Professional Documents
Culture Documents
Hira 1
Hira 1
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 1: BLOCK WORKS
1 Storage of blocks 1. Height above 1.5 M 1. Fall of blocks 4 3
2. Improper Storage 2. Personal Injury
2 Transportation of blocks to the site 1. Unsecured blocks 1. Breakage of blocks 3 2
2. Rough and uneven Road. 2. Personnel injury.
4 Shifting blocks to the building site 1. Use of defective dumper 1. Damage to dumper 3 4
by dumper 2. Mis-operation. 2. Tilting of dumper.
Page 22
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 2: CONCRETE CHIPPING
1 Chipping 1. Bad condition of tools 1. Personnel injury 2 3
2. Foreign particles 2. Eye injury
3. Tripping hazard
ACTIVITY - 4: CONCRETING.
1 Concreting 1. Air pollution by cement. 1. May affect Respiratory System. 3 3
2. Handling of ingradients. 2. Hands may get injured.
3. Protruding reinforced rods. 3. Feet may get injured.
4. Earthing of electrical mixers, 4. Can cause electrocution/
vibrators etc. not done. asphyxiation.
5. Falling of materials from 5. Persons may get injured.
height. 6. Causes tiredness of workers and
6. Continuous pouring of by may lead to accident.
same gang. 7. Parts of body or clothes may get
7. Revolving of concrete mixer/ entrapped.
vibrators
Page 23
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
2 Super- structure 1. Air pollution by cement. 1. Shuttering /props may collapse 4 3
2. Handling of ingradients. and prove fatal.
3. Protruding reinforced rods.
4. Earthing of electrical mixers,
vibrators etc. not done.
5. Falling of materials from
height.
6. Continuous pouring of by
same gang.
7. Revolving of concrete mixer/
vibrators
8. Deflection in props or
shuttering material
Page 24
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 6: MANUAL EXCAVATION
1 Piling Work 1. Failure of pile- driving 1. Can hurt people . 2 3
equipment. 2. Can cause deafness and
2. Noise pollution. psychological imbalance.
3. Extruding rods/ casing . 3. Can hurt people.
4. Working in the vicinity of 4. Can cause electrocution
'Live- Electricity ' /Asphyxiation
Page 25
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
4 Rock excavation by blasting 1. Improper handling of 1. May prove fatal. 4 4
explosives. 2.. May cause severe injuries or
2. Uncontrolled explosion. prove fatal.
3. Scattering of stone pieces in 3. Can hurt people .
atmosphere. 4. May cause severe injuries
4. Entrapping of animals / 5. May explode suddenly.
persons .
5. Misfire
5 Narrow deep excavations for 1. Frequent cave-in or slides. 1. May cause cave-in or slides.. 4 3
pipelines, etc. 2. Flooding due to Hydrostatic 2. Persons may get buried.
testing 3. May cause severe injuries or
prove fatal.
4. May arise drowning situation
Page 26
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 7: MECHANICAL EXCAVATION
1 Excavation using machinery 1. Defective machinery 1. Damage to the machinery 3 5
2. Mis-operation 2. Damage to underground electrical,
3. Inadvertent operation telecom cables and water services.
4. Working near the edge of 3. Fall of machinery into the pit.
excavation 4. Pipe lines rupture/explosion injury.
5. Working near utilities. 5. Shock/Fatality
6. Working near overhead lines. 6. Fatal injury
7. Fall of heavy objects Stone, 7. Lung complaints
boulder, soil etc. into
excavated pit.
2 Incomplete excavation. 1. Un-noticed hazard area. 1. Fall of persons/animals into the pit. 3 4
2. Improper barricading. 2.
3. Bad weather. 3. Fall of machinery into pit.
4. Landslide due to weather effect
Page 27
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 8: ROCK BREAKING
1 Rock excavation using pneumatic 1. Jolts to operator. 1. Ill health. 4 3
equipment, rock breaker, 2. Obstruction to vision 2. Damage, injury to facilities and
excavators. between operator and people
banksman. 3. Injury/Damage to asset.
3. Flying Projectiles. 4. Hearing impairment.
4. Noise. 5. Plumonary disorders.
5. Dust. 6. Fall of material, equipment,
6. Excavated Trench persons and animals
4 Working near overhead lines and 1. Fall of hammer on nearby 1. Damage to Hammer chisel. 2 5
pressure lines facilities. 2. Physical injury.
2. Overhead lines. 3. Damage to assets.
3. Hitting, stricking, reversing 4. Shock.
incidents. 5. Fatal injury
Page 28
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 9: PLASTERING
1 Plastering/ 1. Inhalation of cement dust. 1. Bronchial disease 4 3
Grouting 2. Absorption of cement 2. Irritation
3. Ingestion. 3. Prolonged exposure causes
dermatitis.
4. Gastro-intestinal disorders.
Page 29
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 11: WORK ON REBAR
1 Manual bar bending. 1. Defective tools 1. Personnel injury. 2 3
2. Wrong application of tools. 2. Damage to tools.
3. Wrong posture. 3. Back pain.
Page 30
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 12 REINFORCEMENT
1 Reinforcement 1. Curtailment and binding of 1. Persons may get injured . 3 3
rods. 2. Workers may get injured on their
2. Carrying of rods for short hands and shoulders.
distances/ at height. 3. Rods may cut or injure the fingers.
3. Checking of clear distance/ 4. Persons may get injured and fall
cover with hands. down .
4. Hitting projected rods and 5. May prove fatal.
standing on cantilever rods. 6. Protruded rods may hit the persons
Page 31
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 14: GRINDING
1 Grinding and grinding wheel 1. Grinding without goggle. 1. Injury to eyes by flying chips. 3 4
replacing. 2. Absence of tool rest on 2. Accident and injury
bench grinder.
3. More gap between the
wheel and tool rest of bench
grinder.
4. Improper /wrong size
grinding wheel.
5. Excess pressure on wheel.
6. Breakage of wheel.
Page 32
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 18: GAS WELDING
1 Gas welding / cutting / heating. 1. Welding radiates invisible 1. Radiation can damage eyes and 2 5
ultraviolet and infrared rays. skin.
2. Improper placement of 2. Explosion may occur.
oxygen and acetylene 3. May cause fire.
cylinders. 4. Cylinder may burst.
3. Leakage /cuts in hoses.
4. Opening - up of cylinder.
5. Welding of tanks, container
or pipes storing flammable
liquids.
Page 33
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 19: ARC WELDING
1 Arc welding 1. Radiation harmful to naked 1. Welder's cataract. 2 5
eyes. 2. Burn injury.
2. Splinters / slag. 3. Lung ailments
3.Toxic flames. 4. Dermatitis.
4. Dislocation / fall of job piece 5. Hit injury / crush injury.
due to faulty clamping. 6. Electric shock.
5. Loose connections / Loss of 7. Fire / explosion.
insulation. 8. Asphyxiation.
6. Flammable gases.
7. Poor ventilation
Page 34
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 21: MATERIAL HANDLING (MANUAL)
1 Material handling (manual) 1. Non-use of PPE. 1. Accident/ injury. 3 4
2. Inadequate manpower. 2. Back pain,sprain,etc.
3. Lack of co-ordination in 3. Property damage.
group effort. 4. Injury /property damage.
4. Wrong body posture. 5. Loss of property.
5. Lifting error.
6. Sharp edges / corners /
projecting parts / protruding
nails.
7. Slippery materials.
8. Loose materials.
Page 35
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 24: WORKING UNDER CRANE / LIFTING EQUIPMENT.
1 Working under crane / lifting 1. Working without PPE. 1. Fatality / injury due to fall of loads. 2 5
equipment 2. Failure of slings. 2. Material damage.
3. Improper handling.
4. Overloading.
5. Defective equipment.
6. Lack of awarness.
Page 36
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 26: MATERIAL HANDLING WITH CRANE
1 Crane positioning 1. Outriggers on soft 1. Tilting of crane & consequent 3 4
ground/loose soil damage & loss.
4 Loading operation 1. Side loading / dragging of 1. Tilting of the crane due to uneven 2 5
load. load.
2. Overload. 2. Damage to crane and loss of
3. Swinging the load. materials.
4. Abrupt operation of control 3. Instability & tilting of crane.
levers. 4. Jerking, fall of load, hitting person.
5. Keeping the load in the 5. Fall of load due to mechanical
elevated position. failures.
6. Persons standing below the 6. Fall of load causing human
lifted load. injuries.
7. Electric shock.
8. Fall of load & tilting of crane.
Page 37
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 27: HYDROTESTING
1 Testing 1. Bursting of piping. 1. May cause injury and prove fatal. 4 4
2. Collapse of tanks.
3. Tanks flying off.
4 Tightening flange bolts under high 1. Flanges & bolts under 1. Hitting of thrown out flange & 2 5
pressure. pressure. injury.
Page 38
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 28: HANDLING OF GAS CYLINDERS
1 Transporting gas cylinders: 1. Cylinders kept horizontal. 1. Fire and explosion by leakage and 2 5
* Oxygen 2. Cylinder kept untied property damage.
* Acetylene. /unlocked in welding truck 2. Gas leakage due to valve damage.
* Argon. /mobile welding unit. 3. Human injury by fall of cylinder.
* Nitrogen. 3. Valve leakage. 4. Damage to cylinder/valve.
* LPG. 5. Leakage of gas.
Page 39
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 29: RADIOGRAPHY
1 Radiography on welded joints. 1. Ionizing radiation. 1. Radiations may react with the skin 2 5
2. Transportation and storage and can cause cancer, skin irritation,
of Radiography source. dermatitis etc.
3. Loss of Radio isotope
Page 40
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 30: TANK ISOLATION AND CLEANING
1 Working in confined space 1. Inadequate access to 1.Inability to escape. 2 5
(tanks/vessels) outside. 2. Inability to contact the standby
2. Lack of communication. man.
3. Tools stricking due to 3. Injury/fatality
congested work place. 4. Exhaustion or other heat ailments.
4. Heat stress. 5. Aspthyxiation.
5. Inadequate ventilation. 6. Trip and fall injury.
6. Darkness inside the tank
due to lack of illumination.
Page 41
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 32: STRUCTURAL WORKS
1 Structural works 1. Personal negligence and 1. Can cause injury or casualty. 4 5
danger of fall.
2. Lifting / slipping of material
Page 42
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 33: PIPELINE WORKS
1 Pipe laying 1. Erection/ lowering failure. 1. Can cause injury. 4 5
2. Others 2. Can cause injury.
Page 43
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 35: PAINTING
1 Unloading of Paint Material from 1.Fall of Material 1.Personal injuries 2 2
vehicle 2.Improper 2.Lack of co-ordnation among the
manual material handling group
3 .Injury
due to material fall
3 ) Fall
of material
4 )Damage
of property
2 .Defective
scaffolding
4.Improper erection
4 Working in hot enviroment 1.Heat stress due to failure of 1.Heat ailments as such heat 2 4
thermo regulatory system of exausting,heat cramps and heat
the body stroke
2.Dehydration due to
excess loss of body fluids
Page 44
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
5 Working at elevated place 1.Fallof person 1.May sustain sever injuries or prove 2 5
fatal.
2.Fall of Material 2.May hit by another object
3.Scaffold structure can collaps
4 .Material can
fall from height
3.Defective Scaffold
4.Improper use
5.Faulty access to
platform
6.Inadequate size of
platform
7.Over loading
8 .Faulty /
Unguarded
access/ladder/stairs
2)Fall of material
3) Improper
manual material handling
Page 45
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 36: SPRAY PAINTING.
1 Washing vehicle/equipment 1. Slip hazard. 1. Physical injury. 3 4
thoroughly by steam or high 2. Flying objects 2. Vehicle damage.
pressure water. 3. Vehicle roll. 3. Hot burns.
4. High pressure hose. 4. Cuts.
5. Hot surface. 5. Material damage.
6. Sharp corners.
7. Electrical contacts.
7. Handling putty.
8. Dust.
9. Electrical Hazard.
10. High pressure hose.
Page 46
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 37: LABOUR CAMP
1 To Stay in residental camp 1. Fall of Material 1.Personal injuries 2.property
1 5
2.Bad housekeeping Damage
3.Over crowding 3Asphyxia (suffocation) 2 3
5 To stay in hot enviroment 1.Heat stress due to failure of 1.Heat ailments as such heat 2 4
thermo regulatory system of the exausting,heat cramps and heat stroke
body
2.Dehydration due to excess loss
of body fluids
5 Vehicle movement Vehicle accident 1) Personal injury 2) Property 3 4
damage
Page 47
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 38: WORKING IN DUSTY ENVIRONMENT
1 Working in dust 1. Dust (Inhalation and striking 1. Lung disorders (silicosis) and eye 5 1
the eye) injury.
Page 48
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 41: SLIPS, TRIPS AND FALLS AT WORK PLACE.
1 Moving in the work area. 1. Timbering blocks, wooden 1. Bodily injury due to fall of persons 3 4
planks, steel rod bits. , fall of heavy objects, tools etc.
2. Pipe pieces. 2. Hitting on overhead projections.
3. Protruding bolts on concrete
foundations of pipe supports.
4. Paint tins, polythene papers,
electric cable/wire insulations,
steel wire insulations, steel
wire cuttings, tools & tool
boxes.
5. Overhead projection of
pipes.
ACTIVITY - 42: ELECTRICAL CABLE DRUM UNLOADING ,CABLE LAYING AND TERMINATION OF ELECTRICA
Unloading of Cables by hydra 1) Improper communication 1) Accident /Injury
(HT, LT Cables)
2)Over loading
1 4 4
3) Untrained
operator 2 ) Damage of
Shifting of Cable by hydra (HT, 1)Improper communication 1) Accident /Injury
LT Cables)
2)Over loading
3) Untrained operator
2 2 ) Damage of 4 4
property
4) Improper metrial
handling 5)Defective equipment
Cable Terminations in a panel 1) Short Circuits 1) Personal injury
2) Electrocution
3 2 5
2)
Fire
4 3) Electrodes might 3 4
short 3 ) Battery
terminals shall be shortened if the
metals gets in contact.
Page 49
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
Cable Megger and 1) Short Circuits 1) Personal injury
Cable HI- 2) Electrocution
POT
2)
5 Fire 3 5
3) Electric shock
Page 50
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 44: LAYING ELECTRICAL CABLES
1 Laying out electrical cables 1. Unstable Cable drum. 1. Fatality / service injury due to fall 4 5
(Cable drum handling) 2. Wrong position of jack. of cable drum or jack.
3. Inadequate jack / spindle. 2. Injury by hitting / caught in.
4. Defective jack / spindle. 3. Finger injury due to trapping
5. Rotating parts. between drum / rollers.
6. Drum rollers. 4. Serious injury due to slip & fall of
7. Pulling in wrong posture. cable.
8. Open trench. 5. Loss of cable.
9. Theft.
Page 51
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 46: PASSAGE UNDERNEATH OVERHEAD LINES.
1 Transportation of equipment 1. Excess height can contact 1. Fatal electric shock. 2 5
exceeding 5m height with overhead lines. 2. Damage to equipment.
Page 52
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 49: INSPECTION OF EQUIPMENTS
1 Use of Inspection Lamp 1. Short Circuit. 1. Electrocution (fatality / severe 2 5
injury)
2. Damage to equipment and
property.
Page 53
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 51: DRIVING / OPERATING VEHICLES & EQUIPMENTS
1 Driving /operating vehicles/ 1. Lack of knowledge and skill. 1. Fatality / injury. 2 5
equipment 2. Untrained drivers / operators. 2. Loss of property / material.
3. Defective vehicles / 3. Damage to equipment.
equipments.
4. Over speed / overload.
2 Driving on graded roads 1. Loose surface, erosion, pot 1. Injury / fatalities due to accidents. 1 5
holes.
Page 54
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 52: PARKING OF VEHICLES IN PARKING AREA
1 Vehicle parking in designated area 1. Improper parking. 1. Rolling of vehicle resulting in 1 4
2. Uneven surface. fatality / injury.
3. Defective hand brake. 2. Damage to vehicle / properties /
4. Absence of wheel choke. live facilities nearby.
5. Non / Partial application of
hand brake.
Page 55
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 54: HANDLING BATTERY
1 Remove old / discharged battery 1. Inadvertent movement of 1. Physical injury . 2 5
from vehicle vahicle . 2. Fire burns.
2. Spark. 3. Acid burns.
3. Fire
Page 56
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
5 Transportation of charged battery 1. Manual handling. 1. Physical injury. 2 5
from charging room to vehicle / 2. Spark. 2. Acid burns
store. 3. Fire. 3. Material hazard .
Page 57
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 55: OPERATION OF COMPACTOR
1 1. Starting by pulling up with 1. Inadvertent contact with 1. Accidents. 2 4
string. vibrator. 2. Damage.
2. Running compactor 2. Rotating parts.
3. Fall.
Page 58
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 57: OPERATION OF FORKLIFT
1 Loading Forklift 1. Careless operation 1. Can lead to accidents. 2 4
Page 59
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 58: OPERATION OF VIBRATOR
1 Starting by pulling up with string 1. Inadvertant contact with 1. Injury. 2 4
vibrator. 2. Contact with body.
2. Rotating parts. 3. Damage.
Kick back of hose. 4. Burn hazard.
3. Cement splash.
4. Fall of vibrator into
excavation concreting location.
5. Fire hazard
2 Parking vehicle for the job. 1. Vehicle rolling of. 1. Physical injury. 2 4
2. Vehicle under a live 2. Vehicle damage.
mechanism 3. Material damage.
4 Removal of gear box 1. Tilting & falling of gear box. 1. Damage to engine. 2 4
2. Physical injury.
Page 60
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 60: CHANGING OF ALTERNATOR
1 Prepare a vehicle for replacing 1. Rolling of vehicle. 1. Physical injury . 2 4
alternator. 2. Hit. 2. Vehicle injury
Page 61
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 62: TOWING OF DEFECTIVE VEHICLE
1 Assess the causes of break down. 1. Hot surfaces. 1. Physical injury. 1 4
2. Inadvertent movements. 2. Heat burn.
3. Hit hazard. 3. Vehicle damage / injury.
2 Prepare the vehicle for towing. 1. Defective movable parts. 1. Nip hazard. 1 4
2. Improper towing devices /
hook / chain.
Page 62
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 63: WIRE ROPE REPLACEMENT (CRANE)
1 Parking the crane 1. Inadvertent movement 1. Accident 3 4
2. Physical injury.
3. Equipment damage
Page 63
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 64: HANDLING AND LIFTING EUIPMENTS (GENERAL)
1 Handling and lifting equipments 1. Failure of load lifting and 1. Can cause accident and prove 3 4
moving equipment. fatal.
2. Overloading of lifting 2. Can cause electrocution and fire
equipments.
3. Overloading electrical wires
Page 64
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 65: GRIT BLASTING
1 Copressor operation 1. Bursting of piping. 1. May cause injury and prove fatal. 3 5
2. Collapse of tanks.
3. Tanks flying off.
Page 65
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
3 Application of nozzle. 1. Bursting of joint 1. Physical Injury. 1 2
2. Flying of nozzale & hitting 2. Eye Injury
persons 3. Ill health.
3. Bursting of hosses. 4.Hit by
nozzle in the eyes
Page 66
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 66: FABRICATION YARD OPERATIONS
1 Grinding and grinding wheel 1. Absence of tool rest on 1. Eye / face injury 3 4
replacing. bench grinder. 2. Hand injury
2. More gap between the
wheel and tool rest of bench
grinder.
3. Improper/wrong size
grinding wheel.
4. Excess pressure on wheel.
5. Breakage of wheel.
Page 67
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
5 Material handling (manual) 1. Lack of co-ordination in 1. Back pain,sprain,etc. 3 4
group effort. 2. Body Injury
2. Wrong body posture.
3. Lifting error.
4. Sharp
edges/corners/projecting
parts/protruding nails.
5. Slippery materials.
6. Loose materials.
7 Transporting gas cylinders: 1. Falling of cylinders 2. Gas leakage due to valve damage. 2 5
* Oxygen 2. Explosion 3. Human injury by fall of cylinder.
* Acetylene. 4. Fire / body injury due to explosion
* Argon.
* Nitrogen.
* LPG.
8 Laying out electrical cables 1. Unstable Cable drum. 1. Body injury due to fall of cable 3 4
(Cable drum handling) 2. Wrong position of jack. drum or jack.
3. Inadequate jack / spindle. 2. Injury by hitting / caught in.
4. Rotating parts. 3. Finger injury due to trapping
5. Drum rollers. between drum / rollers.
6. Pulling in wrong posture.
7. Open trench.
Page 68
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 67: ERECTION OF STRUCTURAL ROOF TRUSS
1 Unloading the truss parts from 1. Crane Failure. 1.Fall of materials. 3 5
the Trailor/Tractor 2. Sling Failure because of 2.Property damaged.
loose D shackles, broken sling 3.Personal inury.
etc.
3. Body part caught in between.
4. Fall of the entire load and
the injury to the persons
nearby.
Page 69
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
3 Assembling of two truss parts to 1. Body parts caught in 1.Physical Injury 2 3
form a single piece by bolting. between. 2.Property Damaged.
4 Placing the assembled part in a 1. Sling failure due to loose D 1.Tilting the crane due to uneven 3 5
lifting position. shackles, deteriorated slings, ground.
etc. 2.Fall of load
2. Load may slip on ground if causing physical injury .
not properly placed on wooden 3 .Fall of
sleepers. load due to mechanical failure.
3. Load may hit to the nearby
persons/objects causing
injury/property damage.
4. Collapse of the load
structure.
5 Tying the steel wire rope slings to 1. Body part/fingers caught in 1.Damaged Property. 2 3
the truss structure for lifting. between. 2.Fall of materials.
6 Movement of crane to the 1. Contact/hit with any other 1.Tilting the crane due to uneven 3 3
load/truss structure location for mobile/stationary bodies ground.
lifting. nearby. 2.Fall of load causing
2. Body parts caught in physical injury.
between. 3 .Fall of
load due to mechanical failure.
Page 70
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
7 Lifting the respective roof truss 1. Sling failure due to 1.Fall of materials. 3 3
structure to the particular deteriorated sling. 2.Property damaged.
elevation row. 2. Load may slip from rigging if 3 .Personal
not properly attached. inury.
3. Fall of load and injury to the 4.Physical Injury
workers nearby. 5.Fatality.
4. Electrical hazard. 6 .Eye injury.
5. Plley failure due to broken 7 .Damage
chain. the body parts.
6. Hitting of girder to
persons/structures due to free
movement in air and could
result in injury/property
damaged/load falling.
Page 71
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
8 Placement of truss assembly to 1. Fall of person from height. 1.Fall of materials. 2.Property 3 2
the anchor bolts on the beams at 2. Fall of materials/tools from damaged. 3.Personal inury.
elevation with plumping and height. 4.Physical Injury 5.Fatality.
alignment. 3. Fall of load. 6.Eye injury. 7.Damage the
4. Body parts caught in body parts.
between.
5. Body strain/loss of balance.
6. Hitting of truss
structures to persons/structure
due to free movement in air
and could result in
injury/property loss/load falling.
7. Load may slip from rigging if
not properly attached. Fall of
load and injury to the workers
nearby.
9 Tightening the nut into the anchor 1. Fall of person, materials 1.Caught in between. 3 2
bolt. /tools from height. 2.Physical injury.
2. Fall of load. 3.Fall of materials.
3. Body part caught in
between/strain and loss of
balance.
Page 72
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
10 Releasing the steel wire rope 1. Fall of person, materials 1.Physical Injury. 2 2
sling from the body. /tools from height. 2.Materials damaged.
2. Fall of load.
3. Body part caught in
between/strain and loss of
balance.
4. Hitting of sing wire/D
shackles to the body parts of
workers, while releasing.
11 Lifting the purling and chord 1. Sing failure due to lose D 1.Fatality. 3 4
bracings using Electric winch to shackles, deteriorated sling, 2.Physical Injury.
the particular location where truss etc. 3.Materials
structure rests. 2. Load mat slip from rigging if damaged.
not properly attached. Brake 4.Crane tilted due to uneven ground.
failure.
3. Displacement of winch
assembly from the working
position.
4. Electrical Hazard.
5. Knot failure of the steel wire
rope that is tied to columns.
6. Hitting of bracing pipes to
persons/structure due to free
movement in air and could
result in injury/Property
loss/load falling.
Page 73
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
12 Bolting the purling, Top chord 1. Fall of person from height. 1.Fatality. 3 4
bracing and bottom Chord 2. Fall of materials/tools from 2.Physical Injury.
bracing to the truss structure for height. 3.Materials damaged.
sheeting arrangement. 3. Fall of load. 4.Crane tilted due to
4. Body parts caught in uneven ground.
between.
5. Body strain/loos of Balance.
Page 74
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 68: MOBILE ELEVATED WORK PLATFORM
1 Working in hot enviroment 1. Heat stress due to failure of 1. Heat ailments as such heat 3 3
thermo regulatory system of exausting,heat cramps and heat
the body stroke
2.
Dehydration due to excess
loss of body fluids
2 Vehicle movement 1. Collosion with nearby 1. Personal injury 5 4
structure 2. Damage to property
2. Being struck by other
vehicle
2. Fall of Material
2.
May hit by another object
3.
4 Cage movement Horseplay parts / excavator
1.Rotating 1. May sustain sever injuries or 5 4
itself come into contact with prove fatal.
person. 2.Collosion with 2. May hit by another
nearby structure object
2 .n
3. Property damage
Damaged / Defective tools
7 Working near overhead lines Live lines 1. Electrocution(fatility /severe injury) 2 5
2. Damage to equipment
8 Positioning outriggers 1) Outriggers can sink in soft and propertyinjury
1. Physical 4 4
ground
2)Improper 2.
locking of outriggers Property damage
3. Tilting of vehicle
Page 75
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 69: OFFICE WORK AT H.O.
1 Lift operation 1. Over crowding 1. Suffocation. 1 2
2. Collaps of cage due to 2 . Fatality 1 5
breakage wire rope.
3. Electrical shut down 2
1
Page 76
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 70: LIFT OPERATION AT H.O.
1 Travelling by Passenger Lift from 1. Stoppage of Lift due to 1. Panic 2 3
Lobby to 6th Floor Office Power failure in between floors. 2. Physical problems due to
2. Stoppage of Lift due to hypertension and anxiety
technical problems in between
floors.
3. S
Page 77
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 73: ILLUMINATION IN H.O.
1 Office illumination 1. Insufficient illumination. 1. Gradual vision loss. 2 3
2. Pathways, exits and stairs 2. Physical problems due to
not properly illuminated. hypertension and anxiety.
3. General illumination too low 3. Irritation.
compared to localised 4. Physical Injury.
illumination.
Page 78
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
ACTIVITY - 75: INSULATION, WRAPPING & COATING
1 Using of Standing / Mobile 1)Person can fall down 1) Physical injury 2 4
scaffolding 2) Scaffolding can 2) Property damage
collapse 3) Person working at lower
3) Material can fall level get injured
down.
3) Itching.
Page 79
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
5 Adhesives and 1) Fume Inhalation 1) Burn injury 4 2
Welding agent 2) Improper material handling 2) Explosion may
occur 3)Cylinder
3) Welding radiates invisible may burst 4)
ultra violate and infrared rays Contact with hot object
5) Property damage
4) Improper 6) Radiation can damage
placement of cylinders eyes and skin
5) Back fire
6) Welding
slag can fall down
2)Tripping / Slipping
hazard
Page 80
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
PROBABILITY SEVIRITY
Sl. No. ACTIVITY HAZARD CONSEQUENCE
FACTOR FACTOR
10 Roller Machine 1)Electrical shock. 1) Physical injury 3 3
2) Trip hazard 2) Property damage
3) Itching.
Page 81
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 82
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
R.
MODERATE 3 1. Hold firm.
2. Secure chisel firm to jack.
3. Rotation of work force to avoid prolonged
exposure.
Page 83
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
MODERATE 3 1. Use PPE like goves, shoes, helmets,etc.
2. Avoid usage of make-shift tools.
Page 84
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 85
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1. Ensure proper storage, handling and carrying of
explosives by trained personnel.
2. Comply with the applicable explosive acts and
rules.
3. Allow only authorized persons to perform
blasting operations.
4. Smoking and open flame are to be strictly
prohibited.
5. Use PPEs like gloves, goggles, face mask, etc.
5. Barricade the area with red flags and blow siren
before blasting .
6. Do not return to site for atleast 20min. or
unless announced safe by designated person.
Page 86
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 87
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 88
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 89
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 90
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 91
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 92
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 93
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 94
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 95
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 96
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 97
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4
Page 98
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 99
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 100
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
NG
HIGH 4 1. Train on proper manual lifting procedures.
2. Use only tested and certified equipment & lifting
tackles.
3. Erection only by experienced persons under
supervision of a competent person.
4. Daily inspection and certification by competent
person.
5. PTW in place.
Page 101
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 102
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 103
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
MODERATE 3
4.Implementation of PTW.
5.Implementation of Tag system.
Page 104
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1.Obtained PTW before starting the work. 2.Use
proper PPE.
3.Provide adequate working space
4.Do not throw any loose material
5.Tied up loose material.
6.Ensure adequate supervision
7 . Follow Working
at height procedure OCPM-04
Page 105
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 106
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
LOW 2 1.Use2)adequate
Ensure PPE.
material carried are properly
Page 107
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 108
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
EXTREME 5
2)Use required PPE.
5) are
1) Ensure all cables Usetightened
only certified slings to be
properly.
MODERATE 3
2 ) Maintain
adequate ventilation.
3 ) Use adequate
Page 109
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
1) Ensure Calibration test certificates is available
HIGH 4
3 )Work to be carry out
by competent person only.
4 ) Permit to work to be
follow (HSE-F-027)
Page 110
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
MODERATE 3 1. Banksman.
2. Experienced riggers.
3. Deploy caged truck.
4. Use guide rope.
Page 111
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1. PTW.
2. Erect goal post.
3. Restrict passage.
4. Use inspected & approved lifting equipments &
tackles.
Page 112
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 113
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 114
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1. Put the vehicle gear in the neutral & ensure it.
2. Connect booster battery +ve & -ve terminals
corresponding with the stalled vehicle.
3. Insert ignition key to start the engine &check
the instruments & controls.
4. Direct the vehicles to workshop for changing
the battery.
Page 115
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1. Make sure that front and rear tyres are chockd .
2. Switch off & take out ignition key.
3. Trained persons are to be deployed for removal
of batteries.
4. Wear gloves,googles, safety shoes, etc.
5. Remove -ve terminal first , then +ve terminal to
prevent spark-up.
Page 116
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1. Adopt proper method of manual handling.
2. Use the service of required persons to handle
heavy battery.
Page 117
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 118
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
MODERATE 3 1. Check the load chart for load weight & load
centre information.
2. Always pick up loads as close to weight centre
as possible to avoid imbalance
Page 119
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 120
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 121
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 122
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
MODERATE 3 1. Tie the wire rope with nylon cord & tie to the
nearby frame.
2. Safe drawing of cable out.
MODERATE 3 1. Lift the cable drum with forklift or crane truck
and mount it on a proper rope drum stand.
2. Strict supervision.
Page 123
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 124
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 125
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
LOW 2 1. Nozzle to be operated only by experienced &
qualified operator.
2. Periodical check for equipment to be carried out
for any wear & tear of the hosses for it's
serviceability.
Page 126
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 127
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
MODERATE 3 1. Training & instructions.
2. Use hand gloves/ packing materials.
3. Remove protruding nails before handling.
4. Use proper lifting devices for good grip.
5. Fasten the item properly or use suitable
packing / container.
Page 128
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 129
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
MODERATE 2 1. All the workers should be well experienced &
should be always in vigil.
2. Use proper PPES.
3. Required number of wooden slippers in
required length, size should be placed on the
ground below the load.
Page 130
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1. Before lifting ensure the availability of continues
life line made of 8mm dia steel wire rope of 25mm
dia poly propylene rope tied column to column .
2. Ensure the crane & load lifting appliances are
load tested by a competent person and available
with documents.
3. Ensure sling free of cuts, breaks etc.
4. Warn with proper cautioning nearly workers and
ensure continuous supervision.
5. A signal men should be there to give standard
registered to signals to the operators.
6. Ensure wind velocity is not exceeding the
prescribed limit while doing the operation.
7. Ensured the crane should be positioned such
that hoist ropes are vertical.
8. Ensure the operations should be under the
direct supervision of a competent person and
should be carefully planned in advance. Ensure
the uses of tagline to control all loads .
9. Ensure the usage of gunny bags or half round
pipes at the points where wire rope comes in to
contact with the sharp edges of concrete beams.
Page 131
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1. All workers who are engaged should wear full
body harness/safety belts and hooked in to the life
line made of 8mm steel wire ropes.
2. Ensure the availability of continuous life line .
3. Proper PPEs should to be use. Should be in a
convenient position while working.
4. Use four legged sling arrangement for lifting
and a signal men should be there to give standard
signals to the operator.
Page 132
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
MODERATE 2 1. All workers who are engaged must be qualified
for height pass & should wear full body harness
and hooked it to the life line made of
polypropylene ropes or 8 mm steel wire ropes.
2. A Safety net made of ploy propylene/nylon wire
should be hooked to the truss structures, so that
fall of persons and tools/objects can be safely
hindered.
3. All hand tools should properly tied while
working, it should not fall down. Hand tools should
be carried up a beg while going up and coming
down.
4. All workmen should be using proper PPEs.
5. Intense care should be taken while working with
lifting tools and tackles. Use proper SWL rating
tools to be used.
6. Ensure proper tightening of the nut to the
anchor bolt before releasing the sling.
7. Intense care should be maintained while
releasing.
8. Ensure proper clearance from the sling while
releasing.
Page 133
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
HIGH 4 1. All workers who are engaged must be qualified
for height pass & should wear full body harness
and hooked it to the lifeline made of 8mm steel
wire rope.
2. All hand tools should be properly tied while
working, it should not fall down. Hand tools should
be carried in a bag while going up and coming
down.
3 . All working crew
should be wear mandatory PPEs.Use lifeline
every time while working at high elevation .
4. Use safety net made of poly propylene/nylon
wire should be used under the working level.
Page 134
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
EXTREME 5 3 . Provide
1. Obtained PTW before starting adequate
the work (HSE-F-
027- A).
3 . Ensure
adequate supervision.
2.
Use tools only with protective handles.
2 . Work to be carry
out by competent person only.
EXTREME 5 1. Vehicle to be set on firm ground.On soft ground
place strong wooden blocks or steel plates.
Page 135
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 136
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 137
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
Page 138
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
4 ) Provide
safety nets.
2 ) Provision of proper
access.
4 ) Only authorized
person can execute the job.
2 )Provision of proper
ventilation.
2 ) Use
proper tools.
4 ) Provide of
adequate manpower.
5)
Page 139
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
LOW 2 1) Use specific welding shield and all other
necessary PPE's.
2 ) Provision of adequate
ventilation.
3)
Ensure adequate supervision.
3 ) Shifting the
material in safe manner.
3 ) Only
competentent person should execute the job.
2 ) Work must
be carried out under closed supervision .
2 ) Work must be
carried out under closed supervision. open
place/proper ventilation.
Page 140
PETRON ENGINEERING CONSTRUCTION LTD - HAZARD IDENTIFICATION AND RISK ASSESSMENT - DEVELOPMENT OF RISK
CONTROL MEASURES (HIRA)
RISK
RISK LEVEL CONTROL MEASURES
RATING
LOW 2 1) Only authorized person can carry out the job.
3 ) Use all
necessary PPE's.
4)
Area must be barricade
LOW 2 1) Use all necessary PPE's.
2 ) Job must be
carryout under closed supervision.
5 ) Provision
of proper ventilation.
Page 141