Project: The Oriana

Subject: Weekly Concreting Schedule


Period: May 13-18, 2024

PROJECT WEEKLY CONCRETING SCHEDULE (NORTH TOWER)

Project Code Date Structure Location Design Mix Volume Method of Pouring
ORI 13-May-24 Columns, Flagwall NT 21F Area 1 8500 PSI 3/8 PCD 28.0 cu.m. CB
ORI 13-May-24 Beams and Slab ST Mezzanine Area 1 6000 PSI 3/8 PCD 85.0 cu.m. PC/PB
ORI 13-May-24 Walls ST STP B7 8500 PSI 3/8 PCD 20.0 cu.m. CB
ORI 14-May-24 Beams and Slab NT 21F Area 4 6000 PSI 3/8 PCD 130.0 cu.m. PC/CB
ORI 14-May-24 Columns NT 21F Area 2 8500 PSI 3/8 PCD 10 cu.m. CB
ORI 15-May-24 Elevator Shearwall, Flagwall, Columns NT 21F Area 2 8500 PSI 3/8 PCD 70.0 cu.m. PC/PB
ORI 15-May-24 Walls and Columns ST STP B7 8500 PSI 3/8 PCD 30.0 cu.m. CB
ORI 15-May-24 Beam and Slab ST GF Area 13 6000 PSI 3/8 PCD 50.0 cu.m. PC/PB
ORI 15-May-24 Columns ST Mezzanine Area 1 8500 PSI 3/8 PCD 20.0 cu.m. CB
ORI 16-May-24 Beams and Slab NT 21F Area 5 6000 PSI 3/8 PCD 86 cu.m. PC/CB
ORI 16-May-24 Columns NT 21F Area 3 8500 PSI 3/8 PCD 22.0 cu.m. PC/CB
ORI 17-May-24 Columns NT 21F Area 3&4 8500 PSI 3/8 PCD 17.0 cu.m. CB
ORI 18-May-24 Beams and Slab NT 22F Area 1 6000 PSI 3/8 PCD 86.0 cu.m. PC/PB
ORI 18-May-24 Elevator Shearwall, Flagwall, Columns NT 21F Area 4 8500 PSI 3/8 PCD 70.0 cu.m. PC/CB
ORI 18-May-24 Columns ST STP B6 8500 PSI 3/8 PCD 20.0 cu.m. CB
ORI 18-May-24 Beams and Slab ST GF Area 7 6000 PSI 3/8 PCD 70.0 cu.m. PC/PB

814.0 cu.m.

Prepared by: Noted by:

MARCO HIPOLITO / KEANNEL LEOP JHOEY CANTIGA


Concreting Engineer (North and South Tower) Project-in-Charge