IMPOUNDING PROJECT
Location : Brgy. Cagawasan, Dagohoy, Bohol
Fund Source : DA-Rice Program 2019
Minimum Equipment : Dumptruck-2, Concrete Mixer-1
Personnel Required : Project Engineer-1, Foreman-1, Laborer-30
Project Duration : 120 Calendar Days
MANPOWER SCHEDULE
MONTHLY DEPLOYMENT
ITEM MANPOWER DESCRIPTION
MONTH 1 MONTH 2 MONTH 3
1 Project Engineer 1 1 1
2 Foreman 1 1 1
3 Skilled Worker 2 2 2
4 Unskilled Worker 28 30 30
TOTAL 32 34 34
SAN SMALL WATER
ENT
MONTH 4
28
32