Details M T W T F S S
0 Small Building Construction
90 days76 days Mon 15/07/24 Work
Mon 15/04/24 1d 1d 1d 1d 1d 1d
1 Excavate 5 days5 days Mon 15/04/24 Fri 19/04/24 Work 1d 1d 1d 1d 1d
Project Manager 5 days Mon 15/04/24 Fri 19/04/24 Work 1d 1d 1d 1d 1d
2 Lay foundation 8 days8 days Sat 20/04/24Mon 29/04/24 Work 1d
Engineer 8 days Sat 20/04/24Mon 29/04/24 Work 1d
3 Rough Plumbing 5 days5 days Tue 30/04/24Mon 06/05/24 Work
Foreman 5 days Tue 30/04/24Mon 06/05/24 Work
4 Frame 10 days10 days Tue 30/04/24 Sat 11/05/24 Work
Skilled Laborer 1 10 days Tue 30/04/24 Sat 11/05/24 Work
5 Finish Exterior 8 days8 days Mon 13/05/24 Tue 21/05/24 Work
Skilled Laborer 2 8 days Mon 13/05/24 Tue 21/05/24 Work
6 Install HVAC 4 days4 days Mon 13/05/24 Thu 16/05/24 Work
Skilled Laborer 3 4 days Mon 13/05/24 Thu 16/05/24 Work
7 Rough Electric 6 days6 days Mon 13/05/24 Sat 18/05/24 Work
Skilled Laborer 4 6 days Mon 13/05/24 Sat 18/05/24 Work
8 Sheet Rock 8 days8 days Wed 22/05/24 Thu 30/05/24 Work
Unskilled Laborer 1 8 days Wed 22/05/24 Thu 30/05/24 Work
9 Install cabinets 11 days11 days Fri 31/05/24 Thu 13/06/24 Work
Unskilled Laborer 2 11 days Fri 31/05/24 Thu 13/06/24 Work
10 Paint 10 days10 days Fri 31/05/24 Tue 11/06/24 Work
Unskilled Laborer 3 10 days Fri 31/05/24 Tue 11/06/24 Work
11 Final Plumbing 4 days4 days Fri 14/06/24 Tue 18/06/24 Work
Unskilled Laborer 4 4 days Fri 14/06/24 Tue 18/06/24 Work
12 Final Electric 4 days4 days Thu 13/06/24Mon 17/06/24 Work
Unskilled Laborer 5 4 days Thu 13/06/24Mon 17/06/24 Work
13 Install Flooring 7 days7 days Wed 19/06/24Wed 26/06/24 Work
Unskilled Laborer 6 7 days Wed 19/06/24Wed 26/06/24 Work
14 FINISH 0 days0 days Mon 15/07/24Mon 15/07/24 Work