SCHEDULE DATES

WORK ACTIVITY OCTOBER

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 MATERIAL PROCUREMENT

PIPES

FITTINGS

SUPPORTS

2 WET RISER INSTALLATION

a Stair -1 Riser

b Stair -2 Riser

c Testing of riser-1

d Testing of riser-2

3 Painting of sprinkler drain riser& supports

4 INSTALLATION OF FIXED SUPPORTS

a BASEMENT -2

b BASEMENT1

c GROUND FLOOR

d MEZZAINAINE FLOOR

e PODIUM -1

5 RECTIFICATION OF SPRINKLER ORIENTATION

a BASEMENT -2

b BASEMENT1

c GROUND FLOOR
d MEZZAINAINE FLOOR
e PODIUM -1
Note :Dates are tentative subject to clearnce avialble at site and depend on your activity ie scaffolding readiness inside the shaft
Draining of the sprinkler sytem in each level prior to rectification of oriection of sprinkler in parking areas
Mobile scaffolding required in parking areas for fixed support installation and changig of sprinkler orientation.
end on your activity ie scaffolding readiness inside the shaft