PT.

LIK -
▣ Renovation Project – CHANG SHIN FACTORY
Times : 8 am – 18.00 pm Times : -

2023-11-14

Progress
Division Unit
Total Before Today Accum. %

ZINCALUM GUTTER 0.4 TCT + ASPALT WATER PROF m1 1,488 0 0 0 0%

GUTTER FRAME ZINCLUM 0.4TCT m1 1,488 130.2 241.8 372 25%

SILICON, RIVET, BOLT SUB MATERIAL m1 1,488 130.2 13.8 144 9.7%

FRP ROOF THICKNESS 1.5T SUSUPUTIH


m1 6,240 0 0 0 0%

FLASING FOR FRP(SAMPING FRP ONLY) 0,3T with


m1 12,480 0 0 0 0%
Water proof type

SCAFOLDING set 20 0 20 20 100%

REMOVE ROOF AND WALL TO INSTALL GUTTER m1 1,488 130.2 241.8 372 25%
PT. LIK -
▣ Renovation Project – CHANG SHIN FACTORY
Times : 8 am – 18.00 pm Times : -

Worker
Division Staff Supir SUM Remark
Roof worker Cleaning operator
Manpower 1 1 7 2 11
Equipment

□ Schedule

6.11 30.12
Devision
0 10 20 30 0 10 20 30
11/06 FINISH 12/30
FRP

11/06 FINISH 12/30


GUTTER
PT. LIK -
LOCATION - Before Today

JJC

JJC – Plan C

JJC - ACC
JJC – Plan B

JJC – Plan A
PT. LIK -
DOCUMENTATION WORK