You are on page 1of 1

Form No. 3-QC-23.

0 CLIENT: CONSULTANT: CONTRACTOR:

METHOD STATEMENT
SUBMITTAL FORM
Project No. & Name: RAK FISHERMEN’S PORT

Record Reference: MS-020 Date: 10.04.2014


Project Details: N/A Clients Project Number: CPC-01313-C1
Client: CROWN PRINCE COURT Engineer: Dorsch Gruppe DC Abu Dhabi
Contractor: China Harbour Engineering Co.L.L.C
IR No: N/A Rev No : 01

Discipline  Civil  Architecture  Mechanical  Electrical  Others

G Method Statement for CONCRETE REPAIR MATERIALS / Quality Control Procedure For CONCRETE REPAIR MATERIAL

1- purpose 1- purpose
2- scope 2- scope
3- reference 3- reference
4- definitions 4- definitions
5- responsibilities 5- responsibilities
6- equipment 6- procedures
7- procedure 7- attachment
8- health & safety requirements
9- attachments

Contractor Signature:

Discipline Engineer: QA/ QC HSE MEP Construction


Manager:
The Engineer:
A- Approved B- Approved with Comments C- Revise and Resubmit D- Rejected
Comments: