Professional Documents
Culture Documents
C324 Construction
Road & Marine Application
Day 18
Kelera Loma Mataika
Design+Tenders Contact Types Construction Equipment
CONSTRUCTION PHASES 1
https://vro.agriculture.vic.gov.au/dpi/vro/vrosite.nsf/pages/soilhealth_toolbox_tracks_roads_construction
Design+Tenders Contact Types Construction Equipment
8. ELEMENTS+
9.ROAD ENVIRONMENT Drainage inlets/boxes, irrigation
UTILITY CONSTRUCTION
SEQUENCE OF WORKS INSTALL structures, manholes+pipes is
located and built as far as INSTALL
1.CONSTRUCTION STAKING STORM WATER DRAIN possible prior to finishing ISLANDS< BARRIERS,
ORAD subgrade.
- ROUGH STAKING UTILITIES + LINES
MARKINGS+LIGHTING &
Translate geometry on paper to ground SEAL ROADS
Recon work on path suitability of design to site SIGNAGE
-this informs construction programme SIGNAL HEADS
Schedule of work stages, MANHOLE
Schedule/Budget Staff+Material delivery,
Equipment selection 7.PAVEMENT
10. COMMISSIONING OF
2.PROGRAMME FINALISED CONSTRUCTION
ROAD
EQUIPMENT DECIDED ON KERB INSTALL
Best Management Practice 4.EARTHWORKS 5.EARTHWORKS +BUILD UP BASE
Project Design Features LAYERS
EIA + Geometry drawings
GRUBBING & CLEARING SUB GRADE
+ budget + Right of way cleared and no more EXCAVATION + BITUMEN COATS
best to not disturb soil.a ll logs
SUBGRADE EXCAVATION
3.FINE LINE & used in retaining elements
+ Trees felled w bark at 1.2m high -STRIPPING
GRADE + Top soil stockpiled Non structural soils 6.EMBANKMENT
STAKING + Install safety barriers +fencing -FOUNDATION FOR CONSTRUCTION
Accurate Levels + STRUCTURES LAYERING+COMPACTION
Alignments staked Drainage culverts, sewer lines, -REINFORCE DRAINAGE
Site prepped, collection ponds Access tunnels,
-LAY CULVERT+LINES
Site Drainage -SITE DRAINAGE
Ensure site is drained well+runoff
https://austroads.com.au/publications/pavement/agpt04e
Design+Tenders Contact Types Construction Equipment
1. Step 1: Planning.
3. Step 3: Earthworks.
4. Step 4: Paving.
https://vro.agriculture.vic.gov.au/dpi/vro/vrosite.nsf/pages/soilhealth_toolbox_tracks_roads_construction
Design+Tenders Contact Types Construction Equipment
This involves identifying any hazardous areas where work needs extra
precautions and setting up appropriate traffic control measures. The BMPs
(Best Management Practice) and PDFs (Project Design Features)are an
integral part of the Proposed Action and were developed to avoid or
reduce the potential for adverse impacts to resources
https://vro.agriculture.vic.gov.au/dpi/vro/vrosite.nsf/pages/soilhealth_toolbox_tracks_roads_construction
Design+Tenders Contact Types Construction Equipment
https://vro.agriculture.vic.gov.au/dpi/vro/vrosite.nsf/pages/soilhealth_toolbox_tracks_roads_construction
Design+Tenders Contact Types Construction Equipment
• 4) Use Google to review Ariel photographs- look for tells if the previously
disturbed area is evident.
Working outside the road prism without going through environmental review risks
disturbing unrecognized cultural or biological resources or hazardous materials.
Design+Tenders Contact Types Construction Equipment
https://eplanning.blm.gov/public_projects/2017596/200510206/20054081/250060264/Appendix%20A%20BMPs%20and%20PDFs.pdf
Design+Tenders Contact Types Construction Equipment
https://eplanning.blm.gov/public_projects/2017596/200510206/20054081/250060264/Appendix%20A%20BMPs%20and%20PDFs.pdf
Design+Tenders Contact Types Construction Equipment
https://eplanning.blm.gov/public_projects/2017596/200510206/20054081/250060264/Appendix%20A%20BMPs%20and%20PDFs.pdf
Design+Tenders Contact Types Construction Equipment
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
1. ROUGH STAKING
Rough grade staking defines the proposed
location and grade of site improvements by
mapping out its slopes, parking, streets, and
buildings for the purposes of land clearing
and getting the land leveled and ready for
construction. Essentially, the purpose of
rough grade staking is to ensure that the
topography of the build site is suitable for
the project. As this staking is mostly to define
rough locations and elevation, it is not nearly
as precise as site layout staking.
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
https://jbpro.com/construction-staking/
Design+Tenders Contact Types Construction Equipment
2. identify potential problems or conflicts between field conditions and design plans early on, which is
invaluable as even the simplest mistakes can negatively affect the entire project.
3. provides a tangible guideline for construction crews to visualize the construction design conditions
as a whole.
4. helps a construction project stay on time and within budget, eliminating the potential for
inaccurate installations that may have to be removed and re-constructed. It is always more
manageable and less costly to preemptively fix issues before construction begins rather than waiting
until it is well underway.
5. the surveyor develops the necessary data to produce final as-built drawings, which are often
required for many construction projects
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
Starting the cut at the proper point becomes more important as the side slope increases.
As a rule, slope stakes should be set when sideslopes exceed 40 to 45 percent
depending on the sensitivity of the area and the operator's experience.
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
C324 Construction
Road & Marine Application
Day 19
Kelera Loma Mataika
Design+Tenders Contact Types Construction Equipment
Table lists common
road construction
Steps of Road Construction equipment and their
Step 3: Earthworks : EQUIPMENT SELECTION suitability for the
different phases of road
construction
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
2. Earth is moved down-grade with the aid of - sideslopes do not exceed 45 to 55 percent
gravity, not up-grade.
- proper compaction equipment is available
3. Fill material is borrowed rather than pushed such as a "grid roller" or vibrating or tamping
or hauled farther than the economic limit of roller
the bulldozer.
- fills have a sufficient width to allow passage
4. Rock outcrops should be bypassed. Unless of either compaction equipment or
substantial rock blasting is specified requiring construction equipment, such as dump
drilling and blasting equipment, solid rock trucks
faces should be avoided (This, however, is
- Bulldozer can not adequately compact
primarily a road locator's responsibility.) https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
https://www.fao.org/3/T0099E/T0099e06.htm
Design+Tenders Contact Types Construction Equipment
The excavator production rate approaches the dozer production rate as side slope increases. There
are now indications that excavator production rates are higher than dozer production rates on slopes
steeper than 50 percent. This difference will increase with increased rock in the excavated material.
The bucket of the excavator is much more effective at ripping than the dozer blade. Excavators are also
more effective at ditching and installing culverts
https://doctordigger.chapter24.blog/kaiser-spider-walking-excavator-takes-you-where-nothing-else-can/
Design+Tenders Contact Types Construction Equipment
https://doctordigger.chapter24.blog/kaiser-spider-walking-excavator-takes-you-where-nothing-else-can/
Design+Tenders Contact Types Construction Equipment
https://www.fao.org/3/T0099E/T0099e06.htm#6.1
Design+Tenders Contact Types Construction Equipment
https://www.fao.org/3/T0099E/T0099e06.htm#6.1
Design+Tenders Contact Types Construction Equipment
Embankment roading
Design+Tenders Contact Types Construction Equipment
-unsuitable material is
cleared and imported
suitable material are layered
and compacted. Wetland
soils are not suitable as
loading bearing material and
will settle over the years
Design+Tenders Contact Types Construction Equipment
In the former case, most if not all of the excavated Material is wasted as loose side
cast material readily available for erosion. In the latter case, it has been
incorporated into the fill, properly compacted, and presumably unavailable for
erosion.
The key to a stable, balanced road design is proper compaction of fill material.
Haber and Koch (1982) quantified costs for erosion and compaction for several
types of sediment control treatments on roads in southwest Idaho. This study
represents an excellent example of applying uniform criteria to examine differences
Design+Tenders Contact Types Construction Equipment
(1)local (Boise) labor and equipment rates, taxes, insurance, and servicing (repair and
maintenance) including 10 percent profit and risk margin, and
(2) Regional Equipment Blue Book Guidebook which include margins for profit and risk, fuel, oil,
lubrication, repairs, maintenance, insurance, and incidental expenses. After actual costs for
each activity were calculated, average cost per unit and average crew cost was determined
based on design quantities. A comparison was then made between actual costs for "non-
standard" treatments and actual costs of standard treatments.
Average observed production rates for all activities were calculated for use in predicting time and
costs associated with "non-standard" construction techniques. Figure 116 illustrates an example of
their results in determining the cost of three different methods of embankment placement. These
methods are: (1) side cast embankments with no compactive effort, (2) layer placed (less than 30
cm (12 in) thick) embankments in which each layer is leveled and smoothed before each
subsequent layer is placed (some compaction is obtained during the leveling process as the
bulldozer passes over the material), and (3) controlled compaction in which embankments are
placed in layers (less than 20 cm (8 in) thick) followed by compaction with water and vibratory roller
to achieve relative density of 95 percent.
Design+Tenders Contact Types Construction Equipment
It is worth noting that production rates of manual labor for excavation work are generally 3.8 to 4
m3 (5 yd.3) of dirt during eight hours of work (Sheng, 1977). However, these rates will vary widely
depending on terrain, soil, environmental, and psychological conditions of the work crew.
Design+Tenders Contact Types Construction Equipment