Rainwater gutter and goods 1 skilled labour Nail, hammer, screwdiver Install rainwater gutter and goods c/w accessories RM 63,771.60 7 days
ARCHITECTURAL WORKS RM 873,119.20 21 days
Bricklaying RM 253,001.20 18 days
External Wall RM 126,388.00 18 days
Brick, mortar and DPC damp proof course 1 skilled labour and 2 labour (helper) Trowel,brick hammer Bricklaying including DPC RM 126,388.00 18 days - Internal Wall RM 126,613.20 14 days Brick, mortar and DPC damp proof course 1 skilled labour and 2 labour (helper) Trowel,brick hammer Bricklaying including DPC RM 126,613.20 14 days
Shower wall niche RM 7,200.00 3 days
Plywood 1 operator, 1 skilled labour Nail, Hammer Install formwork RM 2,400.00 3 days Rebar 1 skilled labour and 2 labour (helper) End plier's cutter, chain block, stell hook, measuring tape Install bar reinforcement RM 2,400.00 3 days Cement 1 skilled labour and 2 labour (helper) Concrete Mixer Truck, shovel, wheelbarrow Concreting RM 2,400.00 3 days
Reinforced concrete counter top RM 6,480.00 5 days
Plywood 1 skilled labour and 1 labour (helper) Nail, hammer Install formwork RM 2,160.00 5 days Rebar 2 skilled labour End plier's cutter, chain block, stell hook, measuring tape Install bar reinforcement RM 2,160.00 5 days Cement 2 general worker Concrete Mixer Truck, shovel, wheelbarrow Concreting RM 2,160.00 5 days - Door RM 90,704.00 21 days timber 2 labour Nail, hammer Installation of lintol RM 10,880.00 4 days hardwood timber 1 carpenter Nail, hammer,screwdriver Supply and install door frame RM 13,500.00 7 days harwood timber, key lock stainless steel 2 labour Nail, hammer,screwdriver Supply and install door including lockset RM 66,324.00 21 days
Window RM 63,184.00 7 days
timber 2 labour Nail, hammer Installation of lintol RM 4,000.00 4 days hardwood timber 1 skilled labour (carpenter) Nail, hammer,screwdriver Supply and install windows c/w accessories RM 59,184.00 7 days
Internal Finishes RM 452,550.00 14 days
Internal Ceiling Finishes RM 48,263.20 7 days
plasterboard 1 skilled labour plasterboard lifter, hoist, trolley, screwdriver,sander Installing plasterboard RM 29,859.20 7 days silicon sealant 2 labour Sealant finishers and sealant gun Apply sealant RM 18,404.00 4 days
Internal Wall Finishes including wall niche RM 211,052.40 14 days
Cement, paint 1 skilled labour Trowel,scraper, paint brush Plastering and painting RM 160,461.60 14 days cement, tile 2 labour level screed, tile trowler, grout saws Screeding and tiling RM 50,590.80 11 days
Reinforced concrete counter top RM 4,320.00 7 days
Cement, paint 1 skilled worker Trowel,scraper, paint brush Plastering and painting RM 2,160.00 7 days cement, tile 2 labour level screed, tile trowler, grout saws Screeding and tiling RM 2,160.00 5 days
Sanitary Appliances RM 72,900.80 7 days
sanitary item 1 skilled labour screwdriver Install sanitary appliances RM 72,900.80 7 days
Internal Floor Finishes RM 116,013.60 14 days
cement, tile 2 skilled labour level screed, tile trowler, grout saws Screeding and tiling RM 116,013.60 14 days