Lifting Plan

Forecourt Structure & Canopy Link

NTI Shell Gading Serpong


Tangerang, Banten
2019
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Description:
 
 Project Type & Site Name : NTI Shell Raya Parung
 Proposed Date: March, 20th 2020
 Description of Lifting Operation : Forecourt Structure & Canopy Link
 JHA/Risk assessment reference : 01
 Permit Issuer: Devi Murdiani
 Permit Holder: Farid Herdiansyah
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Lifting Object:
 
 Weight of load: Steel Structure ± 600 kg
 Dimension of load: length (m) x wide (m)
Steel Structure : 8m x 0,25m
 Weight of load: Steel Structure ± 600 kg
Column HB 250 = 72.4 kg/m x 5 meters
= 362 kg
Approx. = 400 kg
Beam WF 400 = 66 kg/m x 8 meters
= 528 kg
Approx. = 600 kg
Steel Pipe for Canopy Link
= 1280 kg
Approx. = 1300 kg

 Object : Steel Structure (profiled)


Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Job Hazard Analysis
JHA Erection Baja-NTI Serpong.pdf
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Task Detail
1. Toolbox meeting is to be conducted by the site in charge / supervisor before starting that day’s work.
2. Personnel should be informed about the specific hazards involved during that day’s work
3. The work area should be cordoned off with hard barricades (safety cones, caution tapes)
4. Check parts of Equipment by Checklist and must be operated by licensed operator
5. Check lifting slings (wire rope /chain), eyebolts, D-shackles. Specific crane parts and other lifting & lifting
equipment
6. Crane outriggers to be extended and positioned on firm Steel / wooden base plates before start of lift
7. No one other than the operator on duty should travel /stand on crane / heavy equipment
8. Do not lift during windy / thunder storm conditions. Suspend site activities till climate is favorable
9. While crane erection is on, no one should be allowed to be near/under the work areas & crane
10. Always work with caution
11. Do not move within heavy equipment blind spots
12. All equipment to have audible reverse horn & a signal man to warn / guide workers
13. Supervisor to warn & guide workers regarding equipment blind spots
14. No worker to be inside Lifting Radius while equipment are in operation
15. Ensure every single lift item must have tag lines/ Install hold down strap with turn buckle
16. Tighten the bolt at height using Galvanized scaffold.
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Steps Taken To Eliminate Danger To Personnel Involved and Others
(including barriers where appropriate):
1. Check Crane Condition, fit to work before reinforce.
2. Provide Permits, such As JHA, PTW,WCF, Supporting Checklists (Lifting Plan, Lifting & Hoisting and Hot Work)
and get approval from permit Issuer
3. Provide proper outrigger pad (Mandatory)
4. Install hard and mobile barricade
5. Provide Emergency Lay out
6. Enforce ERP plan incase of Emergency
7. Provide First Aid Kit
8. Staff Brief before start of installation
9. Operator are fit to work
10. Conduct Alcohol test
11. Check Scaffolding condition are in Proper Condition
12. Tool box talk checklist and conduct before start of the work
13. Explain work method by Site Manager/Officer and or supervisor
14. DO LMRA before conduct the work and when doing the work.
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Lifting Equipment Lifting Gears

No. Item Brand WLL Qty


Manufacture: ZOOMLION – CHINA 1 Webbing Webster 8 Ton 2ea
2016 sling
Type: Hydraulic Crane 2 Shackle Crosby 1 ton 2ea
D25
S/N: L5E6B3D37GA002588
3 Guide N/A N/A 30m
Max. WLL: 25000 kg rope
SILO valid until: July 2020 12mm

QY25D531R.pdf

Web Slink SN.jpeg


Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Inspection Checklist
(SIO, SILO, Inspection Checklist)
SIO SILO

SIO Ahmad Muhajir.jpeg

Riksa Uji Disnaker Zoomlion QY25D.jpeg

Sertifikat layak fungsi Zoomlion QY25D.jpeg


Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Inspection Checklist
(SIO, SILO, Inspection Checklist)

Equipment Checklist.jpeg
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Zonation & Sequences Arrangement

Jacking Pad
Double Plat 16 mm

Zone-1 Zone-2
Zone-3
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Radius Works Arrangement (ZONE-1)

Jacking Pad
Double Plat 16 mm

Barricade

15m

Barricade
Flag Man

Barricade

18m

Material Barricade
Flag Man

All working area will be conduct Hard Barricade


Lifting start from the longest point from material loading area
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Radius Works Arrangement (ZONE-2)

Jacking Pad
Double Plat 16 mm

Barricade

Barricade

24m
6m

Barricade
Material
Flag Man

Barricade

Flag Man

All working area will be conduct Hard Barricade


Lifting start from the longest point from material loading area
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Radius Works Arrangement (ZONE-3)

Jacking Pad
Double Plat 16 mm

Material

12m

8m

Flag Man
Barricade
Barricade

All working area will be conduct Hard Barricade


Flag Man
Lifting start from the longest point from material loading area
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Working Radius Load Chart

26

1,3 TON

24
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Lifting Study
1. Crane’s Max Capacity for this
installation is 25 tons,
manufacturer: ZOOMLION QY25D.
2. Longest Working Radius Plan for
this work is 24 meters to steel
structure installation point
3. Boom Radius Plan for this work is
34,5 meters Max. Weight / SWL
4. SWL (Safe Working Load
Capacity) for 34,5 meters Boom is
1.3 tons = 1.300 kg
5. Max Weight for steel structure
approximately 600 kg
Lifting Category:
• Non-routine – simple : less than 80%
• Non-routine – complex
• Non-routine – heavy
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Working Radius Load Chart

5,8 TON

20

24
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Lifting Study
1. Crane’s Max Capacity for this
installation is 25 tons,
manufacturer: ZOOMLION QY25D.
2. Longest Working Radius Plan for
this work is 12 meters to steel
structure installation point
3. Boom Radius Plan for this work is
23,5 meters Max. Weight / SWL
4. SWL (Safe Working Load
Capacity) for 34,5 meters Boom is
5.8 tons = 5.800 kg
5. Max Weight for steel structure
approximately 1300 kg
Lifting Category:
• Non-routine – simple : less than 80%
• Non-routine – complex
• Non-routine – heavy
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Traffic Management

Jacking Pad
Double Plat 16 mm

IN OUT
IN OUT
Flag Man

Flag Man
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Emergency Exit Plan

Construction Zone

Assembly Point
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Emergency Contact Number

RUMAH SAKIT AMBULANCE KANTOR POLISI


Eka Hospital BSD Ambulans Polsek Serpong BSD
021-25655555 021-118 021-5384139

Pemadam Kebakaran Power Station


Summarecon Serpong PLN Serpong
021-29177377 021-5372709
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan
Emergency Respon Procedure
Adobe Acrobat
Document
Lifting Plan
Forecourt Structure & Canopy Link
Lifting Plan

End of Document