TASK NAME COST Materials Labour Machinaries/ Equipment Duration

ROOF CONSTRUCTION RM 321,782.80 14 days

Roof Truss RM 59,400.00 14 days


Roof truss 3 labours Nail, hammer
Install roof truss c/w accessories RM 59,400.00 14 days

Roof Covering RM 198,611.20 14 days


Roof covering 2 skilled labours Nail, hammer, screwdiver
Install roof covering c/w accessories RM 198,611.20 14 days

Rainwater Gutter and Goods RM 63,771.60 7 days


Rainwater gutter and goods 1 skilled labour Nail, hammer, screwdiver
Install rainwater gutter and goods c/w accessories RM 63,771.60 7 days

ARCHITECTURAL WORKS RM 873,119.20 21 days

Bricklaying RM 253,001.20 18 days

External Wall RM 126,388.00 18 days


Brick, mortar and DPC damp proof course 1 skilled labour and 2 labour (helper) Trowel,brick hammer
Bricklaying including DPC RM 126,388.00 18 days
-
Internal Wall RM 126,613.20 14 days
Brick, mortar and DPC damp proof course 1 skilled labour and 2 labour (helper) Trowel,brick hammer
Bricklaying including DPC RM 126,613.20 14 days

Shower wall niche RM 7,200.00 3 days


Plywood 1 operator, 1 skilled labour Nail, Hammer
Install formwork RM 2,400.00 3 days
Rebar 1 skilled labour and 2 labour (helper) End plier's cutter, chain block, stell hook, measuring tape
Install bar reinforcement RM 2,400.00 3 days
Cement 1 skilled labour and 2 labour (helper) Concrete Mixer Truck, shovel, wheelbarrow
Concreting RM 2,400.00 3 days

Reinforced concrete counter top RM 6,480.00 5 days


Plywood 1 skilled labour and 1 labour (helper) Nail, hammer
Install formwork RM 2,160.00 5 days
Rebar 2 skilled labour End plier's cutter, chain block, stell hook, measuring tape
Install bar reinforcement RM 2,160.00 5 days
Cement 2 general worker Concrete Mixer Truck, shovel, wheelbarrow
Concreting RM 2,160.00 5 days
-
Door RM 90,704.00 21 days
timber 2 labour Nail, hammer
Installation of lintol RM 10,880.00 4 days
hardwood timber 1 carpenter Nail, hammer,screwdriver
Supply and install door frame RM 13,500.00 7 days
harwood timber, key lock stainless steel 2 labour Nail, hammer,screwdriver
Supply and install door including lockset RM 66,324.00 21 days

Window RM 63,184.00 7 days


timber 2 labour Nail, hammer
Installation of lintol RM 4,000.00 4 days
hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver
Supply and install windows c/w accessories RM 59,184.00 7 days

Internal Finishes RM 452,550.00 14 days

Internal Ceiling Finishes RM 48,263.20 7 days


plasterboard 1 skilled labour plasterboard lifter, hoist, trolley, screwdriver,sander
Installing plasterboard RM 29,859.20 7 days
silicon sealant 2 labour Sealant finishers and sealant gun
Apply sealant RM 18,404.00 4 days

Internal Wall Finishes including wall niche RM 211,052.40 14 days


Cement, paint 1 skilled labour Trowel,scraper, paint brush
Plastering and painting RM 160,461.60 14 days
cement, tile 2 labour level screed, tile trowler, grout saws
Screeding and tiling RM 50,590.80 11 days

Reinforced concrete counter top RM 4,320.00 7 days


Cement, paint 1 skilled worker Trowel,scraper, paint brush
Plastering and painting RM 2,160.00 7 days
cement, tile 2 labour level screed, tile trowler, grout saws
Screeding and tiling RM 2,160.00 5 days

Sanitary Appliances RM 72,900.80 7 days


sanitary item 1 skilled labour screwdriver
Install sanitary appliances RM 72,900.80 7 days

Internal Floor Finishes RM 116,013.60 14 days


cement, tile 2 skilled labour level screed, tile trowler, grout saws
Screeding and tiling RM 116,013.60 14 days