SCHEDULES
SCHEDULE -A
1 The Site
1.1 Site of the proposed Dwarka Expressway between Design Chainage km 9+500 to 19+700
(Package-3) in the State of Haryana shall include the land, buildings, structures and road works as
described in Annex-I of this Schedule-A.
1.2 The dates of handing over the Right of Way to the Contractor are specified in Annex-II of this
Schedule-A.
1.3 An inventory of the Site including the land, buildings, structures, road works, trees and any other
immovable property on, or attached to, the Site shall be prepared jointly by the Authority
Representative and the Contractor, and such inventory shall form part of the memorandum referred
to in Clause 8.2.1 of this Agreement.
1.4 The alignment plans of the Project Highway are specified in Annex-III. In the case of sections
where no modification in the existing alignment of the Project Highway is contemplated, the
alignment plan has not been provided. Alignment plans have only been given for sections where
the existing alignment is proposed to be upgraded. The proposed profile of the Project Highways
shall be followed by the contractor with minimum FRL as indicated in the alignment plan. The
contractor, however, may improve/upgrade the Road Profile as indicated in Annexure-III based on
site/design requirement.
1.5 The status of the environment clearances obtained or awaited is given in Annex IV.
Annex -I
(Schedule-A)
Site
1. Site
Site for the project highway comprises the proposed Dwarka Expressway between Design Chainage
km 9+500 to 19+700 (Package-3) in the State of Haryana. The land, carriageway and structures
comprising the site are described below.
2. Land
The site of the project comprises the land (Sum-total of Land already in possession & Land to be
possessed) as described below:
1. 9+500 19+700 90
3. Carriageway
4. Major Bridges
Nil
The site includes the following ROB (road over railway line)/RUB (road under railway line):
Nil
6. Grade separators
Type of structures
Chainage No. of Spans with span
S. No. Foundation Super Width (m)
(km) length (m)
Structure
Nil
7. Minor bridges
2 13+825 3 x 7m 57m
3 17+645 3 x 7m 46m
Nil
9. Underpasses (vehicular, non-vehicular)
Nil
10. Culverts
NIL
The details of roadside drains within the existing ROW are as follow:
Existing Chainage Approx.
S. No. Left / Right Width Remarks
Start End Length (m)
1 9+500 11+600 2100 Both 0.5m to 1.00 m
2 12+900 19+700 6800 Both 0.5m to 1.00 m
NIL
18. Referencing System
Annex -II
(Schedule-A)
The dates on which the Authority shall provide Right of Way to the Contractor on different stretches of
the site are stated as below
Sl. No. From Km to Length (km) Width (m) Date of Providing
Km ROW*
1 2 3 4 5
1 Full Right of Way
2 Part Right of Way
3 Balance ROW
* The dates specified herein shall in no case be beyond 150 (One hundred and fifty) days after the
Appointed Date.
Annex -III
(Schedule-A)
Alignment Plans
The existing alignment of the Project Highway shall be as modified in the following sections as per the
Plan & Profile for the Project attached herewith.
Annex -IV
(Schedule-A)
Environmental Clearances
1. Environmental clearance approval form MoEF is not required as per clause 7(f) of EIA Notification
2006 and subsequent amendment issued from MoEF.
SCHEDULE -B
Development of the Project Highway shall include design and construction of the Project
Highway as described in this Schedule-B and in Schedule-C.
2 Dwarka Expressway
The Project Highway shall be designed and constructed in conformity with the Specifications and
Standards specified in Annex-I of Schedule-D.
Annex -I
(Schedule-B)
1.1 The Project Highway shall follow the alignment as shown in the alignment plans specified in Annex
III of Schedule-A. Geometric deficiencies, if any, in the proposed horizontal and vertical profiles
shall be corrected as per the prescribed standards for plain terrain to the extent land is available.
2.1 General
Geometric design and general features of the Project Highway shall be in accordance with the
manual.
Nil
Vertical
Length Proposed Width
S. No. Design Chainage Clearance Remarks
(m) Structure (m)
(m)
10+660 to 18+810 8150 5.5
Elevated As per
1 34.0
18+810 to 19+010 200 Structure Design Ramp on Structure
Profile
Length and width are w.r.t.
Main Carriageway;
Vertical
Length Proposed Width
S. No. Design Chainage Clearance Remarks
(m) Structure (m)
(m)
Both side approaches of the
depressed cross-road
through underpass are
included in the scope of
work;
As per
Both side service road on
14+600 to 14+800 200.0 Design
ramp of elevated structure
9.0 Profile
Elevated (LHS) Both side service road on
7 14+800 to 15+250 450.0 5.5
Structure 9.0 elevated structure
(RHS) As per
Both side service road on
15+250 to 15+450 200.0 Design
ramp of elevated structure
Profile
Length and width are w.r.t.
Main Carriageway;
Vertical
Length Proposed Width
S. No. Design Chainage Clearance Remarks
(m) Structure (m)
(m)
As per
Both side service road on
17+550 to 17+750 200.0 Design
ramp of elevated structure
Profile
Length and width are w.r.t.
Main Carriageway;
2.8.2 Lateral clearance: The width of the opening at the overpasses shall be as follows:
Length of
Location of Service Road
S. No. LHS RHS Service Remarks
(from km to km)
Road (km)
1. Km 9+540 to km 10+700 11.5m 11.5m 1.160
Varies from
80 m of existing
Varies from 11.5m 11.5m to
2. Km 10+700 to km 10+900 0.200 service road can be
to 14.5m to 11.5m 14.5m to
used
11.5m
Existing Road
3. Km 10+900 to Km 11+350 12.5m 12.5m 0.450 section shall be
used
New Road of
11.5m wide can be
constructed for
varies from
varies from 12.5 m length of 100 m.
4. Km 11+350 to 11+500 12.5 m to 0.150
to 18 m Existing service
18 m
road of 12.5 m can
be used for a
length of 100 m
11.5 11.5
5. Km 11+500 to Km 11+700 0.200 New Construction
11.5 -
6. Km 11+700 to km 11+935 New Construction
Underpass with
- 9.5 Box Length of 40
7. Km 11+700 to Km 12+400 0.500
m remaining 460
m under ramps
- 9.0 At Grade Service
8. Km 11+700 to Km 12+400 0.500
Road
12.5 - Existing Service
9. Km 11+934 to 12+265 0.331
Road
8.0 -
10. Km 11+934 to 12+265 0.135 New Construction
11.5 -
11. Km 12+265 to Km 12+400 0.135 New Construction
11.5 11.5
12. Km 12+400 to 12+800 0.400 New Construction
12.5 12.5 Existing Service
13. Km 12+800 to 13+000 0.200
road
200 m of existing
Varies from service road of
Varies from 12.5
12.5 to 31 12.5 m can be
14. Km 13+000 to Km 13+200 to 31 m 0.200
m used. Remaining
can be new
Construction
12.5 m width of
20.5 20.5 existing Road and
15. Km 13+200 to Km 14+100 0.900
8 m width of new
construction
Varies from 12.5 Varies from 200 m of existing
16. Km 14+100 to 14+200 to 31 m 0.200 service road
12.5 to 31
having of 12.5 m
Construction of Dwarka Expressway between Design Chainage
km 9+500 to 19+700 (Package-3) in the State of Haryana Page 15 of 45
National Highways Authority of India Volume II: Schedules & Annexure
Length of
Location of Service Road
S. No. LHS RHS Service Remarks
(from km to km)
Road (km)
m can be used.
Remaining can be
new Construction
12.5 12.5 Existing Service
17. Km 14+200 to 14+300 0.100
road to be used
130 m of existing
Varies from service road
Varies from 12.5
12.5 to 30 having of 12.5 m
18. Km 14+300 to 14+430 to 30 m 0.130
m can be used.
Remaining can be
new Construction
12.5 m width of
existing Road can
20.5 20.5
19. Km 14+430 to Km 14+900 0.470 be used.
Remaining can
new construction
12.5 12.5 Existing Service
20. Km 14+900 to 15+100 0.200
Road
Width Existing service
Width varies from varies from road for 12.5 m
21. Km 15+100 to 15+200 12.5 to 30 m 12.5 to 30 0.100 width can be used.
m Remaining can be
new construction
12.5m wide
20.5 20.5
22. Km 15+200 to Km 15+600 0.400 existing service
road to be widened
Width Existing service
Width varies from varies from road for 12.5 m
23. Km 15+600 to Km 15+830 12.5 to 30 m 12.5 to 30 0.230 width can be used.
m Remaining can be
new construction
Width Existing service
Width varies from varies from road for 12.5 m
24. Km 15+830 to Km 16+100 12.5 to 30 m 12.5 to 30 0.270 width can be used.
m Remaining can be
new construction
12.5m wide
20.5 20.5 existing service
25. Km 16+100 to 17+000 0.900
road to be widened
12.5m wide
20.5 20.5 existing service
26. Km 17+000 to 17+900 0.900
road to be widened
Length of
Location of Service Road
S. No. LHS RHS Service Remarks
(from km to km)
Road (km)
12.5 m 12.5 m Existing service
28. Km 18+100 to 18+200 100 m
road shall be used
width 12.5 m width of
existing service
width varies from varies from
road for a length of
29. Km 18+200 to 18+360 30 m to 12.5 m 30 m to 0.200
200 m can be used.
12.5 m Remaining can be
new construction.
12.5m wide
20.5 20.5
30. Km 18+360 to 18+800 0.560 existing service
road to be widened
11.5 11.5
31. Km 18+800 to km 19+200 0.600 New Construction
width
width varies from varies from
32. Km 19+200 to Km 19+330 21 m to 11.5 21 m to 0.130 New construction
11.5
Where service road has been shown to be varying, it is indicative only and shall be decided as per
existing road width, site requirement and detailed design duly approved by the Authority
Engineer. Any change in this varying width and the length in which it is varying shall not be
treated as change of scope.
Where existing road is used as part of service road, necessary repair and rehabilitation of the
existing pavement shall be done as per the requirement set forth in Schedule B and the Manual.
Proposed Remarks
Sl. No. Design Chainage Length (m)
Structure
Elevated
1 10+660 to 19+010 8350
Structure
Proposed Remarks
Sl. No. Design Chainage Length (m)
Structure
scope of work;
Proposed Remarks
Sl. No. Design Chainage Length (m)
Structure
2.10.2 Grade separated elevated structures and underpasses on Service Road shall be provided as per
particulars given below:
Proposed Remarks
Sl. No. Design Chainage Length (m)
Structure
2.10.3 the minimum spacing between successive expansion joints shall be 200 m.
NIL
2.13 Subway
2.13.1. New Pedestrian Subway is to be done as per particulars given below:
Clear Size
Type of Tentative
Sl. No. Location (Horizontal x Remarks
Structure Length
Vertical)
1 Km 11+060 Box 5m x 3m 100m
2 Km 11+188 Box 5m x 3m 100m
3 Km 12+050 Box 5m x 3m 90m
4 Km 13+553 Box 5m x 3m 90m
5 Km 13+646 Box 5m x 3m 90m
6 Km 14+816 Box 5m x 3m 90m
7 Km 14+900 Box 5m x 3m 90m
8 Km 16+485 Box 5m x 3m 70m
9 Km 16+596 Box 5m x 3m 70m
10 Km 17+434 Box 5m x 3m 90m
11 Km 17+544 Box 5m x 3m 90m
12 Km 18+705 Box 5m x 3m 90m
13 Km 18+818 Box 5m x 3m 90m
The subway shall have both stairways and ramps at both ends. The ramp gradient shall not exceed
1:12. As per the above particulars, subway shall be designed as per Manual and as per
IRC:103-2012.
All intersections and grade separators shall be as per Section 3 of the manual. Existing
intersections which are deficient shall be improved to the prescribed standards.
Properly designed intersections shall be provided at the locations and of the types and features
given in the tables below:
Road to be carried
Minimum Length of
S No. Location Salient Features under the
viaduct to be provided
structure
Right side Service
Underpass along
1 12+033 40.0 road is through
Service Road
Underpass
Service road on
2 13+602 510m HUDA sector Road
Elevated Structure
Service road on
3 14+855 850m HUDA sector Road
Elevated Structure
Service road on
4 16+540 510m HUDA sector Road
Elevated Structure
Road to be carried
Minimum Length of
S No. Location Salient Features under the
viaduct to be provided
structure
Service road on
5 17+487 510m HUDA sector Road
Elevated Structure
Service road on
6 18+760 510m HUDA sector Road
Elevated Structure
4.1 Widening and improvement of the existing road embankment/cuttings and construction of new
road embankment/cuttings shall conform to the Specifications and Standards given in section 4
of the Manual and the specified cross sectional details. Deficiencies in the plan and profile of the
existing road shall be corrected.
4.2 Raising of the existing road: NIL
5. PAVEMENT DESIGN
5.1 Pavement design shall be carried out in accordance with IRC : 37-2012.
Flexible pavement for new pavement or for widening and strengthening of the existing pavement
shall be designed for a minimum design period of 20 years. Stage construction shall not be
permitted.
All rigid pavements shall be designed for a minimum design period of 30 years. The minimum
thickness of rigid pavement shall be 300 mm of Pavement Quality Concrete (PQC) and 150 mm
of de-bonded Dry Lean Concrete (DLC).
Notwithstanding anything to the contrary contained in this Agreement or the Manual, the
Contractor shall design the pavement for minimum Design traffic of 75 MSA for main
carriageway (all roads except Slip/Service Road), 20 MSA for slip/service road/cross road. For
new pavement following minimum thickness of the bituminous layers shall be maintained:
BC – 40mm
DBM – 105 mm
5.4 Reconstruction of stretches
NIL
6. ROADSIDE DRAINAGE
Drainage system including surface and subsurface drains for the Project Highway shall be
provided as per IRC-SP: 50-1999.
Along all underpasses and their approaches, 1.5m wide RCC covered drain shall be constructed
on left hand side.
7. DESIGN OF STRUCTURES
7.1 General
7.1.1 All bridges, culverts and structures shall be designed and constructed in accordance with section
7 of the Manual and shall conform to the cross-sectional features and other details specified
therein.
7.1.2 Width of the carriageway of new bridges and structures shall be as follows: Nil
7.1.5 The following structures shall be designed to carry utility services specified in table below:
Nil
7.1.6 Cross-section of the new culverts and bridges at deck level for the Project Highway shall conform
to the typical cross-sections given in section 7 of the Manual.
7.2 Culverts
7.2.1 Overall width of all culverts shall be equal to the roadway width of the approaches.
All existing culverts which are not to be reconstructed shall be widened to the roadway width of
the Project Highway as per the typical cross section given in section 7 of the Manual. Repairs and
strengthening of existing structures where required shall be carried out.
Type, span, height and
SL No, Culvert Location Remarks
width of structure
7.2.4 Additional new culverts shall be constructed as per particulars given in the table below for full
width of the road:
Construction of Dwarka Expressway between Design Chainage
km 9+500 to 19+700 (Package-3) in the State of Haryana Page 22 of 45
National Highways Authority of India Volume II: Schedules & Annexure
SL Culvert Type of
Size Remarks
No. Location* Structure
1 11+500 Box 1 x 6m
2 10+610 Box 1x 2m Balancing culvert
3 14+990 Box 1x 2m Balancing culvert
4 16+650 Box 1x 2m Balancing culvert
5 16+960 Box 1x 2m Balancing culvert
6 17+220 Box 1x 2m Balancing culvert
7 18+140 Box 1x 2m Balancing culvert
8 18+800 Box 1x 2m Balancing culvert
9 19+140 Box 1x 2m Balancing culvert
10 19+280 Box 1x 2m Balancing culvert
* Note: Location is indicative only; To be identified as per site and design requirement.
7.2.5 Repairs/replacements of railing/parapets, flooring and protection works of the existing culverts
shall be undertaken as follows: Nil
7.2.6 Floor protection works shall be specified in the relevant IRC Codes and specifications. Nil
7.3 Bridges
(i) The existing bridges at the following locations shall be re-constructed as new Structures:
Nil
New bridges at the following locations on the Project Highway shall be constructed.
7.3.3 The railings of existing bridges shall be replaced by crash barriers at the following locations:
Nil
Nil
Nil
7.4.1 Design, construction and detailing of ROB/RUB shall be as specified in section 7 of the Manual.
Nil
Road over-bridges (road over rail) shall be provided at the following level crossings, as per GAD
drawings attached: Nil
Road under-bridges (road under railway line) shall be provided at the following level crossings,
as per GAD drawings attached: Nil
The grade separated structures shall be provided at the locations and of the type and length
specified in paragraphs 2.6 and 2.9 of this Annex-I.
The existing bridges and structures to be repaired / strengthened, and the nature and extent of
repairs /strengthening required are given below:
Nil
8.1 Traffic control devices and road safety works shall be provided in accordance with
IRC-SP-44-1996.
9. ROADSIDE FURNITURE
9.1 Roadside furniture shall be provided in accordance with section 9 of IRC: SP: 87-2013 and as per
Schedule D.
9.2 Overhead traffic signs: location and size
The Overhead traffic signs shall be provided as per numbers given below. The locations shall be
finalized in consultation with Authority Engineer.
S. No. Type Nos Remarks
1 Cantilever 30 Location to be decided in consultation with the Authority Engineer
2 Full Gantry 20 Location to be decided in consultation with the Authority Engineer
NIL
11. HAZARDUOS LOCATIONS
Concrete crash barrier shall be installed along both the edges of the flyover and the underpass
approaches and structures.
Traffic impact attenuators shall be provided at the following locations:
Sl.
Junction No. of locations Remarks
No
1 9+540 2 At all points of divergence.
2 10+675 2 At all points of divergence
3 11+475 1 At all points of divergence
4 13+200 1 At all points of divergence
5 13+600 6 At all points of divergence
6 14+000 2 At all points of divergence
7 14+430 2 At all points of divergence
8 14+855 6 At all points of divergence
9 15+195 1 At all points of divergence
10 16+540 4 At all points of divergence
11 17+085 2 At all points of divergence
12 17+487 4 At all points of divergence
13 18+360 2 At all points of divergence
14 19+200 2 At all points of divergence
12.1 RE Wall along main carriageway shall be provided at the following locations:
Average Height
S. No. Chainage Length(m) Side from Ground Remarks
Level
Km 10+260 to 5.0m (Varying
1 400m Both
10+660 from 1m to 8 m)
km 19+010 to 2.0m (Varying
2 200m Both
19+210 from 1m to 4 m)
12.2 RE Wall along service road shall be provided at the following locations:
Average Height
S.No. Chainage Length(m) Side from Ground Remarks
Level
13+145 to 2.0m (Varying
1 200m both
13+345 from 1m to 4 m)
13+855 to 2.0m (Varying
2 200m both from 1m to 4 m)
14+055
14+400 to 2.0m (Varying
3 200m both from 1m to 4 m)
14+600
4 15+450 to 200m both 2.0m (Varying
Construction of Dwarka Expressway between Design Chainage
km 9+500 to 19+700 (Package-3) in the State of Haryana Page 26 of 45
National Highways Authority of India Volume II: Schedules & Annexure
Average Height
S.No. Chainage Length(m) Side from Ground Remarks
Level
15+650 from 1m to 4 m)
16+090 to 2.0m (Varying
5 200m both from 1m to 4 m)
16+290
16+790 to 2.0m (Varying
6 200m both from 1m to 4 m)
16+990
17+050 to 2.0m (Varying
7 200m both from 1m to 4 m)
17+250
17+750 to 2.0m (Varying
8 200m both from 1m to 4 m)
17+950
18+310 to 2.0m (Varying
9 200m both from 1m to 4 m)
18+510
19+010 to 2.0m (Varying
10 200m both from 1m to 4 m)
19+210
Chainage of Road specified in the Schedule is tentative and approximate. The length of structures
and bridges specified hereinabove shall be treated as an approximate assessment. The actual
length of Approaches to structure, length of ramp, slip road, service road, RE Wall, Retaining
wall and length of drains as required on the basis of detailed investigations shall be determined by
the Contractor in accordance with the Specifications and Standards. Any variations in the lengths
specified in this Schedule B shall not constitute a Change of Scope, save and except any
variations in the length arising out of a Change of Scope expressly undertaken in accordance with
the provisions of Article 13.
TCS - 2 TYPICAL CROSS SECTION OF ELEVATED DWARKA EXPRESSWAY WITH AT-GRADE SERVICE ROAD
NOT FOR CONSTRUCTION NATIONAL HIGHWAYS AUTHORITY OF identified on the cover sheet for the purpose for which it has been prepared and AECOM undertakes no
duty to or accepts any responsibility to any third party who may rely upon this document.
ALIGNMENT PLAN & CONCEPTUAL DESIGN OF
REV DATE DESCRIPTION OF REVISION INDIA (NHAI) All rights reserved. No section or element of this document may be removed from this document,
reproduced, electronically stored or transmitted in any form without the written permission of AECOM. INTERCHANGES - DWARKA EXPRESSWAY RB BS MSR MSR
TCS - 3 TYPICAL CROSS SECTION OF DWARKA EXPRESSWAY ON RAMP WITH AT-GRADE SERVICE ROAD
TCS - 4 (TYPICAL CROSS SECTION OF ELEVATED DWARKA EXPRESSWAY WITH SERVICE ROAD ON RAMP AND AT-GRADE
NOT FOR CONSTRUCTION NATIONAL HIGHWAYS AUTHORITY OF identified on the cover sheet for the purpose for which it has been prepared and AECOM undertakes no
duty to or accepts any responsibility to any third party who may rely upon this document.
ALIGNMENT PLAN & CONCEPTUAL DESIGN OF
REV DATE DESCRIPTION OF REVISION INDIA (NHAI) All rights reserved. No section or element of this document may be removed from this document,
reproduced, electronically stored or transmitted in any form without the written permission of AECOM. INTERCHANGES - DWARKA EXPRESSWAY RB BS MSR MSR
90000
EXISTING ROW
KERB SHYNESS
7750 2000 2000 11500 5000 15500 500 1500 500 15500 5000 11500 2000 2000 7750
UTILITY CORRIDOR CYCLE SERVICE ROAD SEPARATOR CARRIAGEWAY MEDIAN CARRIAGEWAY SEPARATOR SERVICE ROAD CYCLE UTILITY CORRIDOR
CUM DRAIN
CUM DRAIN
FOOTPATH
FOOTPATH
TRACK TRACK
TCS - 5 (TYPICAL CROSS SECTION OF AT-GRADE DWARKA EXPRESSWAY WITH AT-GRADE SERVICE ROAD)
NOT FOR CONSTRUCTION NATIONAL HIGHWAYS AUTHORITY OF identified on the cover sheet for the purpose for which it has been prepared and AECOM undertakes no
duty to or accepts any responsibility to any third party who may rely upon this document.
ALIGNMENT PLAN & CONCEPTUAL DESIGN OF
REV DATE DESCRIPTION OF REVISION INDIA (NHAI) All rights reserved. No section or element of this document may be removed from this document,
reproduced, electronically stored or transmitted in any form without the written permission of AECOM. INTERCHANGES - DWARKA EXPRESSWAY RB BS MSR MSR
TYPICAL CROSS SECTION SCHEDULE
NOT FOR CONSTRUCTION NATIONAL HIGHWAYS AUTHORITY OF identified on the cover sheet for the purpose for which it has been prepared and AECOM undertakes no
duty to or accepts any responsibility to any third party who may rely upon this document.
ALIGNMENT PLAN & CONCEPTUAL DESIGN OF
REV DATE DESCRIPTION OF REVISION INDIA (NHAI) All rights reserved. No section or element of this document may be removed from this document,
reproduced, electronically stored or transmitted in any form without the written permission of AECOM. INTERCHANGES - DWARKA EXPRESSWAY RB BS MSR MSR
National Highways Authority of India Volume II: Schedules & Annexure
SCHEDULE -C
PROJECT FACILITIES
1. PROJECT FACILITIES
The Contractor shall construct the Project Facilities in accordance with the provisions of this
Agreement. Such Project Facilities shall include:
v. Delineators
Delineators for the entire Project Length at the locations as suggested in Manual.
vi. Boundary stones: for the entire Project Highway.
vii. Hectometer / Kilometer stones: for the entire Project Highway.
Construction of Dwarka Expressway between Design Chainage
km 9+500 to 19+700 (Package-3) in the State of Haryana Page 29 of 45
National Highways Authority of India Volume II: Schedules & Annexure
Sl.
Design Chainage Side (LHS/ RHS)
No
1 9+900 Both
2 11+000 LHS
3 11+300 RHS
4 12+100 Both
5 12+700 Both
6 13+000 LHS
7 13+700 RHS
8 14+200 Both
9 14+700 LHS
10 15+100 RHS
11 16+000 Both
12 16+400 LHS
13 16+700 RHS
14 17+300 LHS
15 17+700 RHS
16 18+500 Both
17 18+800 LHS
18 18+900 RHS
Polycarbonate roof sheeting shall be provided for entire length of the ramps of Underpass to entry
of water in the event of rain. The sheeting shall allow sufficient lighting.
Overhead digital speed monitoring device along with closed circuit automatic number plate
recognition (ANPR) camera is to be installed at every 1km interval of the project highway
including the service road stretch.
V. Noise Barriers
Noise barriers to be installed both sides of elevated portion of Main Carriageway and also along
the both sides of elevated portion service roads.
VI. Utility Ducts
Utility Ducts of adequate size and capacity to be provided on both sides of the project corridor for
the purpose of ITS and ITMS.
SCHEDULE -D
1. Construction
The Contractor shall comply with the Specifications and Standards set forth in Annex-I of this
Schedule-D for construction of the Project Highway.
2. Design Standards
The Project location including Project Facilities shall conform to design requirements set out in
the following documents:
Manual of specifications & standards for Six Laning of Highway through Public Private
Partnership (IRC SP:87- 2013)
Annex -I
(Schedule-D)
All Materials, works and construction operations shall conform to the Manual of Specifications
and Standards for Six Laning of Highway through Public Private Partnership (IRC SP:87- 2013),
Geometric Design Standards For Urban Roads in Plains (IRC:86-1983), Guidelines for the
Design of Interchanges in Urban area (IRC: 92-1985) and latest MORTH Specifications for Road
and Bridge Works. Where the specification for a work is not given, Good Industry Practice shall
be adopted to the satisfaction of the Authority’s Engineer.
2.1 The terms “Concessionaire”, “Independent Engineer” and “Concession Agreement” used in the
Manual shall be deemed to be substituted by the terms “Contractor”, “Authority’s Engineer” and
“Agreement” respectively.
2.2 Notwithstanding anything to the contrary contained in Paragraph 1 above, the following
Specifications and Standards shall apply to the Project Highway, and for purposes of this
Agreement, the aforesaid Specifications and Standards shall be deemed to be amended to the extent
set forth below:
SCHEDULE - H
1.2 Proportions of the Contract Price for different stages of Construction of the Project Highway
shall be as specified below:
Weightage in
Percentage
Item percentage to the Stage for Payment
weightage
Contract Price
1 2 3 4
A- Widening and
strengthening of existing
road
Weightage in
Percentage
Item percentage to the Stage for Payment
weightage
Contract Price
1 2 3 4
Foundation 14.34%
Sub structure 3.15%
Super Structure 77.97%
Elevated Structure 10+660
63.34% Wearing Course & Expansion
to 19+010 2.46%
joint
Crash Barrier & Railing 1.55%
Reinforced Earth 0.53%
Foundation 21.11%
Sub structure 2.30%
Elevated Structure in Super Structure 69.72%
SERVICE ROAD 13+345 2.52% Wearing Course & Expansion
to 13+855 1.11%
joint
Crash Barrier & Railing 0.54%
Reinforced Earth 5.22%
Foundation 21.29%
Sub structure 2.48%
Elevated Structure in Super Structure 69.87%
SERVICE ROAD 14+600 4.21% Wearing Course & Expansion
to 15+450 1.97%
joint
Crash Barrier & Railing 1.27%
Reinforced Earth 3.12%
Foundation 22.27%
Sub structure 2.42%
Elevated Structure in Super Structure 68.47%
SERVICE ROAD 16+290 2.49% Wearing Course & Expansion
to 16+790 1.06%
joint
Crash Barrier & Railing 0.50%
Reinforced Earth 5.28%
Foundation 22.27%
Sub structure 2.42%
Elevated Structure in Super Structure 68.47%
SERVICE ROAD 17+250 2.49% Wearing Course & Expansion
to 17+750 1.06%
joint
Crash Barrier & Railing 0.50%
Reinforced Earth 5.28%
Foundation 20.07%
Sub structure 2.16%
Elevated Structure in Super Structure 70.93%
SERVICE ROAD 18+510 2.58% Wearing Course & Expansion
1.15%
to 19+035 joint
Weightage in
Percentage
Item percentage to the Stage for Payment
weightage
Contract Price
1 2 3 4
1.3.1 Road works including approaches to minor bridges, Major Bridges and Structures
(excluding service roads).
Procedure for estimating the value of road work done shall be as follows:
Percentage -
Stage of Payment Payment Procedure
weightage
A- Widening and strengthening of existing Unit of measurement is
road linear length. Payment
of each stage shall be
Percentage -
Stage of Payment Payment Procedure
weightage
made on pro rata basis on
completion of a stage in a
length of not less than 25
(twenty) percent of the
(1) Earthwork up to top of the sub-grade 1.29% total length.
3.72%
(2) Granular work (sub-base, base, shoulders)
Percentage -
Stage of Payment Payment Procedure
weightage
0.00%
b) BC
(4) Rigid Pavement
a) DLC 6.47%
b) PQC 26.75%
11.11%
(1) Culverts
@. For example, if the total length of bituminous work to be done is 100 km, the cost per km of
bituminous work shall be determined as follows:
Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)
L = Total length in km
Similarly, the rates per km for stages (1) and (2) shall be worked out.
Procedure for estimating the value of structure work shall be as stated in table below:
Procedure for estimating the value of structure work shall be as stated in table below:
Procedure for estimating the value of structure work shall be as stated in table below:
Procedure for estimating the value of structure work shall be as stated in table below:
Procedure for estimating the value of structure work shall be as stated in table below:
Procedure for estimating the value of structure work shall be as stated in table below:
1.3.8 Underpass
Procedure for estimating the value of structure work shall be as stated in table below:
Percentage -
Stage of Payment Payment Procedure
weightage
Payment shall be made on
pro rata basis on completion
Box Structure 37.27%
of 25 (twenty five) percent of
total Plan Area of Overpass
Percentage -
Stage of Payment Payment Procedure
weightage
Unit of measurement is
linear length in m. Payment
shall be made on pro rata
Retaining Wall 62.73% basis on completion of a
stage in a length of not less
than 10 % (ten per cent) of
the total length
1.3.9 Subway
Procedure for estimating the value of structure work shall be as stated in table below:
Percentage -
Stage of Payment Payment Procedure
weightage
Payment shall be made on
pro rata basis on completion
Box Structure 100.00%
of 25 (twenty five) percent of
total Plan Area of Overpass
Procedure for estimating the value of other works done shall be as stated in table below:
Percentage -
Stage of Payment Payment Procedure
weightage
(iv) Road signs, markings, km stones, Payment shall be made on pro rata basis for
5.15%
safety devices, … completed facilities
Percentage -
Stage of Payment Payment Procedure
weightage
2.2 Payment for Maintenance shall be made in quarterly installments in accordance with the
provisions of Clause 19.7