State Plan, (Line)

1. Name Of Work Re-conductoring of existing 132 kV Fatuha- Gaighat (D/C)


Transmission line with ACCC HTLS Panther Equivalent Conductor.(Line Length – 27 KM) (NIT-
82/PR/BSPTCL/2015)

2. Project Cost (Rs Cr) -52.04 Cr


3. Agency -M/S KEC International Ltd.
4. LOI Date -12.07.2016
5. SDOC -11.04.2017
6. Likely Date of Completion - 11.04.2017
7. Project Team :- Sri Chittranjan Roy (E.S.E.), Sri Ravi Shankar(EEE) & Sri M.K.Sharma (A.Ex.E.)

Total Qty Scheduled Actual Actual Payment ( Rs. Cr.) Remarks


(30.09.2016) (31.08.2016) (15.10.2016)
Fund Released Fund Pending
for payment
Tower Materials(MT) 20.5

Conductors(Km) Approval of
165 Conductor , Tower
schedule &
Hardware Fittings & 100 hardware Fitting
Accessories(%)
items.

Stringing (Km) 27 Inspection of


Hardware
fitting items
Foundation(%) 100 DI of
conductor
issued.
1
Commissioning(%)
State Plan, (Line)
1. Name Of Work Re-conductoring of existing 132 kV Gaurichak – Jakkanpur (D/C)
Transmission Line with ACCC HTLS Panther Equivalent Conductor.(Line Length – 18 KM )
(NIT-82/PR/BSPTCL/2015)

2. Project Cost (Rs Cr) -52.04 Cr


3. Agency -M/S KEC International Ltd.
4. LOI Date -12.07.2016
5. SDOC -11.04.2017
6. Likely Date of Completion - 11.04.2017
7. Project Team :- Sri Chittranjan Roy (E.S.E.), Sri Ravi Shankar(EEE) & Sri M.K.Sharma (A.Ex.E.)
Total Qty Scheduled Actual Actual Payment ( Rs. Cr.) Remarks
(30.09.2016) (31.08.2016) (15.10.2016)
Fund Released Fund Pending
for payment
Tower Materials(MT) 20.5 .

Conductors(Km) 110 Approval of


Conductor , Tower
Hardware Fittings & 100 schedule &
Accessories(%) hardware Fitting
items.

Stringing (Km) DI of conductor


18 issued

Foundation(%)
Commissioning(%)