TSGENCO Site Work Timeline
Activity Starting Date Finishing Date
Chipping off of 1st Layer of
Existing Concrete at Pump House
Location
21.06.14 15.07.14
Date 5/8/14
Demolishing of complete
concrete at the Location of Pump
House
16.07.14 21.07.14
Removal of concrete at the Pump
House
24.07.14 26.07.14
Removal of soling material at the
pump house location
04.08.14 05.08.14
Excavation of Pump House (with
points marking by total station)
07.08.14 10.08.14
P.C.C. of Pump House 11.08.14 12.08.14
Excavation Of Pump and motor
Foundations
07.08.14 10.08.14
P.C.C. of Pump and motor
Foundations
11.08.14 12.08.14
Foundation Works of Pump
House
13.08.14 23.08.14
Brick Work and R.C.C. in
Superstructure upto 3 Meter
Level of Pump House
24.08.14 03.09.14
Brick Work and R.C.C in
Superstructure upto 6 Meter
Level
04.09.14 15.09.14
Brick Work and R.C.C in
Superstructure upto Roof Level
of Pump House
16.09.14 25.09.14
R.C.C. of Pump Foundations of
Pump House
26.09.14 30.09.14
R.C.C. of Roof Slab of Pump
House
01.10.14 02.10.14
Doors, Windows & Finishing of
Pump House
02.10.14 15.10.14