You are on page 1of 7

HMD-UN PROJECT

Monthly Meeting Presentation


(From 1-Dec to 28-Dec)

Hassi Messaoud January-2019


1. HSE

2
HSE
Safety Statistic as of 28-December-2018
Man-Hour worked / Last LTI
1 825 488

Direct Work Location: Hassi Messaoud


2017 2018 2019
Last month
November
Current month
December
PTD

HSE STATISTIC
Days without work due to bad weather - 15 - 0 0 15

Objectives of the Project: PTD Man-Hour worked 33 380 1 531 111 0 332 568 294 377 1 825 488
- LTIFR < 0.02 0,00 Personnel on Site for the week Direct 686 Indirect 629
- TRIFR < 0.15 0,11
Ratio HSE Direct/ Personnel Direct 1 HSE for every 50 Employees

Date Cat Short description Number


Property Damage A pick up truck came into contact with the height restriction barrier when the driver's
10-Dec JGC-PD-08
(JGC) view was glared by the sunlight.
First Aid Case A scaffolder sustained a minor scratch when his hand came into contact with a rebar
12-Dec JGC-FAC-10
(RHI) tie wire.
First Aid Case A rebar worker sustained a superficial lacertation on his left hand 2nd finger when he
19-Dec JGC-FAC-11
(RHI) came into contact with a end of a rebar tie wire.
Near Miss Case During lifting of a steel structuer frame one of the slings slipped away by about 10cm
26-Dec JGC-NM-09
3 (ENT) from its anchor position due to unknown COG and single choke.
S Curve – Construction Progress

 Month Progress: Planned 4.51% vs Actual 4.59%


 Cumul Progress: Planned 21.13% vs Actual 21.24%

4
Progress Contributor

∑Plan – 21.13%
∑Actual – 21.24%

5
Subcon Direct Manpower

 CSSI Direct Mobilization ~ 200 Workers  +2


 RHI Direct Mobilization is ~ 206 Workers  +28
 ENTREPOSE Direct Mobilization ~ 89 Workers  -4
 INTERSUD Direct Mobilization ~ 66 Workers  +29
 TGCTP Direct Mobilization ~ 60 Workers  +47
6