RESIDENC
ES
TECHNICAL AND FINANCIAL
PROPOSAL FOR REPLACEMENT
OF FLOOR FINISHES AND
CONSTRUCTION OF KITCHEN
CABINET
P R E P A R E D B Y: E N G R . W I L L I A M N O E L P. S A N T I A G O
CONTENT
PROJECT OVERVIEW
KEY PLAN
ACTUAL PHOTOS
SCOPE OF WORK
MATERIAL SPECIFICATION
FINANCIAL PROPOSAL
PROJECT
OVERVIEW
PROJECT OVERVIEW
LOCATION : PHASE 6 SUBDIVISION, RODREGUEZ, RIZAL
OWNER : MR. LORENZ PALEC
PROPERTY AREA : 102.00 SQUARE METER
RESIDENTIAL AREA : 73.03 SQUARE METER
GARAGE AREA : 12.00 SQUARE METER
BALCONY AREA :15.00 SQUARE METER
YARD AREA : 53.48 SQUARE METER
OWNER’S INITIATIVE FOR CONSTRUCTION : TO REPLACE EXISTING FLOOR FINISHES AT LIVING ROOM,
HALLWAY AND BEDROOMS, BALCONY AND CONSTRUCTION OF NEW KITCHEN CABINET
CONSTRUCTION DURATION : TWENTY ONE (21) CALENDAR DAYS
KEY PLAN
KEY PLAN
GROUND FLOOR
• LIVING ROOM
• DINING AREA
• KITCHEN
ACTUAL PHOTOS
SECOND FLOOR
• MASTER’S
BEDROOM
• BEDROOM – 1
• BEDROOM – 2
ACTUAL PHOTOS
BALCONY
MATERIAL
SPECIFICAT
ION
MATERIAL SPECIFICATION
Ceramic Tiles Foresta
Ash (20X100CM)
• Balcony
MATERIAL SPECIFICATION
Vinyl Planks Luxury
2.0mm 6x36" Reddish-
Oak
• Master’s Bedroom
• Bedroom 1
• Bedroom2
FINANCIAL
PROPOSAL
FINANCIAL PROPOSAL
UNIT RATE
ITEM DESCRIPTION QUANTITY UNIT TOTAL AMOUNT
MATERIAL LABOR TOTAL
IV Preliminaries
1 General Requirements and Preliminaries
1.01 Mobilization and Demobilization 1.00 lot - 6,250.00 6,250.00 6,250.00
1.02 Temporary Facilities 1.00 lot - 8,750.00 8,750.00 8,750.00
1.03 Housekeeping (Cleaning) 1.00 lot - 6,250.00 6,250.00 6,250.00
1.04 Site Supervision 1.00 lot - 12,500.00 12,500.00 12,500.00
1.05 Drawings 1.00 lot - 5,625.00 5,625.00 5,625.00
1.06 Covid-19 Requirements 1.00 lot - 5,750.00 5,750.00 5,750.00
1.07 Safety Requirements 1.00 lot - 7,500.00 7,500.00 7,500.00