You are on page 1of 3

Block - 9 KEBL Contractor

Log
TQ No.: BK91-1344-INF-ELE-
Rev.: A Page 1 / 2
TQY-0001
Technical Query
( x Clarification Deviation Note1)

Note 1: if this Technical Query is only related clarification topic, it’s reviewed and approved by PMC only. If it’s
Deviation related topic, thus PMT needs to acknowledge.

Contractor : ADHWAA AL-AWAS COMPANY Contract No : LK9/IRQ-


SF- CON-
1014
Project PRID :
To : KEBL Block-9, Surface Facilities Project Title : EPC for New Fire
Training Ground & Props
Initiation Date : 22nd Mar 2024 Issue Date : 8 th April 2024
Reference : Electrical Design Documents
Subject : Power Source Change Due to Voltage Drop

CONTRACTOR
Description: (include any Safety or Environmental Impact)

Reference to voltage drop calculation for the fire training ground project, EPC has found that
the current voltage drops for the main cable feeder 4C x 185mm2, as following:

VD Calculation total 7.25%


Voltage Cable Max Value
No. From To
(V) Size(mm2) Length(m) %
Fire Station 2x4x
1 SS06 400 160 1.10
Building 185mm2
Fire Station Fire Area Training 1x
2 400 900 4.86
Building Ground 185mm2
Final Load (e.g.
Fire Area
3 4x16mm2 for 230 5 x 16mm2 230 1.29
Training Ground
Lighting)

EPC have taken further steps to calculate the voltage drop if the upgrade option can be
considered to cable size to be 4C x 240mm2, and got the following results:

VD Calculation total 6.3%


Cable Max Value
No. From To Voltage (V)
Size(mm2) Length(m) %
Fire Station 2x4x
1 SS06 400 160 1.10
Building 185mm2
Fire Station Fire Area 1x
2 400 900 3.91
Building Training Ground 240mm2
3 Fire Area Final Load (e.g. 230 5 x 16mm2 230 1.29
Training Ground 4x16mm2 for

Document No. BK91-1000-000-GEN-TMP-0001 (Rev.5, Issued date: 17th-Oct-2023)


Lighting)

In both cases, and even with considering various optimizations for routes and internal
voltage drop within the ground itself, the two results conflicted with the Vendor of the Fire
area ground Probs power supply requirements.

Affected Disciplines:
HSE Process Plot Plan Mechanical Instrument x Electrical Piping Civil/Structure

CP PPL HVAC Telecommunication QAC CNS Material

Affected Document/Drawing: (Attached Mark-Up Document/Drawing)

Recommended Solution:

EPC recommended using a redundancy diesel generator at the field, this shall cover the
required kW for the project and limit the voltage drop.

The Diesel Generators power supply system shall consist of the following items:
 One (1) Continuous and One (1) Standby Diesel Generators, in total Two (2) Gen
with sufficient capacity to cover the project requirements with 20% of Spare KVA
while considering all the power factors and other losses.
 One (1) Diesel Tank and filling requirements.
 All Civil Works and Foundations requirements.
 The shelter requirements over the DGs and Tank.
 Fire extinguishers and safety signs.
 Distribution board and electrical system requirements with the required cables to
supply the main ground DB.
 Earthing and Lightning protection systems.

Proposed Location:
We are proposing using the area between the training ground and the east road as this area
is currently not utilized for any purpose while providing accessibility to Diesel tank through
the closest roads to two sides.
Area is also considered close to the ground utility area which will minimize the voltage drop
significantly.

Document No. BK91-1000-000-GEN-TMP-0001 (Rev.5, Issued date: 17th-Oct-2023)


Indicate Potential Impact:
x SOW Change Cost Reduction Cost Increment Schedule Impact Re-Hazop

Originator Construction/Engineering Manager Project Manager


Print Name Ahmed Mudrik Khaleel Almusawi Monthir Salah
Signature
Date 8th April 2024 8th April 2024 8th April 2024

COMPANY RESPONSE
PMC Comment:

Confirm the following:


Description of Change Yes No Description of Change Yes No
Scope of Work Change Cost Increment
Cost Reduction Impact of Schedule
Change Request required Yes No If yes, Implement Change Order Procedure

Proceed with Modification Yes No

Technical Approval Endorsed Acknowledge


PMC PMC
PMC Project
Discipline Engineering PMT EN PMT SH PMT PM
Manager
Engineer Manager
Print Name
Signature
Date

Document No. BK91-1000-000-GEN-TMP-0001 (Rev.5, Issued date: 17th-Oct-2023)

You might also like