You are on page 1of 8

What are the paths to completion and their durations?

6 3 2 5

A B C D

Start
End

2 1 6 4

E F G I

H
Complete the forward pass.

6 3 2 5

A B C D

Start
End

2 1 6 4

E F G I

H
Complete the backward pass.

6 3 2 5

A B C D

Start End

2 1 6 4

E F G I

H
Expose the float.

6 3 2 5

A B C D

Start End

2 1 6 4

E F G I

H
What are the paths to completion and their durations? ABCD = 16
EFGI = 13
EFHI = 14

6 3 2 5

A B C D

Start End

2 1 6 4

E F G I

H
Complete the forward pass.

1 6 6 7 3 9 10 2 11 12 5 16

A B C D

Start End

1 2 2 3 1 3 4 6 9 11 4 14

E F G I

4 7 10

H
Complete the backward pass.

1 6 6 7 3 9 10 2 11 12 5 16

A B C D

1 6 7 9 10 11 12 16

Start End

1 2 2 3 1 3 4 6 9 11 4 14

E F G I

3 4 5 5 7 12 13 16

4 7 10 You can finish no later than Day


16, the last day of the critical
H path.

6 12
Expose the float.

1 6 6 7 3 9 10 2 11 12 5 16

A B C D

1 0 6 7 0 9 10 0 11 12 0 16

Start End

1 2 2 3 1 3 4 6 9 11 4 14

E F G I

3 2 4 5 2 5 7 3 12 13 2 16

4 7 10

6 2 12

You might also like