You are on page 1of 2

COPI LIFTING PLAN

PAGE 1 of 2

Location

: TEMPORARY FACILITY AREA

Area

: SUBAN

Permit No.

Risk Assessment No.

Generic Lifting Plan No.

: Drawing Attach

Method Statement No.

Is Diagram/Sketch Of Lifting Operation Enclosed?


Description Of Lifting Operation:
LIFTING AND INSTALLATION TEMPORARY FACILITY CONTAINER 20" (EAST SIDE)
Refer to Drawing No. : -

SPECIFICATION OF LOAD
LIFTING WEIGHTS
Items
CONTAINER 40"

LOAD BEARING CAPACITY

CENTER OF GRAVITY
(for awkward load only)

Weight in kg
4,000.00

TOTAL

4,000.00

Lifting Equipment & Accessories To Be Used (specify type, SWL) and manpower required
No

SWL (Te)

Quantity

WIRE SLING 4 LEGS

Type of equipment

13

SHACKLE

8.5

RIGGING SUPERVISOR

TAG LINE

RIGGER

CRANE OPERATOR

Category of lifts:

Simple

Complicated

Man Power (Lifting SPOC, Rigger, Banksman, Slinger)


Designation

Number

Complex

JSA related to category of lifts

LIFT CATEGORY: NON ROUTINE COMPLICATED


The table below shall be completed by the personnel about to perform the lifting operation. Tick against factors which are applicable to the
specific lifting operation and indicate whether or not you have the relevant experience to deal with them.
Category questions
(Refer to JSA session)

Applicable?
(Yes / No)

HAZARDS IDENTIFIED :

Experience (Yes / No)?

CONTROL PLAN :

- Broken/loose lifting gear

- Ensure valid certificate, valid color code, SWL plate and identification number of
lifting gear

- Struck by moving object

- Use tag line

- Uncertified Rigger

- Ensure certificate rigger still valid

- Lack Communication

- Good coordination between rigger and crane operator

- Rigger crew not understand step jobs

- Perform PJSM to all crew rigger and ensure the all crew understand the job
steps

Caught between object

- Avoid pinch point, use heavy duty hand gloves

Assessment performed by :
Name :

Position :

Date:

LIFTING OPERATIONS PLAN

PAGE 2 of 2

Location

: TEMPORARY FACILITY AREA

Area

: SUBAN

Permit No.

Risk Assessment No.

Generic Lifting Plan No.

: Drawing Attach

Method Statement No.

BREAK DOWN STEPS FOR SPECIFIC LIFT PLAN


1

Ensure lifting and rigging equipments are certified for current use and in good working order through pre-use inspections.

Ensure that crane equipments are certified for current use and in a good condition

The certificate of crane operator must be complete

Ensure the radius of boom crane is safe when lifting operation worked

Positioning the crane it's about 7 meters from target location with boom radius 77 (13.9 Tons)

Positioning the trailer would be lifted by crane

Installing the sling 7/8" x 13 M on the top of container 20"

Installing tag line in the below of the container 20"

Ready for lifting from trailler to the location installation it's about 6 meters with boom radius 79 (13.9 Tons)

ON COMPLETION OF WORK

Method(s) Of Communication To Be Used

Radio

Verbal

Steps Taken To Eliminate Danger To Personnel Involved & Others, Including Barriers Where Appropriate:
Barrier off area to all personnel not involved with the lifting operation
A suitable risk assessment to be completed before job start.
Toolbox talk to be held prior to job start and and at any point where task deviates from procedure.
De-brief and learning points:

Planned By:

Signature:

Date:

Reviewed By:

Signature:

Date:

Hand signals

You might also like