# Title Given Given End Predecessors November 2018 December 2018 January 2019 February 2019 March 2019

Given Given End Predecessors November 2018 December 2018 January 2019 February 2019 March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020
Duration WK 48 WK 49 WK 50 WK 51 WK 52 WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10 WK 11 WK 12 WK 13 WK 14 WK 15 WK 16 WK 17 WK 18 WK 19 WK 20 WK 21 WK 22 WK 23 WK 24 WK 25 WK 26 WK 27 WK 28 WK 29 WK 30 WK 31 WK 32 WK 33 WK 34 WK 35 WK 36 WK 37 WK 38 WK 39 WK 40 WK 41 WK 42 WK 43 WK 44 WK 45 WK 46 WK 47 WK 48 WK 49 WK 50 WK 51 WK 52 WK 1
0 GV_GT12_Timeline_20190411 GV_GT12_Timeline_20190411

1 A. Project Development Milestones A. Project Development Milestones

2 A1. MPA approval 27/12/2018 A1. MPA approval

3 A2. Feasibility Study MOIT approval 18/04/2019 2 A2. Feasibility Study MOIT approval

4 A3. Key Agreements with EVN (signing) A3. Key Agreements with EVN (signing)

5 A3.1. Connection Point Agreement with EVN CPC 6 Mar 2019 A3.1. Connection Point Agreement with EVN CPC

6 A3.2. SCADA Agreement with EVN NLDC 17/04/2019 A3.2. SCADA Agreement with EVN NLDC

7 A3.3. Relay Protection Agreement with EVN NLDC 17/04/2019 A3.3. Relay Protection Agreement with EVN NLDC

8 A3.4. Metering System Agreement with EVN EPTC 17/04/2019 A3.4. Metering System Agreement with EVN EPTC

9 A3.5. Translated version of signed agreements 1 week 6; 7; 8 A3.5. Translated version of signed agreements

10 A4. Power Purchase Agreement (PPA) 25/04/2019 2; 3; 4 A4. Power Purchase Agreement (PPA)

11 A5. Investment Registration Certificate A5. Investment Registration Certificate

12 A5.1. Investment Policy Approval 22/02/2019 2 A5.1. Investment Policy Approval

13 A5.2. Deposit to QT department of Planing (0.5% of total investment) (tbd) 10ES+1 week A5.2. Deposit to QT department of Planing (0.5% of t…

14 A5.3. QTP issue Investment Registration Certificate 13ES+1 week A5.3. QTP issue Investment Registration Certificate

15 A6. Project Site Agreements (completed 15.11.2018) 2 A6. Project Site Agreements (completed 15.11.2018)

16 A6.1. Complete land compensation payment (tbd) 10ES+1 week A6.1. Complete land compensation payment (tbd)

17 A6.2. Land Lease Agreement 13; 14; 16ES+2 weeks A6.2. Land Lease Agreement

18 A6.3. Land Use-Right Certificate 13; 14; 16ES+2 weeks A6.3. Land Use-Right Certificate

19 A6.4. Complete land clearance and land mine 4 weeks 16 A6.4. Complete land clearance and land mine

20 A6.5. Ready for Construction 17; 18; 19 A6.5. Ready for Construction

21 A7. Construction Permits A7. Construction Permits

22 A7.1. Construction Permit / approval (LI) 15/05/2019 2 A7.1. Construction Permit / approval (LI)

23 A7.2. Permit for transmission line crossing of communal road from GT2 to GT1 (LI) 54ES+1 week A7.2. Permit for transmission line crossing of commu…

24 A7.3. Electricity Generation License (EPC/LI) 101 A7.3. Electricity Generation License (EPC/LI)

25 A7.4. Approval of Fire Prevention and Fighting (LI) 54ES+1 week A7.4. Approval of Fire Prevention and Fighting (LI)

26 A7.5. Approval of Environmental Impact Assessment (LI) 3 May 2019 3 A7.5. Approval of Environmental Impact Assessment…

27 A7.6. Approval of using water (LI) 54ES+1 week A7.6. Approval of using water (LI)

28 A7.7. Approval of connecting GT1&2 to main road (LI) 15/05/2019 3 A7.7. Approval of connecting GT1&2 to main road (LI)

29 A8. Financial Close A8. Financial Close

30 A8.1. Financial Close (tbd) 10ES+2 weeks A8.1. Financial Close (tbd)

31 A8.2. Complete SPA (tbd) 10; 30 A8.2. Complete SPA (tbd)

32 A8.3. GV transfer 50% payment to LI after PPA signed (tbd) 10; 30 A8.3. GV transfer 50% payment to LI after PPA signe…

33 B. Selection Process for EPC and O&M Contractor B. Selection Process for EPC and O&M Contractor

34 B1. Transmission Line and EVN Substation extension (TO BE DEFINED) 10 B1. Transmission Line and EVN Substation extension…

35 B1.1. Agreements with Licogi for joint usage of transmission line (signed) (?) B1.1. Agreements with Licogi for joint usage of trans…

36 B1.2. EPC Contract for Transmission Line and EVN Substation (tbd) B1.2. EPC Contract for Transmission Line and EVN S…

37 B1.3. Technical Specifications for EPC Contract (tbd) B1.3. Technical Specifications for EPC Contract (tbd)

38 B1.4. ... (tbd) B1.4. ... (tbd)

39 B2. Solar Power Plant and On-Site Substation B2. Solar Power Plant and On-Site Substation

40 B2.1. Completion of Particular Conditions (PC) of EPC Contract (FIDIC) 3 May 2019 B2.1. Completion of Particular Conditions (PC) of EP…

41 B2.2. Completion of Employers Requirements for EPC Contract 40 B2.2. Completion of Employers Requirements for EP…

42 B2.3. Completion of Employers Requirements for O&M Contract 40 B2.3. Completion of Employers Requirements for O&…

43 B2.4. Completion of Reliance Material for EPC 2; 3; 5; 6; 7; 8; 10; 40 B2.4. Completion of Reliance Material for EPC

44 B2.5. Request firm bid 40; 41; 42; 43 B2.5. Request firm bid

45 B2.6. Bid preparation 3 weeks 44 B2.6. Bid preparation

46 B2.7. Bid evaluation and negotiation 4 weeks 45 B2.7. Bid evaluation and negotiation

47 B2.8. EPC contract signing 3 Jun 2019 B2.8. EPC contract signing

48 C. EPC Construction Schedule (excl. OHL) C. EPC Construction Schedule (excl. OHL)

49 C0.1. Limited Notice to Proceed (LNTP) or Critical Component Procurement by SPV 47 C0.1. Limited Notice to Proceed (LNTP) or Critical Co…

50 C0.2. Notice to Proceed (NTP) 46; 49 C0.2. Notice to Proceed (NTP)

51 C0.4. EPC complete technical Design C0.4. EPC complete technical Design

52 C0.4.1. EPC complete Technical Design 8 weeks 47 C0.4.1. EPC complete Technical Design

53 C0.4.2. Independent consultant review and prepare Technical Design Assessment 3 weeks 52
C0.4.2. Independent consultant review and prepare T…
Report (?)
54 C0.4.3. MOIT Technical Design review and approval (?) 2 weeks 53 C0.4.3. MOIT Technical Design review and approval (?)

55 C1. Procurement and Ordering C1. Procurement and Ordering

56 C1.1. Substructure (Order) 2 weeks 50 C1.1. Substructure (Order)

57 C1.2. Modules (Order) 2 weeks 50 C1.2. Modules (Order)

58 C1.3. Inverters and LV/MV Transformers (Order) 2 weeks 50 C1.3. Inverters and LV/MV Transformers (Order)

59 C1.4. Cables and Combiner Boxes (Order) 2 weeks 50 C1.4. Cables and Combiner Boxes (Order)

60 C1.5. PV Plant Monitoring Material + Sensors (Order) 2 weeks 50 C1.5. PV Plant Monitoring Material + Sensors (Order)

61 C1.6. Assignment of Subcontractors 2 weeks 50 C1.6. Assignment of Subcontractors

62 C1.7. Substation and MV/HV Transformer (Order) 2 weeks 49 C1.7. Substation and MV/HV Transformer (Order)

63 C2. Lead Time of Materials C2. Lead Time of Materials

64 C2.1. Substructure (Lead Time) 8 weeks 56 C2.1. Substructure (Lead Time)

65 C2.2. Modules (Lead Time) 8 weeks 57 C2.2. Modules (Lead Time)

66 C2.3. Inverters and LV/MV Transformers (Lead Time) 8 weeks 58 C2.3. Inverters and LV/MV Transformers (Lead Time)

67 C2.4. Cables and Combiner Boxes (Lead Time) 4 weeks 59 C2.4. Cables and Combiner Boxes (Lead Time)

68 C2.5. PV Plant Monitoring Material + Sensors (Lead Time) 4 weeks 60 C2.5. PV Plant Monitoring Material + Sensors (Lead T…

69 C2.6. Substation and MV/HV Transformer (Lead Time) 21 weeks 62 C2.6. Substation and MV/HV Transformer (Lead Time)

70 C4. Transport and delivery of Materials on Site 79; 83 C4. Transport and delivery of Materials on Site

71 C4.1. Substructure (Delivery) 8 weeks 64 C4.1. Substructure (Delivery)

72 C4.2. Modules (Delivery) 8 weeks 65 C4.2. Modules (Delivery)

73 C4.3. Inverters and LV/MV Transformers (Delivery) 4 weeks 66 C4.3. Inverters and LV/MV Transformers (Delivery)

74 C4.4. Cables and Combiner Boxes (Delivery) 4 weeks 67 C4.4. Cables and Combiner Boxes (Delivery)

75 C4.5. PV Plant Monitoring Material + Sensors (Delivery) 2 weeks 68 C4.5. PV Plant Monitoring Material + Sensors (Delivery)

76 C4.6. Substation and MV/HV Transformer (Delivery) 4 weeks 69 C4.6. Substation and MV/HV Transformer (Delivery)

77 C5. Construction of Facility C5. Construction of Facility

78 C5.1. Civil Works 20; 22 C5.1. Civil Works

79 C5.1.1. Leveling and Clearing 4 weeks 61 C5.1.1. Leveling and Clearing

80 C5.1.2. Construction Camp 1 week 79SS C5.1.2. Construction Camp

81 C5.1.3. Erecting Installation Facility 2 weeks 79SS+1 week C5.1.3. Erecting Installation Facility

82 C5.1.4. Drainage 4 weeks 79 C5.1.4. Drainage

83 C5.1.5. Fencing (Storage Area) 1 week 79SS+1 week C5.1.5. Fencing (Storage Area)

84 C5.1.6. Fencing (Power Plant) 4 weeks 79 C5.1.6. Fencing (Power Plant)

85 C5.1.7. Security System 6 weeks 75; 84 C5.1.7. Security System

86 C5.1.8. Facility Roads 4 weeks 79 C5.1.8. Facility Roads

87 C5.1.9. Access Road 8 weeks 79SS C5.1.9. Access Road

88 C5.1.10. Trenching 18 weeks 79 C5.1.10. Trenching

89 C5.1.11. Erecting Foundation Posts 71SS+3 weeks; 79S… C5.1.11. Erecting Foundation Posts

90 C5.2. Assembly and Installations C5.2. Assembly and Installations

91 C5.2.1. Substructure (Installation) 10 weeks 89SS+1 week C5.2.1. Substructure (Installation)

92 C5.2.2. Modules (Installation) 8 weeks 72EE+4 weeks; 91S… C5.2.2. Modules (Installation)

93 C5.2.3. Inverters and LV/MV Transformers (Installation) 6 weeks 73; 91SS+4 weeks C5.2.3. Inverters and LV/MV Transformers (Installation)

94 C5.2.4. Combiner Boxes 74; 91SS+2 weeks;… C5.2.4. Combiner Boxes

95 C5.2.5. DC Cables (Installation) 9 weeks 74; 92SS C5.2.5. DC Cables (Installation)

96 C5.2.6. AC Cables (Installation) 23; 74; 93SS; 98EE C5.2.6. AC Cables (Installation)

97 C5.2.7. PV Plant Monitoring Material and Sensors (Installation) 75; 93SS+1 week; 9… C5.2.7. PV Plant Monitoring Material and Sensors (Ins…

98 C5.2.8. Substation and MV/HV Transformer (Installation) 1 week 76 C5.2.8. Substation and MV/HV Transformer (Installation)

99 C.6 Commissioning and Testing C.6 Commissioning and Testing

100 C6.1. Pre-Commissioning Tests (DC Side) 95EE+1 week C6.1. Pre-Commissioning Tests (DC Side)

101 C6.2. Commissioning Tests and Grid Connection 2 weeks 90; 100 C6.2. Commissioning Tests and Grid Connection

102 C6.3. Performance Tests and Practical Completion 1 week 100; 101EE C6.3. Performance Tests and Practical Completion

103 C6.4. Commercial Operation Date (COD) 102 C6.4. Commercial Operation Date (COD)