Professional Documents
Culture Documents
By Mahendrakumar Patel
2. PROCESS OVERVIEW
1) Purpose
2) Basis of Design
3) Process Description
1 INTRODUCTION
1. Introduction of Training Course Contents 09.00 to 09.20
2. Introduction of Training Schedule
2 PROCESS OVERVIEW
2. Process Principle 09.20 to 09.35
3. Basis of Design
3 PROCESS FLOW AND CONTROL
1) Process Variables 10.00 to 10.45
2) Major Equipment
3) Complex Control Logic
4 START-UP AND SHUTDOWN
Purpose :
The system provides the supply of refinery fire water to refinery area.
Four Firewater Main Pumps: 681.3 m3/hr with 10.5 kg/cm2g each
Two Electric Motor Driven Pumps + Two Diesel Engine Driven Pumps
Worst Fire Scenarios :
Firewater
FIRE ZONE Fire Fighting Facilities Applied Demand
(m3/hr)
Tank Farm Unit (U52) Water Spray / Foam Injection System 1,142.2
Jockey Pump
Fire Fighting Tools and Hose Reel Portable Foam Feeder Portable Hydrant Spray Nozzle
9. Fire Fighting System
Deluge SystemDeluge
system worrk_360p.mp4
Simplified PFD
Filtered
Water
Fire Water
To
Network
AG UG
3A AREA
UNIT 31
2. PROCESS OVERVIEW (Continued) Page : 7 / 19
UNIT 31
2. PROCESS OVERVIEW (Continued) Page : 8 / 19
- Plot plan
2. PROCESS OVERVIEW (Continued) Page : 9 / 19
- 3D Model
2. PROCESS OVERVIEW (Continued) Page : 10 / 19
- Process Description
All firewater pumps has its own pressure sensing instruments to run the pump, when the set pressures are
reached.
The set pressure and the operating sequence are as per below;
3. PROCESS FLOW AND Page : 11 / 19
CONTROL
- Process Variable
The most important and critical variables for the Fire Water Unit are:
Liquid level of Firewater Tank (31-TK-001)
The correct fire water level inside the firewater tank is essential:
The correct fire water level inside the firewater tank is essential:
Time shall be secured to open the PIV which isolates the firewater network of Refiner and
Depot area.
- Major Equipment
Firewater make-up is taken from Filtered Water Storage Tanks (30-TK-001A/B) by Filtered Water
Pumps (30-P-002A/B/C).
Working volume is 8,857 m3, which is based on 6.5 hour supply under firewater pumps rated
capacity of 1,362.6 m3/h.
Tank is fixed roof atmospheric type. They are commonly used to store large
(
Item dedicated to allow the time delivering firewater from Depot area.
Working volume is 113.6 m3, which is based on 5 minutes supply under firewater pumps rated
capacity of 1,362.6m3/h.
Since the lead jockey pumps(31-P-002A) circulates to the fire water tank only, piping boot is
traced for winterization.
3. PROCESS FLOW AND CONTROL (Continued) Page : 13 / 19
- Major Equipment :
Fire Water Pump (31-P-001A/B/C/D)
Four pumps (two first duty and two stand-by) with 2 X 50% (681.3 m3/h) rated
capacity are provided.
31-P-001A/B are electric motor driven / 31-P-001C/D are diesel engine driven.
Two pumps (one lead and one lag) with 60m3/h rated capacity each.
Acts as main pressurizer of the firewater network and provides capacity for
small firewater draw-offs such as fire hoses.
Lead jockey pump (31-P-002A) remains in operation all the time circulating
through spillback line to firewater tank.
4. START- UP AND Page : 14 / 19
SHUTDOWN
- Start-up Procedure
4. START- UP AND SHUTDOWN (Continuted) Page : 15 / 19
Ensure the block valves to pump suction lines are in closed position.
When water level reaches 1.0%, change the mode of 31-LIC-0001A / 31-LIC-0002 to Auto.
4. START- UP AND SHUTDOWN (Continuted) Page : 16 / 19
Make sure level of tank 31-TK-001 is higher than 20% of the level indicator with
At the end of water filling, water make-up valves (31-LV-0001A) will be almost
closed.
Start 31-P-001A.
Check the pump conditions such as vibrations and noises.
Adjust the opening of discharge block valve to achieve discharge pressure (31-PG-0001A)
and then open fully.
When firewater network pressure reaches 10.5kg/cm2g through 31-PI-0001,
stop the firewater pump (31-P-001A) and start the lead jockey pump(31-P-002A) to maintain
the network pressure.
Switch the operation of firewater pumps (31-P-001A/B/C/D) and jockey pumps (31-P-002A/B)
into Auto mode.
4. START- UP AND SHUTDOWN (Continuted) Page : 17 / 19
3. Biocide Injection :
For initial start-up, about 14kg of Biocide shall be dosed into the system.
injected.
1) Open valves 1, 2, 3 and pour in about 2L at a time and close valve 1.
2) Slowly open valve 4 and inject the Biocide. 1~2minutes later, close valve 2,3,4 and drain the remaining through valve 5.
3) After checking the pressure inside dosing pot by 31-PG-0005, close valve 5 and repeat the process again to meet the
target quantity.
4. START- UP AND SHUTDOWN (Continuted) Page : 18 / 19
4.
Firewater Piping Boot Operation :
In case of abnormal conditions such as firewater tank water
level low or failure,
Firewater system from Depot area shall be shared with
refinery area.
To ensure the time required to open the isolation valves
between two firewater network, ……….firewater piping
boot shall be operated.
Shutdown Procedure :
Firewater operation must be maintained to secure refinery anytime since flammable
materials are handled,
Firewater system shall not be shutdown.
Thus manual shutdown is not applied to firewater system.
Partial Shutdown
Although the fire water system is for intermittent use, there are very low possibilities for the
maintenance of firewater pumps.
2) Regardless of the maintenance, all other firewater pumps shall be ready for operation at
all times.
3) Firewater pumps maintenance of unit 31 and 90 shall not be conducted at the same time.
4) At firewater pump maintenance, operator shall be ready for the Firewater piping boot
operation in case of emergencies.
Thanks Any Question
Jockey Pump