The B2 ground floor lobby walls and parts of the ceiling are again getting damp although it did not rain much in
the last couple of months. Is there an issue getting this fixed permanently?
Also, till now (after more than a year), there is no major work done to get the boundary walls fully repaired. Was
your construction team able to suggest anything till now or the research and development is still going on?
Refer point number 5 in the trail email.
Further, I am seeing a wooden rack and other stuffs being kept near the sitting area of the lobby boys. Could
you please work to have these things placed properly so that it looks good because currently the look and feel
is very odd and many visitors have pointed it out. I leave this to suggestions and feedback from other residents.
May be you can get closed cupboards (with doors) which would look neat and clean.
Atul
With reference to our discussion, we will repair the lobby area by tomorrow evening and for the boundary wall, we will
plan as per your suggestions.
Sandeep Kumar
Asst. Manager (Estate)
Ashiana Anmol, Gurgaon
7230014623
Hi Team,
Following up again on point number 5 as per the trail email. Though the patch in B2 lobby was fixed, again a new crack
got developed above the ground floor staircase.
Also, it's close to a year now. Any plans to repair the boundary wall? If yes, provide a definite timeline within which it
will be done, get it repaired and confirm.
Ideally, these things should be automatically taken care by your team present here. Not sure what is the reason for them
being reactive wherein they should be proactively identifying issues (if any), keep asking for regular feedbacks from
residents and provide resolution on a fasttrack basis.
Regards,
Atul
Thank you for your responses to some of the questions. There are more specific queries and asks in a couple of
emails. Can someone address those too.
Accordingly, I will go through all the responses I one go and come back with my comments/suggestions/inputs.
Regards,
Atul
Dear Sir,
Kindly find the reply to your concerns raised in several mails. Pointwise reply is mentioned in blue color.
Dear Sir,
We are in receipt of multiple emails with your concerns.
These will be discussed with the senior team and we will revert by 21st Jun.
regards,
Vivek
Hi Team,
Since yesterday Ashiana security guard is stopping small kids to play in the park area with their balls.
This unwanted behavior should stop with immediate effect and without any negotiation.
The argument which they are giving is that people are getting hurt while kids are playing with their balls. This is
totally unacceptable. How can small kids hurt others or elders?
Example - So many accidents happens on the road on daily basis. So, the government should stop allowing people
to ride their vehicles for prevention of accidents as a permanent solution.
Please look into this and request you to strongly advise the maintenance team not to force their random self-
crafted rules on residents, especially kids.
Suresh - Humble request: As a maintenance manager, you should concentrate in maintaining the society and not
making rules for the residents here. There are many areas where you and your team is lacking to maintain the
society proactively. It would be great if you can focus on that.
Regards,
Atul
Dear Sir,
There was a seepage in Tower-2 lobby area during the rain. We have rectified the root cause of the seepage and were
waiting till walls get dry. painting wark took place in next 2-3 days.
Boundary wall repair and painting work will take place next month.
We placed the wooden rack near the sitting area of the lobby boy as CCTV is covering this location. Some residents were
keeping their couriers and other stuff here.
Sandeep Kumar
Asst. Manager (Estate)
Ashiana Anmol, Gurgaon
7230014623
The repair and painting work of the boundary wall is due this month.
Regards,
Atul
[Quoted text hidden]
Mr. Abhijit,
You have a wonderful team which utilize their time to direct flat owners/residents of Ashiana Anmol society to
follow processes.
It would be great if you can deep dive into the long pending issues and resolve them at the earliest without fail.
See below an example of some great accomplishment of.your on-ground team - The boundary wall repair is still
pending. This request is about two years old and it was agreed to complete this by Sept. 2023.
Not sure if it's true however, it has been brought to my notice that some of the maintenance work remains
pending for long due to slow approval process of senior management. Something to introspect and to be
discussed with your peers internally.
Regards,
Atul
[Quoted text hidden]
Hi All,
As per the below email chain, the maintenance agency of our society Ashiana Maintenance Service LLP has not
taken up the repair of the boundary wall till date. Wanted to check with the learned residents of our society if
there is a better way out to get this done. Your thoughts and suggestions along with some concrete relevant
actions will help in getting through here.
I am also looping the Ashiana Anmol Owners Association (AAOA) governing body and the National Consumer
Helpline email Id' s for their guidance too.
Thanking in advance for your support, due diligence and required action.
Regards,
Atul
[Quoted text hidden]
Dear all
As per.maintenancr agreement all such repairs needs to be taken care by AML only
Thanks
[Quoted text hidden]
Thanks
[Quoted text hidden]
Thank you for contacting the Consumer Helpline. In case you wish to register a grievance, please call the
National Consumer Helpline Toll free number 1800-11-4000 or 1915 or send SMS to 8800001915. You may also
register your grievance on www.consumerhelpline.gov.in or on NCH App or UMANG App.