 days
20 days
20 days
30 days
30 days
25 days
25 days
30 days
30 days
30 days
30 days
30 days
30 days
20 days
11 days
11 days
20 days
20 days
11 days
20 days
20 days
11 days
11 days
20 days
35 days
35 days
3 days
35 days
6 days
30 days
30 days
30 days
6 days
35 days
35 days
30 days?
30 days?
12 days?
7 days
6 days
4 days
8 days
8 days
6 days
8 days?
12 days
4 days
8 days
8 days
6 days
8 days
6 days
6 days
9 days
9 days
5 days
12 days
5 days
7 days
2 days
5 days
12 days
8 days
7 days
5 days
3 days
5 days
7 days
7 days
5 days
21 days
14 days
11 days
16 days
11 days
21 days
25 days
16 days
11 days
14 days
16 days
16 days
11 days
30 days
14 days
16 days
14 days
16 days
30 days
35 days
21 days
18 days
18 days
21 days
14 days
16 days
3 days
4 days
4 days
4 days
5 days
6 days
6 days
6 days
21 days
5 days
8 days
25 days
7 days
5 days
8 days
14 days
7 days
8 days
5 days
14 days
16 days
13 days
7 days
8 days
6 days
7 days
8 days
14 days
16 days
30 days
21 days
18 days
20 days
21 days
25 days
21 days
25 days
30 days
35 days
14 days
7 days
8 days
14 days
16 days
9 days
14 days
16 days
7 days
8 days
16 days
35 days
35 days
3 days
35 days
6 days
30 days
30 days
30 days
6 days
35 days
35 days
30 days
30 days
12 days
7 days
6 days
4 days
8 days
8 days
6 days
8 days?
12 days
4 days
8 days
8 days
6 days
8 days
6 days
6 days
9 days
9 days
5 days
12 days
5 days
7 days
2 days
5 days
12 days
8 days
7 days
5 days
3 days
5 days
7 days
7 days
5 days
21 days
14 days
11 days
16 days
11 days
21 days
25 days
16 days
11 days
14 days
16 days
16 days
11 days
30 days
14 days
16 days
14 days
16 days
30 days
35 days
21 days
18 days
18 days
21 days
14 days
16 days
3 days
4 days
4 days
4 days
5 days
6 days
6 days
6 days
21 days
5 days
8 days
25 days
7 days
5 days
8 days
14 days
7 days
8 days
5 days
14 days
16 days
13 days
7 days
8 days
6 days
7 days
8 days
14 days
16 days
30 days
21 days
18 days
20 days
21 days
25 days
21 days
25 days
30 days
35 days
14 days
7 days
8 days
14 days
16 days
9 days
14 days
16 days
7 days
8 days
16 days
1 day
TASK NAME COST Materials Labour Machinaries/ Equipment Duration

Reinforced concrete counter top RM 7,560.00 5 days


Plywood 2 labour Nail, hammer
Install formwork RM 2,520.00 6 days
Rebar 2 labour End plier's cutter, chain block, stell hook, measuring tape
Install bar reinforcement RM 2,520.00 6 days
Cement 1 skilled labour and 1 labour (helper) Concrete Mixer Truck, shovel, wheelbarrow
Concreting RM 2,520.00 6 days

Door RM 105,688.00 21 days


timber 2 labour Nail, hammer
Installation of lintol RM 12,560.00 5 days
hardwood timber 1 carpenter Nail, hammer,screwdriver
Supply and install door frame RM 15,750.00 8 days
harwood timber, key lock stainless steel 2 labour Nail, hammer,screwdriver
Supply and install door including lockset RM 77,378.00 25 days

Window RM 72,384.00 7 days


timber 2 labour Nail, hammer
Installation of lintol RM 4,560.00 5 days
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver
Supply and install windows c/w accessories RM 67,824.00 8 days

Internal Finishes RM 522,790.20 14 days

Internal Ceiling Finishes RM 55,487.20 7 days


plasterboard 1 skilled labour plasterboard lifter, hoist, trolley, screwdriver,sander
Installing plasterboard RM 34,331.20 8 days
silicon sealant 2 labour Sealant finishers and sealant gun
Apply sealant RM 21,156.00 5 days

Internal Wall Finishes including wall niche RM 244,784.80 14 days


Cement, paint 1 skilled labour Trowel,scraper, paint brush
Plastering and painting RM 185,762.20 16 days
cement, tile 2 labour level screed, tile trowler, grout saws
Screeding and tiling RM 59,022.60 13 days

Reinforced concrete counter top RM 5,040.00 7 days


Cement, paint 1 skilled worker Trowel,scraper, paint brush
Plastering and painting RM 2,520.00 8 days
cement, tile 2 labour level screed, tile trowler, grout saws
Screeding and tiling RM 2,520.00 6 days

Sanitary Appliances RM 84,817.60 7 days


Sanitary item 1 skilled labour screwdriver
Install sanitary appliances RM 84,817.60 8 days

Internal Floor Finishes RM 132,660.60 14 days


cement, tile 1 skilled labour level screed, tile trowler, grout saws
Screeding and tiling RM 132,660.60 16 days

EXTERNAL WORKS WITHIN BOUNDARY RM 273,290.80 30 days

Bricklaying RM 115,682.97 21 days

Fencing RM 62,287.75 18 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 62,287.75 20 days

SESCO Compartment RM 16,936.96 21 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 16,936.96 25 days

Refuse Chamber & Mailbox Compartment RM 36,458.26 21 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 36,458.26 25 days

Sump, manhole & drainage system RM 23,250.79 30 days


PVC pipes, Manhole Cover, Cement 2 labour Pressure gauge, Flow meter
Sump, manhole and pipes installation with allowance for testing RM 23,250.79 35 days

External Finishes RM 108,663.10 14 days

External Ceiling Finishes RM 11,593.40 7 days


Cement Board (panel) 2 labour Hammer drill, Power saw, screws
Install cement board RM 11,593.40 8 days

External Wall Finishes RM 78,890.50 14 days


Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Plastering and painting RM 57,674.50 16 days
Drywall mud 1 labour Trowels, Mud Pans
Apply skim coat RM 21,216.00 9 days

External Floor Finishes RM 18,179.20 14 days


Cement, floor hardener 2 labour Trowels, Wheelbarrows,
Pave cement-sand trowel finish with floor hardener RM 18,179.20 16 days

Gates RM 23,406.09 7 days


Gate panels, frame, hinges, handles, 1 operator, 2 labour Post hole digger, backhoe
gate stops
Supply and install gates RM 23,406.09 8 days
Turf/Sod, Fertilizer 2 labour Wheelbarrow, Rake
Spot Turfing RM 2,287.85 16 days
Handover
RM 0.00 - - - 1 day