What Are The Paths To Completion and Their Durations?
What Are The Paths To Completion and Their Durations?
6 3 2 5
A B C D
Start
End
2 1 6 4
E F G I
H
Complete the forward pass.
6 3 2 5
A B C D
Start
End
2 1 6 4
E F G I
H
Complete the backward pass.
6 3 2 5
A B C D
Start End
2 1 6 4
E F G I
H
Expose the float.
6 3 2 5
A B C D
Start End
2 1 6 4
E F G I
H
What are the paths to completion and their durations? ABCD = 16
EFGI = 13
EFHI = 14
6 3 2 5
A B C D
Start End
2 1 6 4
E F G I
H
Complete the forward pass.
1 6 6 7 3 9 10 2 11 12 5 16
A B C D
Start End
1 2 2 3 1 3 4 6 9 11 4 14
E F G I
4 7 10
H
Complete the backward pass.
1 6 6 7 3 9 10 2 11 12 5 16
A B C D
1 6 7 9 10 11 12 16
Start End
1 2 2 3 1 3 4 6 9 11 4 14
E F G I
3 4 5 5 7 12 13 16
6 12
Expose the float.
1 6 6 7 3 9 10 2 11 12 5 16
A B C D
1 0 6 7 0 9 10 0 11 12 0 16
Start End
1 2 2 3 1 3 4 6 9 11 4 14
E F G I
3 2 4 5 2 5 7 3 12 13 2 16
4 7 10
6 2 12