PART 1 - GENERAL 1.01 A. Description Work in this Section includes, but is not limited to; furnishing survey crew, setting up reference points and bench marks, vertical and horizontal setting out of all buildings, foundations, fences, grading, trench work, utility installations, roadways, asphalt paving, walkways and other works forming part of the Contract. Work is to be performed in accordance with the conditions set forth in subsection 1.03 of Section 02000 General Instructions. Related Work Section 02000 - General Instructions Section 02210 - Excavation, Trenching, Backfilling and Compacting Section 02513 - Base Course and Asphalt Concrete Paving Section 03100 - Concrete Formwork Section 03300 - Cast-In-Place Concrete
Section 01051
PROJECT ENGINEER
____________ DATE
CERTIFIED _ __________
DATE: ________
CONSTRUCTION AGENCY
________________ DATE:
B.
OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:
1.02 A. B.
Date:
C. D. E.
CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS
DRAWING NO.
DOC K55 A
VE-417361 BI-25-00002
RABIGH
SAUDI ARABIA
15-Sep-07
JOB/EWO#
1 OF 4
00
PMT
1.03 Reference Standards A. Saudi Aramco Engineering Standards (SAES). 1. 1.04 SAES-A-100 - Survey Coordinates and Datums.
ENGG
CERT
Contractor Responsibility Contractor responsibility includes, but is not limited to: 1. Performing all surveys for the duration of the Contract to ensure that levels and locations conform to the design Drawings, and shop/working drawings approved by Saudi Aramco Representative. Making formal requests to Saudi Aramco for data on survey control points related to the project prior to construction. Verifying the figures on all Saudi Aramco furnished data and documents before laying out the Work. Contractor shall be responsible for any errors or inaccuracies resulting from his failure to do so. Informing Saudi Aramco Representative if the validity of any survey monument is threatened, and take the necessary steps as outlined in this Specification. Obtaining approval of Saudi Aramco Representative if any survey control points will be disturbed or destroyed by construction activities. Maintaining all Saudi Aramco established reference points and bench marks at all times during construction. Under the direction of Saudi Aramco Representative, replace any survey monuments damaged or disturbed by construction activity. Preparing accurate as-built survey and submission of drawings. 8. Contractor shall submit a survey report after each completed (compacted) layer to Saudi Aramco representative for verifying the correct elevation. No work shall proceed for the next phase prior to approval of the completed work. 9. Contractor shall contact Saudi Aramco Survey Group through SAPMT to verify the exact punch mark prior to start of any backfilling.
DESCRIPTION
A.
2.
DATE JOB/EWO
3.
REV. NO.
4.
DISCIPLINE ENGINEER
5.
PROJECT ENGINEER
____________ DATE
6.
CERTIFIED _ __________
DATE: ________
CONSTRUCTION AGENCY
________________ DATE:
7.
OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:
Date:
1.05 A.
Accuracy and Quality Assurance Contractor is to establish all horizontal and vertical reference points, and monuments accurately within a maximum tolerance of 5 mm vertically and 10 mm
Section 01051
CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS
DRAWING NO.
DOC K55 A
VE-417361 BI-25-00002
RABIGH
SAUDI ARABIA
15-Sep-07
JOB/EWO#
2 OF 4
00
CERT
PMT
DESCRIPTION
ENGG
B.
Contractor will be provided with survey controls (refer to benchmark data shown on the drawings). These control points shall be tied from any of Saudi Aramco survey controls and closed to another Saudi Aramco survey control. All survey field notes must be kept in field at all times for inspection by Saudi Aramco Representative. Submittals Submit to Saudi Aramco Representative all data and grade sheets at least 48 hours prior to construction. Show on the grade sheets the vertical and horizontal relationships between the stakes and the design reference points shown on the Drawings.
1.06 A.
DATE JOB/EWO
PART 2 - PRODUCTS 2.01 A. Stakes Construction Stakes: Construction stakes shall be 14 mm steel rebar. Wood or PVC stakes may be used as directed by Saudi Aramco Representative. Machine Control Stakes: Machine control stakes shall conform to manufacturer's specifications.
REV. NO.
DISCIPLINE ENGINEER
B.
PROJECT ENGINEER
____________ DATE
PART 3 - EXECUTION 3.01 Surveying Work A. Contractor Survey Controls: From Saudi Aramco provided survey controls (refer to bench mark data shown on the Drawings), Contractor shall establish additional survey controls with an accuracy as stipulated in this Specification. Survey Monuments: If the validity of any survey monument is threatened, place at least three (3) reference or witness markers for each point likely to be disturbed. Submit survey notes listing the relative positions of the reference markers to each other, and to the points they are referencing at least 48 hours prior to disturbing or threatening the validity of the monument. Road Works: 1. General: Prior to the start of grading, and during the progress of the Work, set and maintain sufficient stakes to show conformance with the Drawings. Locate all stakes in such a way that they will not be disturbed by construction operations.
Section 01051
CERTIFIED _ __________
DATE: ________
CONSTRUCTION AGENCY
________________ DATE:
OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:
B.
Date:
C.
CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS
DRAWING NO.
DOC K55 A
VE-417361 BI-25-00002
RABIGH
SAUDI ARABIA
15-Sep-07
JOB/EWO#
3 OF 4
00
ENGG
CERT
PMT
3.
DESCRIPTION
DATE JOB/EWO
General: Prior to beginning trenching operations, and during the progress of the Work, set and maintain sufficient stakes to show conformance with the Drawings. Locate all stakes in such a way that they will not be disturbed by construction operations. Stake Placement: Construction stakes are to be place at, but not limited to, the following locations; a. Utility Pipes: Stakes shall be placed at each wye or tee connection, cleanout and manholes and at every 10 meter station.
REV. NO.
2.
DISCIPLINE ENGINEER
PROJECT ENGINEER
____________ DATE
E.
CERTIFIED _ __________
DATE: ________
Park Work: Prior to beginning of grading, and during the progress of the Work, set and maintain sufficient stakes to show conformance with the Drawings. Locate all stakes in such a way that they will not be damaged or disturbed by construction operations. Contractor shall protect the stakes in areas where they are likely to be disturbed or displaced.
F.
CONSTRUCTION AGENCY
________________ DATE:
OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:
- END OF SECTION -
Date:
Section 01051
CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS
DRAWING NO.
DOC K55 A
VE-417361 BI-25-00002
RABIGH
SAUDI ARABIA
15-Sep-07
JOB/EWO#
4 OF 4
00