Professional Documents
Culture Documents
.
.
. ( )Drawing
.
.
.
.
.
.
Khalid mohammadi
.
.
.
.
.
.
.
:
10
.
.
( )Technical Documents
.
.
( )Specification of Materials
.
()Cost of Materials
.
5 10
.
.
.
( )Types of Estimation
Khalid mohammadi
.
( )Preliminary Estimation
0.5 50
.
- 2 ( )Cubage Estimation
.
.
40 50
.
Khalid mohammadi
.3 ( )Cost per Unit of Quantity Estimation
( )Detailed Estimation
.
Unit Cost .
Lump Sum .
( )Complete Estimation
.
( )Total Cost
.
Khalid mohammadi
.1 ( )Direct Cost
.
.2 ( )Indirect Cost 12
Direct Cost .
.3 ( )Profit 10 15 15
10 5
.
.
.
.1 Skilled Labors SL .
.
.2 Unskilled Labors USL .
.
Mandy MD
8
90
.
( )CGS or MKS
:
)Meter, (M
)Kilogram, (Kg
)Second, (Sec
)Ampere, (A
)Kelvin, (K
)Candela (Cd
.
.
(
) ( ) ( ) (
) ( ) ( ) .
Khalid mohammadi
10-1 d ()deci 1012 T ()tera
10-15 f ()femto
10-18 a ()atto
.1 )Meter, (M
1
.
299792458
299792458 m/s
1
.
299792458
.2 )Kilogram, (Kg
- .
()Derived Units
( )m/sec
( ) Kg.m 2 .
sec
.3 ()Units of Area
.
.
Khalid mohammadi
1km2 = 106 m2
= 104 m2 hm2 = 1ha,
= 102 m2 Dm2 = 1ar,
1m2 = 102dm2
1m2 = 104 cm2
1m2 = 106 mm2
.4 ()Units of Volume
.
1m3 = 1000dm3
1dm3 = 1000cm3
1cm3 = 1000mm3
:
1litter = 1dm3 = 1000cm3
1gallon = 3.785litter
.5 ()Units of Weight
. ( )N
.
W = M. g
1N = 1kg. m/sec2
(:)Density
( kg/m3 )SI.
V
(:)Weight density
( )N/m3.
W M g
g
V V
(:)Specific gravity
Sp.gr
w w
(:)British System
Khalid mohammadi
( )ft .1
.
( )Slug. .2
. .3
( ) F . .4
.1
1ft = 0.3048m
1mile = 5280ft = 5280 0.3048m = 1609m
1mile = 1.609km
1 1
= 1inch = ft (0.3048m) = 0.0254m
12 12
1inch = 25.4mm = 2.54cm
1yard = 3ft = 36inch
1m = 39.37in
1m = 3.28ft
4.2km :
:
1000m 10dm
()(4.2km () ) = 42 103 dm
1km 1m
= 42000 dm
:
1000m 3.28 ft
()(4.2km () ) = 13776ft
1km 1m
34000mm : ( )Dm
1m 1D
()(34000mm () ) = 3.4 Dm
1000mm 10m
2.5km : ( )Mile
:
1000m 39.37in
( )(2.5km () ) = 98425 in.
1km 1m
:
1000m 1mile
( )(2.5km () ) = 1.554 mile
1km 1609m
.2
1 ton = 1000 kg
1 kg = 1000 g
1 kg = 0.0685 slug
1 slug = 14.6 kg
:
Khalid mohammadi
0.05 ton slug
1000kg 0.0685slug
( )(0.05 ton () ) = 3.425 slugs
1ton 1kg
.3
1.308 yd 3
( )(472 m3 ) = 617.38 yd3
1m3
.5
lb . slug
ft 3 ft 3
:
8.9g 0.089m3:
cm 3
.1
.2
.3
Khalid mohammadi
.4
.1
W M g 7770.5 N
= g 3
= 87309 N/m3
V V 0.089m
.4
N N
= 9.81 3
= 9810 3
dm m
87309 N
m3 = 8.9
Sp.gr =
w w 9810 N 3
m
:
.1
.2
322.752 square feet :
.3
30000 square meter :
.4 15m3
1.784m :
.5 2.3
N
22563 :
m3
.6 30cm 12kg
4 3
= r
3
Sp.gr = 0.8488 :
Khalid mohammadi
.1 ()Earth Work
.
.
. .
10cm .
.
.2 ()Concrete in Foundation
( ) .
20cm
45cm 30cm .
( )Lime Concret .
1:4:8 1:5:10.
.3 ()Soling
1
1 : 1 : 3 2.5cm 1:2 2cm
2
.
( )D.P.C .
D.P.C ( )Sills .
: Cem-Seal Impermo
.
.5 ()Masonry
( ) .
( )Superstructure .
Khalid mohammadi
( )Superstructure
.
.
.
( )Partition Wall
. .
.
.
.C .10cm
)a ()Rectangular Openings
= T
= L H T
)b
= T
= L H T
Khalid mohammadi
)c
Segmental
.
2 r3
lr Segmental =
3 2l
:
= L h ( L r t
2
3
)d
:
= 3
4
.
= t
= L h ( L r t
3
4
.
.
.
Khalid mohammadi
= Lm t
= Lm t
( )R.C.C ( )R.B
( s )Clear Span
( )Bearings
1
) 4 ( 12cm .
2
:
l = s + 2t
= l t thickness of wall
= l t thickness of wall
. (
Khalid mohammadi
)
.
:
.i .
.ii .
.
0.6% 1.0% .
.
.
: ( :)Ground Floor (
)
. .
: :
() ( )Floor finishing
2.5cm 4cm.
: ( :)Roof ()
.
( ) :
.i .
.ii 0.5m2
( )Sills, Soffits, and Jambs .
.iii 0.5m2 3m2
.
2
.iv 3m
.
As the outer jambs, etc. are much smaller than the inner ones, the deduction
is usually made from the outer face.
Khalid mohammadi
Inside plaster = L H
Outside plaster = L H l h
12mm
.
R.C.C
.
.
( :)Pointing
.
.11 Cornice
( )
.
.12 Pillars
:
=
:
d 2
=
4
.
.
.17 (:)Painting
. .
2 ( ) 1
1 2
2 3
3 4
1 5
Khalid mohammadi
. .
Reducing Calculation
.
.1 :
:
) ( =
.2
.
.3 :
( )Footing
.
b1 b2
=
2
b1 b2
= L h.
2
= L
Khalid mohammadi
= h
.
.4
:
.
.
0.5cm .
.
1cm 0.01m2 0.01m3
.
:
:
.1
.
.2
.
.3 .
.4 .
:
( )mm
( )cm ( )m .
1
Khalid mohammadi
2
3
4
5
6
7
8
9
I 10
11
:
.1 :
120cm 210cm
110cm 200cm
100cm 190cm
90cm 180cm
75cm 180cm
.2 :
100cm 150cm
90cm 120cm
.3 :
120cm 60cm
100cm 60cm
90cm 50cm
.4 :
12cm 7.5cm
10cm 10cm
10cm 7.5cm
7.5cm 7.5cm
.5 :
2.5cm
Khalid mohammadi
3.0cm
4.0cm
4.5cm
.6 :
15cm 30cm
20cm 40cm
25cm 45cm
.7 :
7.5cm
10cm
12cm
.8 () :
7.5cm 12.5cm
10cm 15cm
.9
10mm 15mm
12mm 20mm
.10 D.P.C
2cm
2.5cm
4.0cm
.11
2cm
2.5cm
4.0cm
.12
2.5cm
4.0cm
.13
Rise and Tread
15cm 30cm
15cm 28cm
18cm 28cm
.14
Khalid mohammadi
30cm 45cm
60cm 75cm
.15
2.80m 3.60m
3.00m 3.90m
3.30m 4.20m
:
1 1 7 3 5 1 3 1
1 1 1
2 4 8 4 8 2 8 4
40 32 25 22 20 16 12 10 6
9.86 6.31 3.85 2.98 2.47 1.58 989 962 922
Khalid mohammadi
1 1 1
3 2 2 1 1
2 2 2
60 50 40 30 20 10
19cm 29cm
10 20 30 .
1
2
3
( ) 4
5
6
7
8
9
10
( ) 11
1
( 2
)
C.C 3
R.C.C 4
C.C R.C.C 5
( D.P.C ) Damp 6
proof course
1
2
3
4
Khalid mohammadi
5
6
Thin partition wall
)Reinforced brick (R.B work 7
( ) 8
9
10
11
1
2
( ) 3
( ) 4
1
( ) 2
3
4
5
()Partition wall 6
Steel Work
( 1
)
R.B R.C.C 2
3
4
5
6
7
8
9
10
( ) 11
Roofing
1
2
3
R.C.C R.B 4
( ) 5
Khalid mohammadi
6
7
8
9
10
Plastering Finishing
( ) 1
2
( ) 3
( ) 4
( ) 5
( ) 6
( ) 7
8
9
Flooring
2.5cm 7.5 1
7.5 2
7.5 3
7.5 4
7.5 5
7.5 6
7
/ 8
Miscellaneous
1
2
( ) 3
4
( ) 5
6
7
( ) 8
9
10
11
Construction Material
1
2
Khalid mohammadi
50 3
4
5
6
7
8
9
10
11
( ) 12
( ) 13
14
15
16
17
.1 :
.a
.b 50cm
.c 25cm 25cm
.d
.2 :
Khalid mohammadi
.a
20cm 10cm 5cm .b
.c
.d 10mm
Khalid mohammadi
( )
.
.
.
:
:
: 32000
850 .
:
= = 3.6 = 4 3 0.3
( ) = 2 = 24 = 2 4 3
= 115200 = 32000 3.6
= 20400 = 24 850
= 135600
:
:
.1
.2
1
:3 2.5 .3 ( )D.PC 1:1
2
.4 12mm 1:6
Khalid mohammadi
.5 12mm 1:6 10cm
.
:
.
()m
Khalid mohammadi
4.32
4.32 0.90 0.80 6.00 1 1
1.44
1.44 0.30 0.80 6.00 1 2
()Plinth
0.72 0.20 0.60 6.00 1
3.24 0.60 0.20 0.50 6.00 1 3
0.48 0.20 0.40 6.00 1
1.44 0.60 0.40 6.00 1
2.4 1
2.4 - 0.40 6.00 1 :3 2.5cm 1:1 4
2
6.3
6.3 3.50 0.30 6.00 1 5
12mm ( )
1:6
21.0 3.50 - 6.00 1 6
46.2 10cm
25.2 4.20 - 6.00 1
21.0 ( )
21.0 3.50 - 6.00 1 7
24.6
24.6 4.10 - 6.00 1 ( 8
)
Khalid mohammadi
: ()Individual Wall Method
.
.
.
.
( )
.
+ = .
= .
:
.
:
.1
.2
.3 1:6
2.5cm .4
.5
* 15cm.
2.1m 1.2m D
1.5m 1m W
*1.5m 1m S
Khalid mohammadi
* Shelves : .
Khalid mohammadi
()m
=
0.30
10.60m= 2+ 0.3+ 6+ 4
2
25.74 1.00 1.10 11.70 2 ...
1
0.30 17.16 1.00 1.10 5.20 3
6.30m= =2+ 6
2 42.90m 3
7.72 0.30 1.10 11.70 2 2
3 5.15 0.30 1.10 5.20 3
=
10 12.87m3
3
1:6
L=10.60+0.80=11.40m 3.65 0.20 0.80 11.40 2
L=10.60+0.70=11.30m 1.58 0.10 0.70 11.30 2 ...
L=10.60+0.60=11.20m 1.34 0.10 0.60 11.20 2 ...
Khalid mohammadi
L=10.60+0.50=11.10m 1.11 0.10 0.50 11.10 2 ...
L=10.60+0.40=11.00m 7.04 0.80 0.40 11.00 2
..
L=6.30-0.80=5.50m 2.64 0.20 0.80 5.50 3
L=6.30-0.70=5.60m 1.18 0.10 0.70 5.60 3
L=6.30-0.60=5.70m 1.03 0.10 0.60 5.70 3 ...
L=6.30-0.50=5.80m 0.87 0.10 0.50 5.80 3 ...
L=6.30-0.40=5.90m 5.66 0.80 0.40 5.90 3 ...
3
26.10m
..
2.5cm
8.80 0.40 11.00 2
4
7.08 0.40 5.90 3
15.88
0.96 0.40 1.20 2
14.92m2
5
L=10.60+0.30=10.90m 27.47 4.20 0.30 10.90 2
L=6.30-0.30=6.00m 22.68 4.20 0.30 6.00 3
50.15m3
1.51 2.10 0.30 1.20 2
Khalid mohammadi
1.80 1.50 0.30 1.00 4
10cm 0.60 1.50 0.20 1.00 2 ...
. ...
15cm 0.14 0.15 0.30 1.50 2 ...
15cm 0.23 0.15 0.30 1.30 4 ...
15cm 0.12 0.15 0.30 1.30 2 ...
3
4.40m
3
45.75m
= 45.75m3
: :
.1
.2
.3
.4 ()D.P.C
.5
:
:
210cm 120cm D1
200cm 100cm D2
180 75cm D3
:
150cm W1 100cm
Khalid mohammadi
150cm W2 200cm
120cm W3 75cm
60cm 75cm C.W Clerestory Window
:
150cm 100cm S
:
15 cm .
.
Khalid mohammadi
: ()Center line method
(
) .
.
)Junction (
.
.
.
.
.
:
:
.1
.2
.3
.4
Khalid mohammadi
= DA + CD + BC + AB
= 19.20m = 4.30 + 5.30 + 4.30 + 5.30
.
Khalid mohammadi
.
.
= 90cm CD + 90cm 90cm BC + 90cm 90cm AB
.90cm 90cm DA + 90cm
( R Q P )S
( M L K )N
( ) .
.
.
()m
)(m3
15.55 0.90 0.90 19.20 1 1
= 19.20m
5.18 0.30 0.90 19.20 1 2
()Plinth
3.46 0.30 0.60 19.20 1 3
2.88 0.30 0.50 19.20 1
4.61 0.60 0.40 19.20 1
10.95
20.16 3.50 0.30 19.20 1 4
Khalid mohammadi
:
.1
.2
.3 1:6
2.5cm .4
.5
:
.
0 .3
10.60m = )+ = (+ 0.3 + 4 + 6
2
0 .3 0 .3
) = 6.30m + = (+ 6
2 2
= 2 3 +
.
Khalid mohammadi
A B
- .
.
:
L same as
12.87 0.30 1.10 39.00 1 2
above.
L=40.10-
.80 1:6
2
2
()Plinth
=39.30m
Khalid mohammadi
26.10
...
50.15 4.20 0.30 39.80 1
5
...
4.40 1
45.75
:
A
.1
.2
.3 1:6
D.P.C .4
.5
:
:
210cm 120cm D1
200cm 100cm D2
180 75cm D3
:
150cm W1 100cm
150cm W2 200cm
120cm W3 75cm
Khalid mohammadi
60cm 75cm C.W Clerestory Window
:
150cm 100cm S
:
15cm
.
:
30cm =
+ .
6 x .
30cm.
( 20cm )
= (c. to c. length of front wall + c. to c. length of side wall) + (c. to c. length of
back verandah long wall including bath + 2 c. to c. length of cross walls of
)bath room
= (9.65 + 2.25) + (9.65 + 2 2.75) = 11.90 + 15.15 = 27.05 m.
30cm
( )20cm .
( ):
0.90
= 63.20 = 6 65.90
2
= 56.88m3 = 1.00 0.90 63.20
Khalid mohammadi
:
0.60 0.90
24.50m = 1- = 5 27.05
2 2
= 7.35m3 = 0.50 0.60 24.50
()m
56.86 1.00 0.90 63.20 1
1
7.35 0.50 0.60 24.50 1
64.23
17.06 0.30 0.90 63.20 1
2
3.06 0.20 0.60 25.50 1
20.12
1:6
()Plinth
7.69 0.20 0.60 64.10 1
3
6.44 0.20 0.50 64.40 1
23.29 0.90 0.40 64.70 1
2.07 0.20 0.40 25.85 1
5.44 0.70 0.30 25.90 1
44.93
2.4 2.5cm
25.88 - 0.40 64.70 1 4
0.60 - 0.30 0.50 4
Khalid mohammadi
2.19 - 0.30 7.30 1 ( )
28.67
2.88 0.40 1.20 6 D1
0.80 0.40 1.00 2 D2
0.23 0.30 0.75 1 D3
3.91
24.76m2
78.00 4.00 0.30 65.00 1
15.98 3.05 0.20 26.20 1
93.98
4.54 2.10 0.30 1.20 6 D1
1.20 2.00 0.30 1.00 2 D2
0.27 1.80 0.20 0.75 1 D3
5
4.95 1.50 0.30 1.00 11 W1
0.90 1.50 0.30 2.00 1 W2
0.36 1.20 0.20 0.75 2 W3
Clerestory window,
2.43 0.60 0.30 0.75 18 C.W.
1.50 1.50 0.20 1.00 5 S
4.03 2.40 0.20 8.40 1
0.96 2.40 0.20 2.00 1
Khalid mohammadi
3.26 2.40 0.20 6.80 1
0.405 0.15 0.30 1.50 6 D1
0.117 0.15 0.30 1.30 2 D2
0.029 0.15 0.20 0.95 1 D3
0.644 0.15 0.30 1.30 11 W1
0.103 0.15 0.30 2.30 1 W2
0.057 0.15 0.20 0.95 2 W3
0.770 0.15 0.30 0.95 18 C.W.
0.293 0.15 0.30 1.30 5
0.293 0.15 0.20 9.75 1
0.065 0.15 0.20 2.15 1
0.225 0.15 0.20 7.50 1
27.40
66.58
: .
Khalid mohammadi
.
.
.1 :
20mm
.
()m
)(m3
0.27 0.15 0.95 1.90 1 1
Khalid mohammadi
0.18 0.10 0.95 1.90 1 2
0.324 0.20 0.90 1.80 1
0.162 0.15 0.60 1.80 1 3
0.081 0.15 0.30 1.80 1
0.567
1.62 0.30 1.80 3 *
1.08 0.15 1.80 4 **
0.27 0.15 0.90 2 *** 4
0.18 0.15 0.60 2
0.09 0.15 0.30 2
2
3.24m
* Treads
** Risers
*** Ends
0.90 0.30
0.486 = 1.80 )0.45 = (
2
= 0.081 = 0.05 0.90 1.80= 567m3
=
= 2.70 = )0.30 3 + 0.15 4( 1.80
= 2
0.90 0.30
= 3.24m2 = 0.54 ) 0.45 =( 2
2
: ( ) .
.
Khalid mohammadi
= 3.51 = )0.30 4 + 0.15 5( 1.80
1.20 0.90 0.60 0.30
= 4.41m2 ) 0.90 = 0.60 = ( 2
4
.2 :
1
:3 . 2.5 1:1
2
Khalid mohammadi
()m
0.71 0.20 1.10 3.2 1 1
0.53 0.15 1.10 3.20 1 2
0.690 0.23 1.00 3.00 1
0.338 0.18 0.75 2.50 1
3
0.180 0.18 0.50 2.00 1
0.068 0.18 0.25 1.50 1
1.276m3
1.125 0.25 4.5 1
0.900 0.18 5.00 1
0.875 0.25 3.50 1
0.720 0.18 4.00 1
4
0.625 0.25 2.50 1
0.540 0.18 3.00 1
0.375 0.25 1.50 1
0.360 0.18 2.00 1
0.270 0.18 1.50 1
5.790m2
2.5cm
5.00 5.00 1
4.00 4.00 1 5
3.00 3.00 1
2.00 2.00 1
Khalid mohammadi
14.00r m
: Nosing 2-17 .
0.71m3 .1
0.53m3 .2
1.276m3 .3
2
5.79m .4
14.00 running meter. .5
.3 :
Khalid mohammadi
1:3 .
.
( )Tread
( ) .
.
:R
:
h s2
R
2 8h
s h .
:
:
0.5 1.52
R4 0.81m
2 8 0.5
:
R3 = R4 + 0.30 = 0.81 + 0.30 = 1.11m
R2 = R3 + 0.30 = 1.11 + 0.30 = 1.41m
R1 = R2 + 0.30 = 1.41 + 0.30 = 1.71m
:s
) ( = 1.50m
Khalid mohammadi
___ h = 0.50m = ___ h = 0.50 + 0.30
0.80m
___ h = 0.80 + 0.30 = 1.10m ___ h = 1.1 + 0.30 = 1.40m
2 h3
= ) (Area of Segment sh
3 2s
s h rise.
(:)arc length
8b 2a
= Curved length , where a = half straight length, b a 2 h 2
3
1.5
= ___ a 0.75, h 0.50, b 0.752 0.502 0.90
2
8 0.90 2 0.75
l4 1.90m
3
2.13
= ___ a 1.065, h 0.80, b 1.0652 0.802 1.33m
2
8 1.33 2 1.065
l3 2.84m
3
2.75
= ___ a 1.375, h 1.10, b 1.3752 1.102 1.76m
2
8 1.76 2 1.375
l2 3.78m
3
3.36
= ___ a 1.68, h 1.40, b 1.682 1.402 2.186m
2
8 2.186 2 1.68
l1 4.71m
3
= x
= x
2 1.53
1. Earthwork in excavation 1 { ( 3.56 1.5) } .15 .605 cu m
3 2 3.56
Khalid mohammadi
2 h3
Area x depth = ( sh ) x depth
3 2s
2 1.53
2. Concrete in foundation 1 { ( 3.56 1.5) } .10 .403 cu m
3 2 3.56
3. Bricks in step __
2 1.43
1st step 1 { ( 3.36 1.4) } .20 .708
3 2 3.36
2 1.13
2nd step 1 { ( 2.75 1.1) } .15 .338
3 2 2.75
2 .83
3rd step 1 { ( 2.13 .8) } .15 .188
3 2 2.13
2 .53
4th step 1 { ( 1.5 .5) } .15 .081
3 2 1.5
Total 1.315 cu m
4. 20 mm cement plaster 1:3 __
4.71 3.78
1st step __ Tread 1 .30 _ 1.27
2
Riser 1 4.71 _ .15 .71
3.78 2.84
2nd step __ Tread 1 .30 _ .99
2
Riser 1 3.78 _ .15 .57
2.84 1.90
3rd step __ Tread 1 .30 _ .71
2
Riser 1 1.90 _ .15 .29
2 .53
4th step __ Tread 1 ( 1.5 .5) _ .54
3 2 1.5
Riser 1 1.5 _ .15 .23
Total 5.31 sq m
Khalid mohammadi
Masonry Water Tank
:
:
1:6 _
12mm 12mm
1
5cm 1 : 1 : 3 30cm 1:4 . _
2
.
:
Rs. 350.00 .1
Rs. 220.00 .2
Rs. 320.00 .3 1:6
Rs. 8.50 12mm .4 1:2
Rs. 8.30 12mm .5 1:4
1
Rs. 55.00 5cm .6 1 : 1 : 3
2
:
footing
.
:
= 7.50 m =5.50 m
:
( 7.40 m = )40 cm =
. 5.40 m
( 7.30 m = )30 cm =
. 5.30 m
Khalid mohammadi
Masonry Water Tank
()m
33.15 1.95 1.00 8.50 2
)1 17.55 1.95 1.00 4.50 2 1
36.56 1.25 4.50 6.50 1 ()
3
87.26m
)2 5.10 0.30 1.00 8.50 2 2
2.70 0.30 1.00 4.50 2
Khalid mohammadi
7.00 0.20 5.00 7.00 1
3
14.80m
1:6
:
2.29 0.20 0.70 8.20 2
1.94 0.20 0.60 8.10 2
10.00 1.25 0.50 8.00 2 50 cm
1.34 0.20 0.70 4.80 2
)3 3
1.18 0.20 0.60 4.90 2
6.25 1.25 0.50 5.00 2 50 cm
:
6.24 1.00 0.40 7.80 2 40 cm
4.00 1.00 0.40 5.00 2 40 cm
2.28 0.50 0.30 7.60 2 30 cm
1.50 0.50 0.30 5.00 2 30 cm
3
37.02m
12 mm
35.00 2.50 - 7.00 2
)4 25.00 2.50 - 5.00 2 4
2
60.00m
12 mm
* 40 cm
19.50 1.25 - 7.80 2
14.50 1.25 - 5.80 2
** 30 cm
9.12 0.60 - 7.60 2
5
6.72 0.60 - 5.60 2
)5 :
4.56 - 0.30 7.60 2
3.00 - 0.30 5.00 2
2
57.40m
Khalid mohammadi
1)
L = 7.50 + 1.00 = 8.50 m
L = 5.50 1.00 = 4.50 m
L = 7.50 1.00 = 6.50 m
B = 5.50 1.00 = 4.50 m
2) Floor lime concrete is not taken with c.c. floor as sufficiently thick.
:
) Platform(
:
.3 .2 .1
2.5cm 7.5cm 2.5cm
1:6 12mm .4
.
Khalid mohammadi
.1
.2
.
.
.
.
Khalid mohammadi
)490 lb/ft3( 7850 kg/m3 .
:
0.7 1.0
1.0 2.0
1.0 5.0
0.5 0.8
Cover
Cover 1.2 2 2.5
5 .
9 .
:
L = I + 18 dia
Khalid mohammadi
:
= L
= l
= Dia
45 :
Khalid mohammadi
=
d 1
= ( d d 1) 0.42d 0.45d
sin 45 0.707
:
0.45d = 0.9d = 2
d
() cover .
( )30:
d d
= - = 2d 1.73d = 0.27d 0.3d
sin 30 tan 30
30 :
= 2 0.3d = 0.6d
Framed ( R.C.C :
)Building ( )Plinth Area Rate
:
( :)Brick work 20 cm
1:6 . 1:3
hoop iron 25 mm 1.5 mm .
:Reinforced Work R.C.C
( )1:3
Mild Steel . .
-:
i. R.C.C footing of columns 0.5%
ii. R.C.C beams 1.0%
iii. R.C.C columns 1.5%
iv. R.C.C chujja and sunshade 0.5%
v. R.C.C roof slab 0.8%
Khalid mohammadi
:
. 12 8cm . 4 cm
fanlight 4 cm .
fittings.
12 mm ( :)Finishing
( )1:6 . .
SECTION ON ABC
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Khalid mohammadi
Estimating of R.C.C Slab
.
)Details of Measurement and Calculation of Quantities (Ex. 2
R.C.C
()m
3
) (m
R.C.C
2.495 0.12 3.30 6.30 1 1
. 1:2:3
Khalid mohammadi
12 mm dia.@ 0.89
kg/m
Side cover 4 cm :
L = 3.3 2 side 24 cm c/c
:
6.33 3 2
:
6.33 3 2
33.42
0.22 151.92 151.92
kg
197.54
kg
Khalid mohammadi
ABSTRACT OF ESTIMATED COST
1. R.C.C work 1:2:4 excluding steel
and its bending but including centering
and shuttering and bending of steel 2.495 m
3
675 Rs/m3 = Rs. 1684.12
2. Steel bars including bending ( mild
steel ) in R.C.C work 197.5 kg 5.15 Rs/kg = Rs. 1017.13
Total = Rs. 2701.25
Add 5% for Contingencies and Workcharged Establishment Rs. 135.06
Grand Total Rs. 2836.31
:
R.C.C ()
:
Area of centering and shuttering 6.00 m 3.00 m = 18 m2
Rs 20 per sq m
Cost of centering and shuttering = 18 20 = Rs. 360
. 5 overlaping ()
45 18
.
Khalid mohammadi
Estimating of R.C.C Beam
: 8 m
40 cm 75 cm
R.C.C
()m
2.58 1:2:4
3
0.75 0.40 8.60 1 1
. m
end cover 4 cm
L = 8.6 2 end
covers + 2
hooks 20 mm
= 8.6 0.08 + 106.33 4 8.92 8.92 4 2.98
= )(18 x 0.022 kg = 2.98
8.92 m. 106.33 kg
2
L = 8.6
)0.08+(18 0.02
+ 0.6 = 9.48 m 93.66 4 9.48 9.48 4 20 mm
kg = 2.47 2.47 :
93.66 kg
Khalid mohammadi
12 mm
0.89 kg/m
L = 8.6 0.08 +
( 18 0.012 ) = 2 8.74
8.74 m 15.56 0.89 = 8.74 2
kg 15.56 kg
0.62 10 mm
L = (2 65 + 12 kg/m
2 32) + 2 2.42 2 5 cm
hooks + extra
30 cm = 194 cm 20 cm
2.42 2 4
+ (18 1)+30
cm = 2.42 m
18 2.42
27.01
0.62 = 2.42 18
kg
27.01 kg
6 mm
14 2.42
7.45 0.22 kg/m
0.22 = 2.42 14
kg 35 5.2
7.45 kg
cm
250.01
kg
Total 3029.05
3% Contingencies 90.87
2% Workcharged Establishment 60.58
Grand Total 3180.50
Khalid mohammadi
Note - (i) if centering and shuttering is paid separately, the area and cost can be found as
follows:-
Area of centering and shuttering = ( Bottom and two vertical sides length + two
ends.) = [(40 cm + 2 75 cm) 8.60 m] + (2 40 cm 75 cm) = (1.90 8.60) + (2 0.40
2
0.75) = 16.34 + 0.60 = 16.94 m .
Cost of centering and shuttering @ Rs. 20.00 per sq m = 16.94 20.00 = Rs. 338.80.
(ii) for overlapping at joints 5% of the whole steel may be provided in the estimate.
Length for hooks and bent ups in steel reinforcement bars for two hooks take
length as 18 dia. of bar. For 45 bent ups at both end; add one depth in between bars.
Khalid mohammadi
R.C.C COLUMN WITH FOUNDATION
: R.C.C
:
Cover 5cm 4cm.
1 2 2 0.83 3.32m3 .1 :
1 2 2 0.25 1m3 :
Khalid mohammadi
Prismoidal Formula :
h 0.50 2 2 0.35 2
( A1 4 Am A2 ) ({2 4 ) 0.352} 0.804m3
6 6 2
= 1.804 = 0.804 + 1 .
.4 1:2:4 :
0.32
( 1 ) 3.3 0.233m3 :
4
.5 :
12 mm 15 cm 0.89 kg/m
:
200cm 8cm
No. of bars 1 14 nos. one way
15
Total 2013.44
Add 3% for Contingencies 60.40
Add 2% for Workcharged Establishment 40.27
Grand Total 2114.11
2.00 0.35
(a) Footing trapezium portion 4 nos. sloping height
2
Khalid mohammadi
R.C.C STAIRCASE
Khalid mohammadi
10 mm bars @ 12 4 cm side cover
cm c/c
12 mm bars @ 12 cm
c/c
:
.
Khalid mohammadi
R.C.C
()m
1:2:4
.
0.150 0.25 0.50 1.2 1
L = 3.21 m
1.156 0.15 1.20 3.21 2
Bearing = 15 cm 1
2.40 m3
2
0.495 1.20 1:4
m3
20 mm
10.97
m2
2.5 cm nosing
1.20 2 12
28.80 r - - in steps in 1:3 4
m cement mortar
Khalid mohammadi
2.5 cm
1:2:4 5
6.48 m2 - 1.20 2.70 2
12 mm
109.16 0.89 kg/m
kg
10 mm
53.17 0.62 kg/m
kg
0.39 8 mm
. 6
45 kg kg/m
85.02
kg
292.35
kg
L = 2 * 3.21 + 0.4 6.82 R.C.C. 1:2:4
- - 6.82 1 7
L = 6.82 m rm Hand rail
R.C.C. 1:2:4
Newal Posts
0.01 0.10 0.10 1 1 Ground Floor 8
0.01 0.10 0.10 1 1 First Floor
3
0.02 m Total
Cap of Newal
9
2 nos. - - - 2 Post of c.c
:
12 mm 0.89 kg/m
:
Khalid mohammadi
:
: 12 mm
10 mm 0.62 kg/m
:
: 10 mm
8 mm 0.39 kg/m
:
Khalid mohammadi
:
: 8 mm
16 mm 2.01 kg/m
No = ( 11 2 2 ) + 3 in middle landing = 47 nos.
L = 0.90 m
W = 47 0.90 2.01 = 85.02 kg
Khalid mohammadi
R..C.C RETAINING WALL
30 :
:
1:2:4 .1
Base Slab ( Toe and Heel ):
Quantity = No. Length Width Height
Quantity = 1 30 3 0.50 = 45.00 m3
3.60 m
Stem:
Quantity = 1 30 6.00 = 72.00 m3
Total = 45 + 72 = 117.00 m3
.2
Stem
Right side 60 cm
22 mm Dia. Bars
22 mm Dia. main bars @ 40 cm c/c ( full height )
L1 = 76 7.53 = 572.28 m
Khalid mohammadi
22 mm Dia. main bars up to 3.60 m ht. @ 40 cm c/c ( remaining bars )
L2 = 75 5.13 = 384.75 m
14 mm Dia. bars
14 mm Dia. distributing bars right side if stem @ 25 cm c/c
L1 = 27 31.52 = 851.04 m
Khalid mohammadi
30 0.10
No 1 101 nos.
0.30
L = 6.50 top and bottom covers + 2 hooks
= 6.50 ( 0.05 + 0.07 ) + ( 18 0.014 ) = 6.63 m
L2 = 101 6.63 = 669.63 m
10 mm Dia. bars
10 mm Dia. distributing bars left side stem @ 30 cm c/c
Base Slab
10 mm Dia. distributing bars at bottom (toe) @ 25 cm c/c
Khalid mohammadi
1.65 0.60 0.25 0.05
No 1 13nos.
0.20
L 31.06m
Length same as above.
L3 13 31.06 403.78m
LT L1 L2 L3 1304.52m
16 mm Dia. bars
16 mm Dia. main bars at bottom (toe) @ 15 cm c/c
30 0.10
No 1 200nos.
0.15
L (0.75 0.60) 0.30 0.05 (18 0.016) 1.89m
L1 200 1.89m 378.00m
30 0.10
No 1 300nos.
0.10
L (1.65 0.60 0.25) 0.05 (18 0.016) 2.74m
LT L1 L2 1200m
Khalid mohammadi
:
4cm Cover 10 mm dia 30 cm c/c 25mm bent up bars 2 nos. 12mm bars
6cm Cover
6cm Cover
10 mm dia 10 cm c/c
Khalid mohammadi
(
)members
( )welding Joint .
.
:
: Tie tie .
. : Strut strut
: Principal Rafter
P.R. .
: Purline
.
:King or queen post .
2.50 3.00
4.50 3.00 ,
.
Khalid mohammadi
.
(
) .
5 )Rivets (
.
( )Gusset Plates
18 .
.
Purlins .
.
.
:
) : Galvanized Iron Sheet (G.I. SHEET
3.20 m 2.80 m 2.50 m 2.20 m 1.10 m
10 80 cm .
.
): Asbestos Cement Sheet (A.C. SHEET
2.75 m 2.25 m 2.00 m 1.75 m 1.50 m
1.05 m . 3.00 m
. 7
:
Khalid mohammadi
12 m x 6m
2.40
m ( )Gable wall .
:
.
()Ridge boards( )Purlins )Common Rafters (
( )Ceiling beams ()Battens ( )Wall Plates ()Eave boards
( )Ceiling battens
.
.
Khalid mohammadi
12 cm 1 6.60 0.10 0.12 0.0792
Stop Pieces-
Foot of King
post 10 x 4 cm . 2 0.15 0.10 0.04 0.0012
Top of King
post 10 x 4 cm . 2 0.30 0.10 0.04 0.0024
Cleats for plinth
8 x 8 cm 2 0.15 0.08 0.08 0.0019
Total of one 0.2179
truss m3
Wood work for 4 x 0.2179 = 0.8716
4 trusses 0.8716
m3
Common rafters
10 x 6 cm at 80
12
cm c/c 2x16 4.10 0.06 0.10 0.7872 No. 1 16
0.8
Purlins 12 x 8
10 cm bearing in to
cm 2 12.20 0.08 0.12 0.2342 gable walls.
Ridge boards
15 x 5 cm 1 12.20 0.05 0.15 0.0915
Eave boards 20
x 2.5 cm 2 12.20 0.025 0.20 0.1220
Wall plates 10 x
8 cm 2 12.20 0.10 0.08 0.1952
Battens 4 x 4cm 2x14 12.20 0.04 0.04 0.5466
Ceiling beams
10 x 6 cm 6 12.20 0.06 0.10 0.4392
Ceiling battens
(in between
beams) 5 x 5
L = 6.00 6 x 0.6 =
cm 11 5.64 0.05 0.05 0.1551 5.64 m
Total 3.4426
m3
2. Iron Work
Three way
straps at the
ridge joint Length measured
50 x 6 mm 2 0.75 - - 1.50 from drawing
Khalid mohammadi
U- shaped or
stirrup strap for
central bottom
joint Wt. of 50 x 6mm
50 x 6 mm 1 1.30 - - 1.30 M.S. Flat = 2.4 kg/m
Heel straps
inverted U-
shaped
(inclined) or the
end joints 50 x
6 mm 2 0.80 - - 1.60
Total ... 4.40 m 4.40 x 2.4 kg/m
10.56 = 10.56 kg
Anchor bolts 20 kg
mm dia. @ 2.47
kg/m 2 0.30 - - 1.48 kg 0.60 x 2.47 =1.48
kg
Head and nuts
@ 0.25 kg/No 2 - - - 0.50 kg
2 x 0.25 = 0.50 kg
Anchor washer
8 mm thick @
62.8 kg/sq m 2 0.08 0.08 - 0.82 kg
0.013 x 62.8 = 0.82
Total for one kg
truss 13.36 kg
5. A.C. (plain)
sheet ceiling
including
2
beading 1 12.00 6.00 - 72.00 m Ceiling beams and
Khalid mohammadi
battens are taken
under wood work
6. Painting two Width column is for
coats over one perimeter.
coat of priming
Principal rafter Perimeter = (12+10)
12 x 10 cm 2 3.50 0.44 - 3.08 x 2 = 44 cm.
Strut 10 x 10
cm 2 1.56 0.40 - 1.25
King post 10 x
10 cm 1 1.80 0.40 - 0.72
Tie beam 10 x
12 cm 1 6.60 0.44 - 2.904
Painting for 4
trusses 4 31.816
m2
Common rafters
10 x 6 cm 2x16 4.1 0.32 - 41.984
Purlins 12 x 8
cm 2 12.20 0.40 - 9.760
Ridge boards
15 x 5 cm 1 12.20 0.40 - 4.880
Eave boards 20
x 2.5 cm 2 12.20 0.45 - 10.980
Wall plates 10 x
8 cm 2 12.20 0.36 - 8.784
Battens 4 x 4
cm 2x14 12.20 0.16 - 54.656
Ceiling beams
10 x 6 cm 6 12.20 0.32 - 23.424
Ceiling battens
5 x 5 cm 11 5.64 0.20 - 12.408
Khalid mohammadi
A.C. sheet
ceiling including
beading 1 12.00 6.00 - 72.00
Total 270.692
m2
Khalid mohammadi
.
.
10
.
:
.1
.2
.3
.4
.
5 10
. 15 20
1.5 .
:
.
:
1.25 m3 1
1.00 m3 2
1.5 m3 ( ) 3
1.25 m3 4
0.55 m3 5
5.00 m2 () 6
0.80 m3 7
8.50 m3 8
0.40 m3 9
3
0.40 m 10
6.00 m3 11
5.00 m3 1:2:4 12
1.00 m3 ()R.B 13
3.00 m3 ()R.C.C 14
8.00 m2 12 mm 15
10.00 m2 16
2
70 m 17
2
200 m 18
2
25 m 19
2
35 m 20
2
5.00 m ( )6 mm 2 cm 21
2
0.15 m 22
3
0.25 m 25 mm 23
3
0.40 m 40 mm 24
3.00 m3 25
Khalid mohammadi
2.00 m3 26
1.00 m3 27
4.00 m3 28
600 29
30
3.00 m3 :
4000 :
15
3
5.50 m :
:
: 2.83 m3
.1
2.83 1.5 9 :
.
.2
15 :
2.83 m3
.
: 2.83 m3
2.83 m3
.
:
1 .1
2.83 m3
.
: .2
3
. 9.60 m
.3
.
3
: 2.83 m
:
3
2.83 m
.
: 2.83 m3
1:4
4 2 :
2.83 m3
.
:
: .1
0.18 m3
.
15 : .2
40 mm
. 2 x 1.15 m2
:
Khalid mohammadi
4 cm 40 m2
.
:
12 mm .1
:
40 m2
.
: .2
. 60
: .3
2
10 m
.
:
( )Strength
( )Workability of Concrete .
.
:
M 250 W/C = 0.45 1:1:2
M 200 W/C = 0.50 1:1.5:3
M 150 W/C = 0.55 1:2:4
M 100 W/C = 0.65 1:3:6
M 50 W/C = 0.75 1:4:8
:
.1 1.52
152
.
:
= 100 m3
= 100 m3 + 52 % (100 m3) = 152 m3
1:2:4 ) (
:
152 152
( 1 ) 1 21.7 m3
1 2 4 7
( ) 50 )30 (
.
152
2 152 43.4 m3
4 7 86.9 m 3
7
Khalid mohammadi
100 .2
2.5
1:2:4
:
10
50
4.125 4.125
( 1 ) 1 0.589 m3
1 2 4 7
4.125
2 1.179 m 3
7
4.125
4
2.357
m3
.3
7 2 100
.
100 .4
1:2:4 4
:
4 0.10 4 4.40 m 3
50
6.60 6.60
( 1 ) 1 0.943 m 3
1 2 4 7
6.60
2 1.886 m3
7
152 .5 7
.
6.60
4 3.771 m 3
sum of constructi on material proportion
7
Khalid mohammadi
100 .6
6
1
1:1
2
:
1.08 1.08
( 1 ) 1 0.40 m 3
11 1 2.50
2
1.08
1.5 0.60 m 3
2.50
Buildings Glossary
Section Name
No English Entries
English
peg
plant -
Preliminaries
preliminaries -
shed -
signboard ()
survey mark
bill of quantities -
)(BOQ -
Requirements
.
General
diagram -
2
.
document - -
layout - -
levels
Demolit
contaminated
ion
demolition -
3
encroachment -
Khalid mohammadi
explosives
infective
liquid -
hazardous
material
noxious -
salvage -
toxic
bark
bulk
bulkhead
.
density
disposal
.
Site preparation
drip line
embankment -
4
erosion ( )
grubbing
plant -
rubbing
rubbish -
rubble
scrap
scrub
spoil
.
stockpile
Khalid mohammadi
stump -
trunk
bearing surface
boulders
cavities -
datum -
earthwork -
excavation
excess -
fault
-
Earthwork
fill maternal
.
5
fissure ( )
layer -
line of influence
piling
pond -
shoring
silt -
strip
turnaround
underpinning ( )
unstable -
Khalid mohammadi
dewatering -
trenching
Service
.
6
reinstate
trench - -
.
earth block
Earth block
nailer -
walling
.
7
arch -
chase (
)
- -
-
.
Brickwork
Chip
coal -
8
crack -
english bond
.
flaws
frog ( )
.
Khalid mohammadi
holding down nailing
bolts block
.
joint -
morter smears (
)
nailing block ( )
.
ring beam
.
nodule
rake
.
scrubbed -
( )
Vitrify (
)
bracing .
course - -
- .
foamed -
footing ( )
foundation
Stonework
igneous stone
jointing
9
lintel
pointing
quarry
raking -
(
)
sandstone -
taping ( )
Khalid mohammadi
tooting
.
apex -
Light steel work
prefabricated
10
.
unseasoned -
timber
.
corrugated metal
sheet
cured corrugated
sheet .
downpipe
.
eave -
Roofing
flashing
11
Khalid mohammadi
ridge -
roof cappings
.
skylight
sump
.
ventilator
barrel bolt
.
bristles (
Doors and door hardware
buffer (
)
closer
12
.
door trims -
.
doorset -
hardware
.
ferrul ( )
Khalid mohammadi
fire-doorset
fixed pin hinge ( )
flashing
floor socket
.
flush door -
.
furniture
hardware
.
.
hinge
joinery door
.
latch
louver blades
.
louvered door
( )
.
nib -
rails
( )
reveal
smoke - door set
spreader
.
Khalid mohammadi
square edges - 90
( - -
)
sticking
stile (
)
strike plate
( .
)
timber veneer
tower bolt
.
weathering
wide throw hinge
.
.
abrasion
backing rod
(
.
) .
Glazing
EPDM
13
.
glazing -
glazing plastic
.
impregnated ( )
obscuring -
( )
Khalid mohammadi
rebated timber
beads
.
sash - .
selvering
)sheaves (sheaf (
)
.
toughend glass
wheater strip
-
.
( )
.
Angle bead (
bead )
bead
. bead
Plastering
.
14
cease
drip bead
)
hoeing -
hydrated lime
mature bin
.
Khalid mohammadi
mechanical key
.
niche
quicklime
stop bead bead
.
back off
( - )
bonding treatment
( )
.
bucket
{( )} (
tiling
bulk
15
)
caulked joint .
conspicuous -
damp -
dampening
deleterious
dense concrete
efflorescing sat
Khalid mohammadi
floor finish devider finish
.
glazed
grout ( )
grouting () -
inhibit
nib -
.
nominal
paver ( )
( ) .
pigment -
.
porous tile
render
screeded bed
surface
.
sealant
.
set out - -
shrinkage -
situ -
soak -
terra cotta tiles (
).
terrazzo
tiling
toppings -
trowel - -
voids
bead .
Paintin
(
16
Khalid mohammadi
coat .
gloss
opaque coat (
)
putty
sanding
stain () -
tinting
veneer ( )
constraints -
cowl ( )
.
down pipe .
gauge (
)
water services
hose
jagged -
17
non-habitable (
)
reel -
.
strainer
.
substrate -
Khalid mohammadi
V=L*W*H .1 :
D= b2+a2 +c2 .2 :
P=AB+AC+BC .3 :
V=1/3 W* H * L .4 :
A=6 a 2 .5 :
A=r2 .6 :
V=r2 *h .7 :
V=4/3r3 .8 :
A=4r2 .9 :
A=*d .10 :
A=L*W .11 :
A=a2 .12 :
A=b*h .13 :
A=1/2b*h .14 :
3/4*a2 =A .15 :
Khalid mohammadi
P=F/A : -24
F=M*G : -25
P=Q*A : -26
Q=AD/T : -27
A=QT/D : -28
D=QT/A : -29
T=AD/Q : -30
F1/sin=F2/sin=F3/sin : -31
P=*G*H : -40
: -41
Abar1*Nbar1=Abar2*Nbar2
: -42
Lbar=Wslab/specing*Lslab
: -43
e=m/n
: -44
spc=100*r2/Aslab
As=m/Ra*h* =0.9 ra=2100kg/cm 2 : -45
Khalid mohammadi
kg/m2 kg/m2
48 1.2 40 W=0.02m DL 1
=2000kg/m3
32.4 1.2 27 DL 2
W=0.015m
=1800kg/m3
38.4 1.2 32 DL 3
W=0.02m
=1600kg/m3
360 1.2 300 DL 4
W=0.12m
=2500kg/m3
420 1.4 300 LL 5
DL=478.8kg/m2 (: )g
P=420kg/m2 (: )p
q=g+p=478.8+420=900kg/m2 :
:
IB = b*h / 12 =0.25*0.503 /12 = 0.0026 m 4
3
:
IC = 0.35*0.35/12 = 0.00125 m 4 :
:
iB = m*IB / LB :
iC = m*IC / hC :
Bea m= 1 :
m Colu Beam (0.25x0.5)m
Khalid mohammadi mn
Column (0.35x0.35)m
Spacings .........:
12.......................................................
30.........................................................
20........................................................
........... 15 ..............
.................................................................... .1
......................... .2
............................................................... .3
, ................................................... .4
............................................................. .5
................................................................. .6
............................................................ .7
...................................... .8
................................................................. .9
................................................. .10
.................................................................. .11
................................................................. .12
.................................................. .13
...................................... .14
................................................. .15
...................... .16
, .................. .17
.............................. .18
............................................................ .19
................................................................... .20
Khalid mohammadi
Khalid mohammadi
Weight .............................
565.25 565248 80 1
7.07 7065.6 4 1
1.77 1766.4 4 1
0.44 441.6 4 1
0.11 110.4 24 1
0.005 4.6 24 1
Area ..........................
5 1
100 1 20
1/ 5 2000 1 20 400
1 10000 5 100 2000
10-8 -: :
.1 ( )
.2
.3
.4
.5 ( )
.6
.7
.8 ( )
-: :
Khalid mohammadi
.
-: :
-
-
-: :
( )
-: :
.
-: :
* ** =
= / =
= / =
= / =
Khalid mohammadi
:
:
3
250m =
100m2 =
300m2 =
:
3
50m =
30m2 =
150m3 =
Layer of road:
1. Wearing course.
2. Surface course.
3. Binder course.
4. Base course.
5. Sub base course.
6. Sub grade.
: -
) 5% (
.
Q = 0.5(g+p) = Q = 0.5*q*lb
Khalid mohammadi
Q = 0.5*1.97*6 = 5.91T
Q<RT*Bw*hb
RT = 7.2T
Bw = 25cm
Hb = 51.5cm
Q<RT*Bw*hb
5.91<7.2*25*51.5
5.91<9.27 .
Khalid mohammadi
Cm2 Kg/M mm
0.0078 0.006 1
0.049 0.038 2.5
0.017 0.055 3
0.096 0.075 3.5
0.126 0.098 4
0.159 0.125 4.5
0.196 0.154 5
0.238 0.188 5.5
0.283 0.222 6
0.385 0.302 7
0.503 0.495 8
0.606 0.499 9
0.785 0.617 10
1.131 0.888 12
1.539 1.208 14
2.011 1.578 16
2.545 1.998 18
3.142 2.466 20
3.801 2.984 22
4.525 3.551 24
4.909 3.853 25
5.389 4.168 26
5.726 4.495 27
6.158 4.839 28
7.069 5.549 30
8.042 6.513 32
10.180 7.990 36
12.566 9.860 40
Khalid mohammadi
Lit/M3 Kg/M3
Kg/M3 M3/M3
135 60 1.120 150
140 100 1.090 200
145 120 1.055 250
150 135 1.020 300
150 150 1.005 325
155 170 0.990 350
Lit/M
3 Kg/CM Kg/M
1.5:1 2:1 2 3
135 0.90 0.60 1.01 0.50 60 150
0 0 0
140 0.85 0.57 0.97 0.48 100 200
5 0 0 5
145 0.81 0.54 0.93 0.46 120 250
0 0 0 5
150 0.76 0.51 0.89 0.44 135 300
8 0 0 5
150 0.76 0.50 0.88 0.44 150 325
0 5 0 0
155 0,75 0.50 0.86 0.43 170 350
0 0 5 5
Kg/CM2
250 200 170 150 100
177 177 170 167 177 1
402 361 298 276 268 2
Khalid mohammadi
626 640 683 713 707 1 3
540 551 564 562 557 2 3 4
660 673 689 686 680 4 5
75 60 45 35 60 6
2463 2470 2470 2455 2445 - 7
kg/m3
66:34 66:34 65:35 64:36 64:36 8
()
Kg/CM3
250 200 170 150 100
44 41 57 60 66 -
Kg
4.5 5 5.5 6 6.5
100 100 100 100 100 Kg
2 2 2 2 2
156 177 229 256 246 Kg 1
3.5 4 5 5.5 6
134 153 189 202 208 Kg -2
3 3 4 4.5 4.5 3
164 186 231 247 256 Kg 4
4 4.5 5.5 5.5 6
Kg/CM2
Kg Kg
- 4 85-105
- 110 4 9
50 110 10 24
120 110 25 49
200 20 50 96
350 35 100 199
Khalid mohammadi
450 45 200
.
%40 ( )3-1
%5 .
M3 M3 M3 Kg Kg : :
0.148 1.04 0.216 153 53 24 : 5 : 1 50/110
0.183 1.00 0.200 142 120 10 : 2 : 1 120/110
0.144 1.00 0.250 178 60 20 : 5 : 1 60/140
0.133 0.98 0.245 175 98 12 : 3 : 1 100/140
0.148 0.87 0.346 246 104 10 : 4 : 1 110/170
0.123 0.92 0.360 255 48 23 : 9 : 1 110/180
0.123 0.90 0.300 213 120 9:3:1 110/210
0.210 0.75 0.431 306 149 6 : 3.5 : 1 200/300
: ( )710
.
M3 M3 M3 Kg Kg : :
0.300 1.03 0.232 165 52 20 : 4.5 : 1 50/110
0.300 1.00 0.275 195 50 20 : 5.5 : 1 50/190
0.320 0.80 0.400 284 103 8:4:1 100/210
0.320 0.90 0.300 213 103 9:3:1 100/150
0.320 0.90 0.300 213 150 6:2:1 150/150
Khalid mohammadi
M3 M3 Kg :
0.209 1.11 220 6:1 200
0.230 1.08 260 5:1 250
0.251 1.09 312 4:1 300
0.280 1.01 346 3.5 : 1 350
0.290 0.98 390 3:1 400
0.300 0.93 445 2.5 : 1 450
0.280 0.87 520 2:1 500
M3 M3 M3 Kg :
0.120 1.060 0.236 168 4.5 : 1 110
0.116 1.040 0.260 185 4:1 130
0.116 1.020 0.288 205 3.5 : 1 140
0.116 0.975 0.325 230 3:1 150
0.143 0.925 0.371 263 2.5 : 1 180
0.130 0.865 0.433 307 2:1 210
0.130 0.780 0.520 396 1.5 : 1 250
Khalid mohammadi
M3 M3 Kg :
0.320 1.000 340 3:1
0.320 0.900 450 2:1
0.340 0.810 540 3:2
0.350 0.680 680 1:1
- - Kg - M3
M3
0.98 0.49 100 12: 6: 1 60
0.96 0.48 120 10 : 5 : 1 75
0.94 0.47 150 8 :4 : 1 100
0.92 0.46 200 6:3:1 120
0.92 0.46 250 5 : 2.5 :1 135
0.90 0.45 276 4 : 2: 1 150
0.81 0.54 296 3: 2 : 1 170
0.84 0.42 390 3 : 1.5 : 1 200
0.80 0.4 402 2: 1 : 1 250
Kg/M3
1800 ( 1
)
1700 ( 2
)
1600 ( 3
)
2400 4
2400 5
2000 6
1400 7
- 2200 8
2300
2400 9
Khalid mohammadi
Kg/M3
1440 10
1760 11
- 1840 12
1410
- 2000 13
1600
- 1600 14
1540
- 2000 15
1760
- 2000 16
1800
1000 17
1800 ( ) 18
1700 ( ) 19
1600 ( ) 20
1100 ( ) 21
600 22
800 23
1200 24
300 25
2200 26
2000 27
1800 28
400 29
2600 30
1000 31
200 32
400 33
900 34
7850 35
Khalid mohammadi
S.No Type of work Mix.
Recommended
1 For rich mix. Concrete work in M 250 (1 : 1 : 2)
columns, beams etc.
For water retaining structures, piles, M 200 ( 1 : 1.5 : 3 )
2 per- cast works or in situation where
dense concrete is desired.
3 Reinforced concrete beams, slabs, M 150 (1 : 2 : 4 )
and columns roads. Etc.
4 Foundations for buildings , mass M 100 ( 1 : 3 : 6 )
reinforced concrete works , machine
foundation etc.
5 For mass concrete. 1:4:8
Kg/cm2 Kg/cm2
M - 100 135 100
M - 150 200 150
M - 200 260 200
M - 250 320 250
M - 300 380 300
M - 350 440 350
M - 400 500 400
Bearing Overall Overall Reinforcement
Clear length at length slab Longitudinal bars
span M each end of slab thickness Bottom bars Top bars
mm m mm Dia Spacing Dia Spacing
mm mm mm mm
1.0 300 1.6 190-150 16 150- 10 300
115
1.5 300 2.1 220-180 16 105-90 10 300
2.0 300 2.6 240-215 16 100-80 10 300
2.5 300 3.1 270-245 16 90-75 10 300
Khalid mohammadi
3.0 300 3.6 305-275 16 75-70 10 300
3.5 300 4.1 340-315 16 60-65 10 300
4.0 300 4.6 370-345 16 100-90 10 300
5.0 400 5.8 420-395 16 90-75 10 300
6.0 400 6.8 475-445 16 75-68 10 300
RENFOCEMENT DETAILS FOR RCC SLABS FOR CULVERTS
Freely supported with 75mm thickness Asphalt Concrete Wearing Coat.
Khalid mohammadi
Kg/m kg/m Kg/m kg/m
m
m
.
.
.
REFERENCES
1. Prof. M.Mirwais
2006.
Estimation and its Conventional types in Construction.
2. Prof. B.N. Dutta, Estimating and Costing in Civil Engineering.
Twenty-Fifth Revised Edition, 2001.
3. Different Internet sites
4. Ministry of Public Work.
Man Power Manual last Edition, 1965
Khalid mohammadi