MPL POWER PLANT PH2 SCH

Page 1

20.09.10

PROJECTIMPLEMENTATIONSCHEDULE
Customer:M/s.MADHUCONPROJECTSLIMTEDHYDERABAD,
2x150MWPOWERPLANTPHASEII,TPPOFSEPL,NELLORE
Rev0
ID

Activity

Responsibility

Start

Finish

Receipt of LOA

Client

10-Sep-10

10-Sep-10

Submission of 3d Modelling and sketches for foundation reactions

Kirby

30-Sep-10

30-Sep-10

Approval of 3D modelling

Consultant

1-Oct-10

7-Oct-10

Submission of Design drawings

Kirby

7-Oct-10

20-Oct-10

Approval of design drawings

MND

18-Oct-10

23-Oct-10

Submission of MND commented Design drawings to DCPL

Kirby

23-Oct-10

28-Oct-10

Approval of MND commented Design drawings

DCPL

23-Oct-10

31-Oct-10

Financial arrangement

Client

10
Oct 10
10-Oct-10

10
Oct 10
10-Oct-10

Despatch of Anchor bolts in templates

Kirby

20-Oct-10

10-Dec-10

10

Preparation of Shop drawings

Kirby

23-Oct-10

30-Nov-10

11

Material procurement

Kirby

8-Oct-10

8-Dec-10

12

Foundations Ready with Compacted Flooring

Client

Axis : A~C

GL.14' ~ GL.19

Client

17-Nov-10

8-Dec-10

Axis : A~C

GL.19 ~ GL.25

Client

8-Dec-10

29-Dec-10

Axis : A~C

GL.25 ~ GL.28

Client

29-Dec-10

19-Jan-11

13

Fabrication, Shop Primer

Kirby

Axis : A~B

GL.14' ~ GL.19

"

1-Nov-10

6-Dec-10

Axis : B~C

GL.14' ~ GL.19

"

22-Nov-10

12-Dec-10

Axis : A~B

GL.19 ~ GL.25

"

29-Nov-10

3-Jan-11

Axis : B~C

GL.19 ~ GL.25

"

24-Dec-10

14-Jan-11

Axis : A~B

GL.25 ~ GL.28

"

1-Jan-11

25-Jan-11

Axis : B~C

GL.25 ~ GL.28

"

14-Jan-11

25-Jan-11

"

6-Dec-10

25-Jan-11

Roof Beams,Axis.A~
Beams Axis A~ C / GL
GL.14~
14~ GL.28
GL 28

MPL POWER PLANT PH2 SCH

Page 2
20.09.10

PROJECTIMPLEMENTATIONSCHEDULE
Customer:M/s.MADHUCONPROJECTSLIMTEDHYDERABAD,
2x150MWPOWERPLANTPHASEII,TPPOFSEPL,NELLORE
Rev0
ID

Activity

14

Despatch of Material

Responsibility

Axis : A~B

GL.14' ~ GL.19

"

15-Nov-10

20-Dec-10

Axis : B~C

GL.14' ~ GL.19

"

6-Dec-10

27-Dec-10

Axis : A~B

GL.19 ~ GL.25

"

13-Dec-10

17-Jan-11

Axis : B~C

GL.19 ~ GL.25

"

7-Jan-11

31-Jan-11

Axis : A~B

GL.25 ~ GL.28

"

15-Jan-11

31-Jan-11

Axis : B~C

GL.25 ~ GL.28

"

19-Jan-11

5-Feb-11

"

20-Dec-10

10-Feb-11

Finish Painting & Erection of Structures

17

Kirby Certified Bldr

Axis : A~C

GL.14' ~ GL.19

"

1-Dec-10

22-Dec-10

Axis : A~C

GL.19 ~ GL.25

"

22-Dec-10

12-Jan-11

Axis : A~C

GL.25 ~ GL.28

"

12-Jan-11

2-Feb-11

"

2-Feb-11

31-Mar-11

Roof Beams,Axis.A~ C / GL.14~ GL.28


16

Finish

Kirby

Roof Beams,Axis.A~ C / GL.14~ GL.28


15

Start

Mezzanine Deck Sheeting

Kirby Certified Bldr

Axis : A~C

GL.14' ~ GL.19

"

16-Dec-10

31-Dec-10

Axis : A~C

GL.19 ~ GL.25

"

1-Jan-11

16-Jan-11

Axis : A~C

GL.25 ~ GL.28

"

17-Jan-11

1-Feb-11

Roof Beams,Axis.A~ C / GL.14~ GL.28

"

2-Feb-11

28-Feb-11

Crane Beams Erection & Alignment

Kirby Certified Bldr


"

16-Dec-10

15-Feb-11

Client

1-Feb-11

15-Mar-11

Axis : A~B

GL.14' ~ GL.28

18

Masonary Wall Completion with Plastering

19

Wall Cladding Works

Kirby Certified Bldr

15-Feb-11

31-Mar-11

20

Finishing Works

Kirby Certified Bldr

21 Mar 11
21-Mar-11

10 Apr 11
10-Apr-11

NOTE: ABOVE SCHEDULE IS SUBJECT TO ENCLOSED CONDITIONS AS PER ANNEXURE-A ENCLOSED