CLASS H - PILING WORKS

MyCESMM2
Class H – Piling Work

CLASS H
PILING WORK

H1
1 of 32 Slides
Copyright@CIDB.Malaysia2018

MyCESMM2
Class H – Piling Work

Measurement covered under other classes


 Boring for site
investigation work
(included in Class D: Site
investigation work)
 Setting out of piles and as-
built drawings (included in Typical piling work processes are:
Class A: General items) 1. Provision of plant and equipment
 Ground anchor and stone 2. Supply of piles
column (included in Class
3. Driving/ installation of piles
G: Geotechnical work)
4. Miscellaneous work
 Walling and tie rod
(included in Class L: 5. Pile testing
Metalwork)
 Diaphragm wall (included
in Class G : Geotechnical
work)

H2
Copyright@CIDB.Malaysia2018

Copyright@CIDB.Malasia.2018 1
CLASS H - PILING WORKS

MyCESMM2
Class H – Piling Work

Measurement rules
M1
Bored and driven depths shall be measured
along the axes of piles from the commencing
surface: Cut-off level
a) To the toe levels of bored piles; and
b) to the bottom of casing of driven cast in
situ piles

M2
The commencing surface is the surface at

Concreted Length
which boring or driving is expected to begin,
and shall be for the measurement of the
completed work.

M3
Each group item for piles to be driven shall
comprise
a) an item for the total supply number of pile
points of stated length and
b) an item for the total depth driven

H3
Copyright@CIDB.Malaysia2018

MyCESMM2
M4 Class H – Piling Work
Depth driven shall be measured from C4
the cutoff levels to the toe levels.
Items for pre-boring shall be deemed to
include grouting void with stated
M5 materials between the piles and the
The concreted lengths of cast in place bores.
concrete piles shall be measured from
the cut-off level to the toe levels C5
expressly required.
Items for depth driven shall be deemed
to include handling, hoisting, pitching,
C1 and driving of piles.
Items for piling work shall be deemed to
include disposal of excavated and C6
surplus materials.
Items for preparing head shall be
deemed to include pile plug, starter
C2 bar, steel plates and welding works.
Items for piling work shall be deemed to
include piling records and number A1
stated.
Item description for piles shall identify
preliminary piles. Item description shall
C3 identify raked piles and their inclination
Items for pre-boring shall be deemed to stated.
include backfilling between the pile .
and the bore.

Copyright@CIDB.Malaysia2018
H4

Copyright@CIDB.Malasia.2018 2
CLASS H - PILING WORKS

MyCESMM2
A2 Class H – Piling Work
Item description for piles shall state the A7
materials composition.
Item description reinforcement shall
state materials and grade including
A3 identifying straight or helical and
Items description for piles shall state the nominal diameter to be stated as not
structure to be supported and identify exceeding 20mm and exceeding
the commencing surface. 20mm.

A4 A8
Item description for piles shall identify Item description for supply of pile shall
initial piles and extension piles. Details of state the cross sectional type and cross
driving head and shoes shall be so sectional dimensions or diameter,
stated in item description. lengths, concrete grade, class of piles,
detail of treatment and coatings
required and working load, where jack-
A5 in method expressly required.
Item description for depth driven shall
state jack-in method when required.
A9
Item description for jointings shall state
A6 type, method and detail of jointing
Item description for reinforcement shall required.
state details of couplers when expressly
required.

Copyright@CIDB.Malaysia2018
H5

MyCESMM2
Summary of First & Second Division Categories Class H – Piling Work
First Division Second Division
1. Plant and equipment. 1. Provision
2. Moving and Handling
3. Temporary staging
2. Piles 1. Bored piles.
2. Driven cast in situ concrete piles
3. Caisson piles
4. Micro piles.
5. Precast reinforced concrete piles.
6. Precast pre-stressed concrete piles.
7. Steel H-piles.
8. Steel pipe piles
3. Piles 1. Timber piles.
2. Precast pre-stressed concrete sheet piles.
3. Interlocking steel sheet piles.
4. Miscellaneous work 1. Obstructions

5. Pile tests 1. Static Load tests.


2. Pile Dynamic analyzer (PDA)
3. Pile Integrity Test (PIT)
4. Sonic Logging test
5. Lateral test
6. Statnamic test
7. Bi-directional static load
8. Global strain extensometers static load
6. Pile tests 1. Plate loading
2. Shaft friction H6
Copyright@CIDB.Malaysia2018

Copyright@CIDB.Malasia.2018 3
CLASS H - PILING WORKS

MyCESMM2
Class H – Piling Work

First division Second division Third division Unit


1. Plant and 1. Provision sum
equipment 2. Moving and sum
Handling
3. Temporary staging sum
2. Piles 1. Bored piles 1. Depth bored or driven m
2. Driven cast in situ 2. Boring through rock m
concrete piles 3. Permanent casings m
3. Barrette piles 4. Reinforcement straight t
bars
5. Reinforcement helical t
bars
6. Concreted length m
7. Cut-off piles nr
8. Preparing head nr
4. Caisson piles 1. Depth excavated m
2. Excavation through rock m
3. Permanent casings m
4. Reinforcement bars t
5. Concreted length m

H7
Copyright@CIDB.Malaysia2018

MyCESMM2
C7 Class H – Piling Work
Items for provision shall
be deemed to include
provision of all
necessary piling plant
and equipment,
transportation to the
site, handling, Micropile rig
assembling and
removal off the site
after completion of
operation.

C8
Items for moving and
handling shall be
deemed to include
moving and handling
all piling plant and Borepile rig
equipment within the
site, and from location
to location as often as
is, and whenever
necessary for the
execution of the whole
piling operation.

Copyright@CIDB.Malaysia2018
Hydraulic hammer rig H8

Copyright@CIDB.Malasia.2018 4
CLASS H - PILING WORKS

MyCESMM2
M6 Class H – Piling Work
Each group of items for bored piles, C9
barrette pile, driven cast in situ Items for bored piles and barrette piles
concrete piles, and caisson piles shall shall be deemed to include temporary
comprise casings, stabilising agent, and enlarged
a) An item for the total depth bored or base.
total depth driven or total depth
excavated, stating total number of C10
pile points, and
Items for boring and excavation
b) An item for the total concreted
through rock shall be deemed to
length of piles include natural and artificial hard
materials including backfilling bore with
D1 stated materials.
Piles consisting of driven permanent
steel casing, which is filled with
concrete, shall be classified as driven
cast in situ piles where the piles are
designed for the load to be carried on
the concrete.

D2
The nominal diameter used for
classification of bar reinforcement shall
be the cross sectional diameter defined
in BS 4449 or MS 146.

Copyright@CIDB.Malaysia2018
“Reaching the sky” H9

MyCESMM2
C11 Class H – Piling Work
Items for permanent casing shall be deemed to include the supply and jointing of
casings, driving heads, and shoes, where applicable.

A10
Item description for bored, cast in place, barrette piles and caisson piles shall state
the diameter.

A11
Item description for bored piles shall state contiguous bored piles where
applicable.

Bored pile
construction

Copyright@CIDB.Malaysia2018
H10

Copyright@CIDB.Malasia.2018 5
CLASS H - PILING WORKS

MyCESMM2
Class H – Piling Work
A12
Item description for permanent casings shall state materials, thickness, and details
of treatments and coating.

M7
The lengths of permanent casings for bored piles shall be measured from the cut-
off level to the bottom of the casings. The length of permanent casing for driven
cast in situ concrete piles shall be measured from the cut-off levels to the toe
levels.

Barrette pile
construction

Copyright@CIDB.Malaysia2018
H11

MyCESMM2
C12 Class H – Piling Work
Items for reinforcement shall be deemed to include supporting reinforcement.

C13
Items for driven cast in situ concrete piles shall be deemed to include pre-boring,
where applicable.

A13
Item description for concreted length shall state when required particular method
of concrete placement, concrete grade, poured at a stated speed,
temperature, compacted or cured in a particular method.

Driven cast in-situ concrete pile construction

Copyright@CIDB.Malaysia2018
H12

Copyright@CIDB.Malasia.2018 6
CLASS H - PILING WORKS

MyCESMM2
M8 Class H – Piling Work
The length of permanent casings for
caisson piles shall be measured from
the top of casing to the bottom of the
casings.

M9
The mass of steel reinforcement shall be
taken as 0.785 kg/m per 100 mm² of
cross section (7.85 t/m³). The mass of
other reinforcing materials shall be
taken as stated in the contract.

D3 Caisson pile
Piles comprising placement of
permanent concrete or steel casing,
where the material within the casing is
excavated and filled with concrete,
shall be classified as caisson piles when
the piles are designed for the load to
be carried on the concrete.

Copyright@CIDB.Malaysia2018
H13

MyCESMM2
Class H – Piling Work

MyCESMM2 Library Description


H100 PLANT AND EQUIPMENT
H110 Provision of all necessary piling plant and equipment, transportation sum
to the site, handling, assembling, and removal off the site after
completion of operation

H200 PILES
Bored piles; [900 mm] diameter bored piles as working piles, include
temporary casings, stabilising agent, and enlarged bases. Piling
records and disposal of excavated and surplus materials ( In no…)
H211.1 Depth boring in earth; [ up to (20 m) for (... Nos). of pile points ] m

Caisson piles; [2500 mm diameter caisson piles as working piles. In


no....]
H241 Depth excavate [in earth, up to (20 m) for (21) nos. of pile points] m

Copyright@CIDB.Malaysia2018
H14

Copyright@CIDB.Malasia.2018 7
CLASS H - PILING WORKS

MyCESMM2
Class H – Piling Work

First division Second division Third division Unit


2. Piles 5. Micropiles 1. Depth bored m
2. Boring through rock m
3. Steel pipe as m
reinforcement
4. Reinforcement bars t
5. Grouting m3
6. Cut-off piles nr
7. Preparing head nr
8. Permanent casing m

6. Precast reinforced 1. Supply of piles nr


concrete piles 2. Depth driven m
7. Precast prestressed 3. Pre-boring m
concrete piles 4. Jointing nr
5. Filling hollow piles with m
concrete
6. Cut-off piles nr
7. Preparing head nr

H15
Copyright@CIDB.Malaysia2018

MyCESMM2
M10 Class H – Piling Work
The mass measured for reinforcement shall
include the mass of reinforcement expressly
required in laps.

M11
The length of steel pipe casing shall be
measured from top of pipe to toe.

C14
Items for boring through rock shall be deemed
to include artificial hard materials.

C15
Items for steel pipe as reinforcement shall be
deemed to include jointing/welding.

A14
Item description for micropiles shall state the
diameter.
Micropile
A15
Item description for grouting shall state the
grout design mix and/or strength.

Copyright@CIDB.Malaysia2018
H16

Copyright@CIDB.Malasia.2018 8
CLASS H - PILING WORKS

MyCESMM2
M12 Class H – Piling Work
Each group of items for precast reinforced
and precast prestressed concrete piles
shall comprise
a) one or more items for the number of
piles of stated length; and
b) an item for the total depth driven RC pile

D4
The supply lengths of precast reinforced
concrete piles and precast prestressed
concrete piles shall be the total number of
piles of stated lengths expressly required to
be supplied.

C16
Items for filling hollow piles with concrete
shall be deemed to include removal of
materials from within the piles before
concreting.

A16
Item description for filling hollow piles with
concrete shall state the specification of
the concrete and reinforcement.
Spun pile
Copyright@CIDB.Malaysia2018
H17

MyCESMM2
Class H – Piling Work

MyCESMM2 Library Description

H200 PILES
Micropiles; Supply and install [200 mm] diameter micropiles as
working piles (in no..)] m
H251 Depth boring in [ earth, up to [20 m] for [30] nos. of pile points ]

H255 Grouting with non-shrink cement grout Grade [C30] as specified into m3
drilled hole

Precast Reinforced Concrete Piles; [200 mm] G40 square precast


reinforced concrete piles with a working load of [….] kN
H262.1 Depth driven m

H271.1 Supply initial pile with rock shoes of [12 m] length nr

Copyright@CIDB.Malaysia2018
H18

Copyright@CIDB.Malasia.2018 9
CLASS H - PILING WORKS

MyCESMM2
Class H – Piling Work
First division Second division Third division Unit
2. Piles 8. Steel H-pile 1. Supply nr
2. Depth driven m
3. Pre-boring m
3. Piles 1. Steel pipe pile 4. Filling hollow piles with m
concrete
5. Cut-off piles nr
6. Jointing nr
7. Preparing head nr
2. Timber piles 1. Supply nr
3. Precast concrete 2. Depth driven m
sheet piles 3. Pre-boring m
4. Precast prestressed 4. Jointing nr
concrete sheet 5. Cut-off piles nr
piles 6. Preparing head nr
7. Jetting m
2. Interlocking steel 1. Supply m
sheet pile 2. Depth driven m2
3. Pre-boring m
4. Jetting m
5. Special pile m
6. Cut-off piles m
7. Ground anchorages nr
H19
8. Preparing head m
Copyright@CIDB.Malaysia2018

MyCESMM2
D5 Class H – Piling Work
The supply lengths of steel H-piles and
steel pipe piles shall be the total
number of piles of stated lengths
expressly required to be supplied.

A17
Item description for supply of steel H-
piles and steel pipe piles shall state the
mass per meter, cross-sectional
dimensions and grade of steel, length
and concrete infill, where applicable.

A18 H-pile
Item description for steel H-piles and
steel pipe piles shall state details of
treatments, coatings and cathodic
protection where required.

A19
Item description for steel H-piles and
steel pipe piles shall state type of
jointing.

Steel pipe pile H20


Copyright@CIDB.Malaysia2018

Copyright@CIDB.Malasia.2018 10
CLASS H - PILING WORKS

MyCESMM2
M13 Class H – Piling Work
The areas of driven precast prestressed
concrete sheet piles shall be
calculated by multiplying the horizontal
lengths of the pile walls formed by the Timber pile
average depths measured from the (damaged)
cutoff levels.

D6
The lengths of timber piles and precast
concrete sheet piles shall be the total
number of piles, of stated lengths,
expressly required to be supplied.
PC concrete
C17 sheet pile
Items for jetting deemed to include jet
pipes, hoses and jet pump.

A20
Item description for supply of timber
piles shall state the grade of timber,
cross-sectional dimensions, length and
any pressure treatment required. Prestressed
concrete
sheet pile

Copyright@CIDB.Malaysia2018
H21

MyCESMM2
A21 Class H – Piling Work
Item description for supply of precast and
prestressed concrete sheet piles shall
state thickness, length and width.

M14
The areas of driven interlocking steel
sheet piles shall be calculated by
multiplying the mean undeveloped
horizontal lengths of the pile walls formed
(including lengths occupied by special
piles) by the depths measured from cut-
off levels to the toe levels.

Interlocking steel sheet pile


M15
Closure and taper piles classed as
special piles shall be measured only
where they are expressly required.

M16
The lengths measured for cutting of
surplus lengths of interlocking steel sheet
piles shall be the mean undeveloped
horizontal lengths to be cut (including
lengths occupied by special piles).

Copyright@CIDB.Malaysia2018
H22

Copyright@CIDB.Malasia.2018 11
CLASS H - PILING WORKS

D7 MyCESMM2
Class H – Piling Work
Interlocking steel corner, junction,
closure, and taper piles shall be A25
classified as special piles. Item description for ground anchorages
D8 shall state the composition and working
The supply lengths of interlocking steel load
sheet piles shall be the total length
expressly required to be supplied.

A22
Item description for interlocking steel
sheet pile shall state the section
reference or mass per metre and
section modulus.
A23
Item description for supply area of piles
shall state details of treatment and
coatings required.
A24
Item description for special piles shall
state the type and length.
A25
Item description for ground anchorages
shall state the composition and working
load

Ground anchor
Copyright@CIDB.Malaysia2018
H23

MyCESMM2
Class H – Piling Work

MyCESMM2 Library Description


H200 PILES
Steel H-Piles; 533 mm x 210 mm x 138 kg/m UB Grade 43A including
cathodic protection using the impressed current system as per
Specification clause (…..)
H281 Supply of steel H-piles with metal-filled primers of [6 m] length nr

Steel pipe piles; Supply and install [323.9 OD x 10 mm thick x 77.4


kg/m] mild steel pipe piles Grade 43A.in no ...]
H314 Filling hollow piles with concrete grade [C30] m

Precast prestressed concrete sheet piles; [996 mm wide x 325 mm


high x 110 mm thick] with cross section area of 1315 cm2 precast
prestressed concrete sheet piles. In no...]
H341 Supply in [12 m] length nr

Interlocking Steel Sheet Piles; Interlocking Grade 43A steel sheet piles,
[Z-section] , at 66.1 kg/m, section modulus of 1200 cm³/m
H351 Supply in [12 m] length m

Interlocking Steel Sheet Piles; Interlocking Grade 43A steel sheet piles,
[Z-section] , at 66.1 kg/m, section modulus of 1200 cm³/m
H352 Depth driven m2

Copyright@CIDB.Malaysia2018
H24

Copyright@CIDB.Malasia.2018 12
CLASS H - PILING WORKS

MyCESMM2
Class H – Piling Work
First division Second division Third division Unit
4. Miscellaneous 1. Obstruction 1. Excavation through m
work obstruction

5. Pile tests 1. Static load/ nr


maintained load
2. Pile dynamic nr
analyser
3. Pile integrity nr
4. Sonic logging nr
5. Lateral nr
6. Statnamic nr
7. Bi-directional static nr
load
8. Global strain nr
extensometers
static load

6. Pile tests 1. Plate loading nr


2. Shaft friction nr

H25
Copyright@CIDB.Malaysia2018

MyCESMM2
M17 Class H – Piling Work
Excavation through obstructions shall
be measured only for breaking out
obstructions or artificial hard materials
encountered above the founding
stratum.

A26
Item description for excavation through
obstruction shall state the cross
sectional dimension or diameters of the
excavation.

C18 Static load test


Items for pile test deemed to include
necessary equipment, inserts and
accessories.

A27
Item description for static load test shall
state the test loads. Where the load is
applied to raked piles, it shall be so
stated.

Pile dynamic analyser


Copyright@CIDB.Malaysia2018
H26

Copyright@CIDB.Malasia.2018 13
CLASS H - PILING WORKS

MyCESMM2
A28 Class H – Piling Work
Item description for pile test shall
identify those which are for preliminary
piles.

A29
Item description for plate loading test
and shaft test shall state type of pile
and identify location of pile test.

Pile integrity test

Pile sonic logging Pile lateral test


Copyright@CIDB.Malaysia2018
H27

MyCESMM2
Class H – Piling Work

Plate bearing test Statnamic

Bi-directional static load test

Copyright@CIDB.Malaysia2018
H28

Copyright@CIDB.Malasia.2018 14
CLASS H - PILING WORKS

MyCESMM2
Class H – Piling Work

MyCESMM2 Library Description

H400 MISCELLANEOUS WORK


Obstructions
H411 Excavation through obstructions for [900 mm diameter bored piles] m

H500 PILE TESTS


H510.1 Initial static load test on 900 mm diameter bored pile up to two times nr
working load of 16,000 kN

H530 Pile integrity test (sonic echo test) on [300 mm] diameter prestressed nr
concrete pile

H570 Bi-directional static load test [ on 900mm diameter bored pile; up to nr


two times working load of ......kN]

H610 Plate loading test [type of pile....; state location of test....] nr

Copyright@CIDB.Malaysia2018
H29

MyCESMM2
Class H – Piling Work

THE
END
Crane
suspended
hammer
mounting type H30
Copyright@CIDB.Malaysia2018

Copyright@CIDB.Malasia.2018 15