You are on page 1of 13

2900292103

PROJECT LESAFFRE SARI NUSA

WWTP 3100 M3/DAY


SITE PROGRESS REPORT
29 Dec 22~04 Jan’22

PREPARED BY
Nur Ahmad ( NUA )

VEOLIA WATER TECHNOLOGIES INDONESIA

ÉVÉNEMENT - date 1
CONTENT

1. Overview
2. Site Progress
3. Site Progress and Photo
4. PID Mark up Attachment
5. Electrical progress
6. Attachment
• Mechanical & Electrical Status installation
• PID mark up progress

ÉVÉNEMENT - date 2
1. OVERVIEW

ÉVÉNEMENT - date 3
2. SITE PROGRESS

ÉVÉNEMENT - date 4
2. SITE PROGRESS

ÉVÉNEMENT - date 5
2. SITE PROGRESS

ÉVÉNEMENT - date 6
3. SITE PROGRESS AND PHOTO
PRE TRATMENT AND AEROBIC TREATMENT

1. Overflow pipe from Equalization Tank to Pre DN = Installed

2. Discharge piping line for CT Feed Pumps On progress

3. Preparation install Effluent pipe UASB Settler = Installed

ÉVÉNEMENT - date 7
3. SITE PROGRESS AND PHOTO
PRE TRATMENT AND AEROBIC TREATMENT

Piping line from CT Feed Pumps to the


Conditioning Tank on progress

ÉVÉNEMENT - date 8
3. SITE PROGRESS AND PHOTO
CALAMITY TANK

1. Additional pipe inside of the Tank for suction =

Install support and Pipe 80%

ÉVÉNEMENT - date 9
3. SITE PROGRESS AND PHOTO
AERATION TANK

Continue install Valve and Suction line for No3 RAS pumps and
Discharge line on progress

ÉVÉNEMENT - date 10
4. PID Mark Up Progress
29 ~ 05 Jan 2023

ÉVÉNEMENT - date 11
5. ELECTRICAL & INSTRUMENTATION PROGRESS

ÉVÉNEMENT - date 12
6. ATTACHMENT

Thank You
ÉVÉNEMENT - date 13

You might also like