TASK NAME COST Materials Labour Machinaries/ Equipment Duration

EXTERNAL WORKS WITHIN BOUNDARY RM 235,509.15 30 days

Bricklaying RM 99,156.84 21 days

Fencing RM 53,389.50 18 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 53,389.50 18 days

SESCO Compartment RM 14,517.40 21 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 14,517.40 21 days

Refuse Chamber & Mailbox Compartment RM 31,249.94 21 days


Bricks, Mortar, Rebar 2 labour (bricklayer) Brick Saw, Wheelbarrow, Shovel
Bricklaying including reinforcement RM 31,249.94 21 days

Sump, manhole & drainage system RM 19,929.25 30 days


PVC pipes, Manhole Cover, Cement 2 labour Pressure gauge, Flow meter
Sump, manhole and pipes installation with allowance for testing RM 19,929.25 30 days

External Finishes RM 94,399.68 14 days

External Ceiling Finishes RM 10,207.60 7 days


Cement Board (panel) 2 labour Hammer drill, Power saw, screws
Install cement board RM 10,207.60 7 days

External Wall Finishes RM 68,140.88 14 days


Plaster, Primer, Paint 2 labour (painter, plasterer) Trowels, Brushes, Rollers, Paint trays
Plastering and painting RM 49,784.88 14 days
Drywall mud 1 labour Trowels, Mud Pans
Apply skim coat RM 18,356.00 7 days

External Floor Finishes RM 16,051.20 14 days


Cement, floor hardener 2 labour Trowels, Wheelbarrows,
Pave cement-sand trowel finish with floor hardener RM 16,051.20 14 days

Gates RM 20,062.36 7 days


Gate panels, frame, hinges, handles, gate 1 operator, 2 labour Post hole digger, backhoe
Supply and install gates RM 20,062.36 stops 7 days
Turf/Sod, Fertilizer 2 labor Wheelbarrow, Rake
Spot Turfing RM 1,961.02 14 days

PLOT C (2 CORNER UNITS, 14 INTERMEDIATE UNITS, 2 END UNITS) RM 3,169,252.53 45 days

PILING WORKS RM 216,143.02 35 days


- 2 labour Lorry/Truck
Mobilisation of piling equipment RM 3,886.36 3 days

Precast Concrete Square Piles RM 212,052.11 35 days


- 1 operator, 2 labour Vibratory Hammer
Supply and deliver initial and extension piles RM 160,185.60 8 days
- 1 operator, 2 labour Vibratory Hammer
Handle, transport and pitch into driving position for initial and extension piles RM 4,536.00 30 days
- 1 operator, 2 labour Vibratory Hammer
Driving pile RM 28,771.20 30 days
- 2 labour (welder) Welding Machine
Butt weld connection RM 12,960.00 30 days
- 1 operator, 1 labor Jack Hammer or Circular Saw
Cutting-Off Piles RM 3,758.40 8 days
- 1 operator, 2 labour Drop hammer
Testing pile RM 1,840.91 35 days
Document 1 labour -
Piling Records RM 204.55 35 days

BUILDING WORKS RM 2,604,255.40 45 days

SUBSTRUCTURE & SUPERSTRUCTURE RM 1,314,601.40 45 days

WBLFF RM 595,730.40 18 days

Pile Cap RM 68,647.80 11 days


- 1 Operator Excavator
Excavation RM 1,069.20 8 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Pour lean concrete RM 860.20 5 days
Plywood Formwork 2 labour Nail, hammer
Install formwork RM 19,437.60 11 days
Rebar 1 labour (bender) End plier's cutter, chain block, steel hook, measuring tape,
Install bar reinforcement RM 19,280.80 11 days
Cement 1 Operator, 2 labour Concrete Mixer Truck, Shovel, Wheelbarrow
Concreting RM 28,000.00 8 days