Date: 02 December 2015

Ref.: SRP/SJJV/AAE/LET/005
To:

M/s. Al Ali Engineering Co.


P O Box: 82614
Doha, Qatar

Attn: Mr. Fadi Sanwar


Project Director
Project:
Subject:

Construction, Completion and Maintenance of Salwa Resort


Buildings and Infrastructure Works Packages Nos 2 and 3.
MEP Works - Planning Package Rev.0 (SR-SC-006)

Dear Mr. Fadi,


With reference to the Letter Of Intent ref. no. DMS/104/CRL/LOI/3/2015 dated 17
September 2015 regarding the aforementioned subject, please find attached
herewith the initial Planning Package rev, 0 for the Subcontract Package SR-SC006 (HLS - JEC JV) along with the comprehensive planning narrative.
The planning package includes the following for your Kind review & approval:
123456789-

The Comprehensive Planning Narrative.


The Initial Baseline Program of works.
Critical Path.
Summarized Program of Works.
Shop Drawings Schedule of Submission.
Material Tracking Schedule (MTS).
Progress Histogram & S-Curve.
Manpower Histogram & S-Curve.
Project Scope of Work Layout.

Assuring you of our fullest cooperation at all times for clarification and planning
workshops to elaborate further if required.
Yours faithfully,
For HLS-JEC JV
Kyriacos Savva
Sr. Project Manager
Attachments: 1-(13 pages), 2-(), 3-(), 4-(), 5-(), 6-(), 7-(), 8-(), 9-()

HABTOOR LEIGHTON SPECON & AL JABER ENGINEERING L.L.C. JOINT VENTURE


P.O.Box 22801 Doha Qatar, Tel: +974 40409600, Fax: +974 40409797