RISK ASSESSMENT Ref. No. : ACC/TKP/RA/LNVT/0003

Title: Piling Works Assessment Date: 15/02/2021


GENERAL NOTES:
1-All necessary permits to be obtained from ACC concerned person prior to work commences.
2-All persons must be Safety Inducted.
3-Mandatory job specific PPEs must be worn by all engageg person
4-Life saving task must be conducted prior to start each shift, All person to be participate the task
5-All engaged person must be aware about their job, potential hazards and control measures
6-Probability, Severity & risk Table is attached for reference

RISK EVALUATION RISK CONTROL

Risk Rating
Probability

Probability

Controlled
Risk Level

Risk Level

risk rating
Consequence

Severity

Severity
(Possible injury/Ill-Health/ Remarks (Acceptable:
S.N. Activity Hazards Persons-at-Risk & Present Control Measures A/ Not- Acceptable: Person responsible
Environmental) NA)

PTW shall be obtained from ACC concerned person prior to start the activity
Unauthorised work commencing at Personal injury, Property damage M Inform all people regarding permit conditions before work starts
1 Work Permit site 2 3 6
Supervisors must conduct daily toolbox talk about nature of work and associated potential hazards and
1 2 2 L Acceptable Site Engnieer
their essential precautionary

2 Pile location is to be
marked by the surveyor
Slip/trip hazards Personal injury 2 2 4 M Pay attention on work/on path
one worker to be deployed as a helper
1 2 2 L Acceptable Site Engnieer

All rig machine shall be TPI certified, physically checked as per checklist, colour coded
Toppling of Rig Property damage, injury to
3 Shifting of hydraulic Rig
at location
Hit to another property or workmen 2 3 6 M Rig machine to operated by only authorised person
Shifting route to be cleared identify
1 2 2 L Acceptable Site Engnieer
workmen
Traffic marshal to be deployed while the machine shifting to designated place

Area to be barricaded with orange mesh


Property damage, injury to
4 Rig placed over the point Crush to worker/engineer workmen 2 3 6 M A trained signal man/foreman to be deployed to the job 1 2 2 L Acceptable Site Engnieer
Only authorised person will stay in barricaded area
Rig to be operated by only authorised person
The tank must be hard barricaded from all sides
During the work near tank maintain body posture
Fall in to tank Personal Injury
5 Prepatation of tank for
bentonite slurry
2 2 4 M Keep safe distance 1 2 2 L Acceptable Site Engnieer
only required person should be engage for the job near tank

Chain block shall be TPI certified and colour coded


Chain block to be hang in right position
Power connection for motor to be checked by ACC concerned person
Fall in to tank, Healthy workmen to be engaged for bentonite mixing into water and maintain good body posture during
Failure of chain block Property damage, pouring bentonite into water
6 Bentonite slurry
preparation electrocution Eye irritation, skin problem, 2 3 6 M housekeeping to be maintained arround bentonite tank 2 2 4 M Acceptable Site Engnieer
inhalation problem Use job specific PPEs-Nose mask, rubber hand gloves etc
wash your eyes if feal eye irritation
Trained rigger deployment to the augar fixing job
Perfect rigging signal between operator and rigging forman
Unwanted access control by barricading
7 Auger fixed at the tip of
Kelly with Rig machine
Hit to engaged workers Personal Injury 2 3 6 M Locked pin to be in right place with perfect body size 2 2 4 M Acceptable Site Engnieer
Use proper PPEs

Area to be barricaded with orange mesh


Initial boring with the only very required person to be engaged for the job and will stay inside barricaded area
Unwamted movement of person
8 help of auger for
placement of Casing fall of person into casing pipe Serious Injury 2 4 8 H casing pipe shall be covered by rebar mesh, while piling work not in progress 1 2 2 L Acceptable Site Engnieer
(6mtr).

Area to be barricaded with orange mesh


only very required person to be engaged for the job and will stay inside barricaded area
9 Pilling/Boring continued
till the required depth
Hit & hurt Personal Injury 1 5 5 M 1 2 2 L Acceptable Site Engnieer

Area to be barricaded with orange mesh


Excess mud to be only very required person to be engaged for the job and will stay inside barricaded area
10 collected into the bucket Slip/trip hazards Personal Injury 2 2 4 M collected mud to be dumped at safe distance from boring point 1 2 2 L Acceptable Site Engnieer
inside the bore

A proper strength bearing grating( 1.0m x 1.0m) to be placed over the bore hole imidiately after comleting
of boring
Slip & fall of person inside the bore Serious Injury Grating/rebar mesh to be tied with casing pipe
11 Ope bore hole hole 2 4 8 H Rebar mesh to be not removed until cage is ready for insert into bored 1 2 2 L Acceptable Site Engnieer
close supervision required

Rig shall be operated by authorised person


Traffic Marshal to be apointed while shifting of rig for unwanted movement control
Rig to be shifted aside Toppling of Rig & Hit to other
12 after completion boring structure / machinery or engaged Serious Injury to workmen,
property damage 2 2 4 M 1 2 2 L Acceptable Site Engnieer
upto required depth worker

work to be performed under trained rigger


Rebar cage hanging for failure of lifting tools All lifting tools to be certified by competent person, colour coded and healthy in physical condition
Personal injury
13 insertion into bore by rig improper hanging property damage 2 4 8 H Guide rope to be tied for movement control 1 2 2 L Acceptable Site Engnieer
machine hitting to workers Only required person to be deployed to the job

Use of Full body leather apron, leather hand gloves, cutting and welding shield etc
Power connection to be done through RCCB
welding cable to be in healthy condition
Cable management system to be in practice
Use of tested and rated capacity sling and D-Shackle,
Electrocution, Burn, Eye Injury, Personal injury
14 Multiple cage insertion Failure of sling, fall of material property damage 2 3 6 H Expert Rigger to be deployed 2 2 4 M Acceptable Site Engnieer
One cage to be hold by rebar at 1 meter above from casing pipe
Make ensure first cage has been hold safely at casing pipe then another cage wil lift and allingment with
first cage then welding will start

All trimie pipes to be in healthy condition including tighting thread


Fixing job to be done under trained rigger supervision
15 Trimie pipe holder / lock
fixing with casing pipe
hurt, failure of fixing thread Personal injury 2 2 4 M Use proper PPEs 1 2 2 L Acceptable Site Engnieer

Use of hand gloves and all mandatory PPE's for fixing of sling the the trimie pipe
Trimie pipe lowered by All lifting tools & tackles to be certified by competent person
machiine/ crane into Hit and Hurt, failure of lifting tools Personal injury, property damage Guide rope to be tied with trimie pipe for swinging control
16 rig
the borehole upto the & tackles 2 3 6 H keep safe distance 2 2 4 M Acceptable Site Engnieer
end of boring

Use of hand gloves and all mandatory PPE's for fixing of trimie pipe with each other
Trimie pipe joined with All lifting tools & tackles to be certified by competent person
failure of lifting tools
17 each other by thread Personal injury, property damage 2 4 8 H Trimie pipe holder to be placed properly for holding the pipe at casing 2 2 4 M Acceptable Site Engnieer
joint keep safe distance

Power connection for tank motor to be in safe condition and gone through RCCB
Washed water to be flow in one identified direction and stored in one place
18 washing of bore hole by
bentonite flow
Slipping hazards, electrocution Personal Injury 1 3 3 L The area to be barricaded 1 2 2 L Acceptable Site Engnieer
Deployment of Road marshal for traffic control
Placement of Transit Mixer shall be guided by skilled person,
Transit mixer arrived at Reverse Horn to be ensured, Barrier/barricadding to be placed to maintain safer distance.
Personal injury
19 site and placed at point Hit and Hurt property damage 2 2 4 M Ensure wheel stopper to be in practice during TM operation. 1 2 2 L Acceptable Site Engnieer
in backward direction. Vehicle driver should not get down from vehicle.
Fix wheel choke with the help of Concreting gang present at site.

make ensure Funnel to be tied properly before concrete pouring started


Housekeeping to be maintained at site
Use of safety goggles, use of rated capacity and tested slings and D-Shackle
Fall of funnel, eye injury, Slip Personal injury
21 Concrete pouring Hazzard property damage 2 3 6 H Ensure proper drainage for excess water 2 2 4 M Acceptable Site Engnieer
trained and identified worker to be deployed to the job
close supervision at site
Casing pipe to be properly covered by reber mesh while concrete work is not in progress

During unlocking of trimie pipe wear all mandatory PPEs


Skilled worker to be deployed to the job
Personal injury
23 Trimie pipe withdrawn
from bore hole
Hit and Hurt property damage 2 2 M 4 Before unlocking the pipe mud to clean from trimie pipe by water 1 2 2 L Acceptable Site Engnieer
Before unlocking of upper trimie pipe lowered pipe to be properly locked with casing pipe

Lifting tools to be checked as per standard before taken in operation


Personal injury
24 Removal of Casing with
the help of rig/crane
Fall hazzard property damage 2 3 6 H Trained rigger to be assigned for the job 1 2 2 L Acceptable Site Engnieer
Area to be barricade
Proper illumination to be provided at site
Personal injury Identified electrician to be present at site at all time
25 work in dark hour Slip/trip hazards 2 3 6 H Cable management to be in practice 1 2 2 L Acceptable Site Engnieer
Housekeeping to be maintaine at site

Personal injury After finished the job housekeeping to be done at site


26 HouseKeeping Slip/trip hazards Acceptable Site Engnieer