You are on page 1of 23

Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND

(B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

Equipment Utilization Schedule


Category 1-30 Days 31-60 Days 61-90 Days

Bar Cutter 1
Welding Machine 1 1
Water Truck
Dump Truck 1 1 1
Electric Drill 1 1 1

Prepared by:

Engr. Midelo D. Ocampo


Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND
(B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

Manpower Utilization Schedule


Category 1-30 Days 31-60 Days 61-90 Days

Project Engineer 1 1 1
Foreman 4 4 4
Carpenter 1
Electrician 1
Welder 2 2
Mason 1
Laborer 32 32 32
Painter 8
Steelman 4
Driver 1 1 1

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer

Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND
(B.E.F.F.)- Lot 15
SCHOOLS: CAMBURANAN NHS, CANDELARIA ES
LOCATION: TAPAZ, CAPIZ

Equipment Utilization Schedule


Category 1-30 Days 31-60 Days 61-90 Days

Bar Cutter 1
Welding Machine 1 1
Water Truck
Dump Truck 1 1 1
Electric Drill 1 1 1

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer

Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND
(B.E.F.F.)- Lot 15
SCHOOLS: CAMBURANAN NHS, CANDELARIA ES
LOCATION: TAPAZ, CAPIZ

Manpower Utilization Schedule


Category 1-30 Days 31-60 Days 61-90 Days

Project Engineer 1 1 1
Foreman 4 4 4
Carpenter 1
Electrician 1
Welder 2 2
Mason 1
Laborer 32 32 32
Painter 8
Steelman 4
Driver 1 1 1

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

CONSTRUCTION SCHEDULE AND S-CURVE

TAPULANG ELEMENTARY SCHOOL


ITEM NO. ITEM DESCRIPTION UNIT QUANTITY TOTAL TOTAL w/ DISCOUNT % Wt. 30 Days 60 Days 90 Days
100.00%
General Requirements 0.00% Z
BLDG. A
B Masonry Works lot 1 28,310.17 22,084.88 1.45%
E Roofing Works lot 1 178,753.92 139,446.64 9.15%
F Steel Works lot 1 218,452.63 170,415.76 11.18%
75.00%
G Carpentry Works lot 1 147,980.67 115,440.30 7.57%
H Electrical Works lot 1 29,844.16 23,281.55 1.53%
I Doors and Windows lot 1 186,956.17 145,845.25 9.57%
J Painting Works lot 1 90,532.29 70,624.60 4.63%
BLDG. B
50.00%
B Masonry Works lot 1 17,300.54 13,496.22 0.89%
E Roofing Works lot 1 132,247.35 103,166.68 6.77%
F Steel Works lot 1 146,797.50 114,517.31 7.51%
G Carpentry Works lot 1 104,406.75 81,448.12 5.34%
H Electrical Works lot 1 22,154.99 17,283.20 1.13%
25.00%
I Doors and Windows lot 1 161,689.76 126,134.82 8.27%
J Painting Works lot 1 59,935.04 46,755.56 3.07%

Others 428,626.71 334,373.39 21.94%


TOTAL 1,953,988.65 100.00%
0.00%
TOTAL 1,953,988.65 1,524,314.25 100.00%
PERIOD ACCOMPLISHMENT 20.86% 61.46% 17.67%
SCHEDULE ACCOMPLISHMENT
CUMMULATIVE ACCOMPLISHMENT 20.86% 82.33% 100.00%
PERIOD CASH FLOW 317,998.73 936,912.82 269,402.69
CASH FLOW
COMMULATIVE CASH FLOW 317,998.73 1,254,911.55 1,524,314.25

Prepared by:

Engr. Midelo D. Ocampo


Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

CONSTRUCTION SCHEDULE AND S-CURVE

INDAYAGAN ELEMENTARY SCHOOL


ITEM NO. ITEM DESCRIPTION UNIT QUANTITY TOTAL TOTAL w/ DISCOUNT % Wt. 30 Days 60 Days 90 Days
100.00%

General Requirements lot 1 8,568.78 6,684.54 1.23%


BLDG. A
A Masonry Works lot 1 108,105.18 84,333.28 15.51%
75.00%
B Concreting Works lot 1 37,332.00 29,122.84 5.36%
C Rebar Works lot 1 19,922.95 15,541.97 2.86%
D Doors and Windows lot 1 103,380.70 80,647.69 14.83%
E Steel Works lot 1 10,306.05 8,039.79 1.48%
50.00%
F Roofing Works lot 1 117,949.36 92,012.76 16.92%
G Carpentry Works lot 1 67,607.95 52,741.23 9.70%
H Electrical Works lot 1 24,072.70 18,779.21 3.45%
H Painting Works lot 1 46,871.83 36,564.90 6.72% 25.00%

544,117.50
Others 152,897.36 119,275.83 21.94%
TOTAL 1,953,988.65 0.00%
TOTAL 697,014.86 543,744.04 100.00%
PERIOD ACCOMPLISHMENT 19.01% 59.48% 21.51%
SCHEDULE ACCOMPLISHMENT
CUMMULATIVE ACCOMPLISHMENT 19.01% 78.49% 100.00%
PERIOD CASH FLOW 103,365.74 323,418.96 116,959.34
CASH FLOW
COMMULATIVE CASH FLOW 103,365.74 426,784.70 543,744.04

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

CONSTRUCTION SCHEDULE AND S-CURVE

MAALAN ELEMENTARY SCHOOL


ITEM NO. ITEM DESCRIPTION UNIT QUANTITY TOTAL TOTAL w/ DISCOUNT % Wt. 30 Days 60 Days 90 Days
100.00%
General Requirements lot 1 - - 0.00% Z
BLDG. A
A Masonry Works lot 1 79,163.15 77,594.00 11.36%
75.00%
B Roofing Works lot 1 146,023.85 143,129.40 20.95%
C Steel Works lot 1 161,314.41 158,116.87 23.14%
D Carpentry Works lot 1 102,548.96 100,516.26 14.71%
50.00%
H Electrical Works lot 1 19,124.97 18,745.88 2.74%
E Doors and Windows lot 1 128,415.37 125,869.95 18.42%
F Painting Works lot 1 47,077.67 46,144.51 6.75%
25.00%
683,668.38
Others 13,346.48 13,081.93 1.91%
TOTAL 1,953,988.65
0.00%
TOTAL 697,014.86 683,198.80 100.00%
PERIOD ACCOMPLISHMENT 27.42% 62.44% 10.14%
SCHEDULE ACCOMPLISHMENT
CUMMULATIVE ACCOMPLISHMENT 27.42% 89.86% 100.00%
PERIOD CASH FLOW 187,365.89 426,581.88 69,251.03
CASH FLOW
COMMULATIVE CASH FLOW 187,365.89 613,947.77 683,198.80

Prepared by:

Engr. Midelo D. Ocampo


Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

CONSTRUCTION SCHEDULE AND S-CURVE


BATABAT ELEMENTARY SCHOOL
ITEM NO. ITEM DESCRIPTION UNIT QUANTITY TOTAL TOTAL w/ DISCOUNT % Wt. 30 Days 60 Days 90 Days
100.00%
General Requirements lot 1 8,220.41 6,412.77 0.78%
BLDG. A
A Earthworks lot 1 1,574.16 1,228.01 0.15%
B Concreting Works lot 1 16,079.10 12,543.37 1.53%
C Rebar Works lot 1 13,856.04 10,809.15 1.32%
75.00%
D Formworks lot 1 6,938.92 5,413.08 0.66%
E Roofing Works lot 1 91,791.46 71,606.88 8.75%
F Steel Works lot 1 102,781.11 80,179.95 9.79%
G Carpentry Works lot 1 80,762.64 63,003.25 7.70%
H Electrical Works lot 1 30,707.11 23,954.74 2.93%
50.00%
I Doors and Windows lot 1 118,180.15 92,192.80 11.26%
J Painting Works lot 1 35,018.21 27,317.84 3.34%
BLDG. B
E Roofing Works lot 1 86,798.79 67,712.08 8.27%
F Steel Works lot 1 29,727.84 23,190.81 2.83%
25.00%
G Carpentry Works lot 1 70,969.70 55,363.74 6.76%
H Electrical Works lot 1 19,944.16 15,558.52 1.90%
I Doors and Windows lot 1 79,631.79 62,121.07 7.59%
J Painting Works lot 1 34,521.89 26,930.66 3.29%
Others 222,027.06 173,204.18 21.15%
0.00%
TOTAL 1,049,530.54 818,742.91 100.00%
PERIOD ACCOMPLISHMENT 29.80% 51.70% 18.50%
SCHEDULE ACCOMPLISHMENT
CUMMULATIVE ACCOMPLISHMENT 29.80% 81.50% 100.00%
PERIOD CASH FLOW 243,951.52 423,294.90 151,496.49
CASH FLOW
COMMULATIVE CASH FLOW 243,951.52 667,246.42 818,742.91

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 15
SCHOOLS: CAMBURANAN NHS, CANDELARIA ES
LOCATION: TAPAZ, CAPIZ

CONSTRUCTION SCHEDULE AND S-CURVE

CAMBURANAN NATIONAL HIGH SCHOOL


ITEM NO. ITEM DESCRIPTION UNIT QUANTITY TOTAL TOTAL with DISCOUNT % Wt. 30 Days 60 Days 90 Days
100.00%
General Requirements 29,566.91 23,067.40 1.38%
BLDG. A
B Masonry Works lot 1 27,182.47 21,207.12 1.27%
E Roofing Works lot 1 169,954.18 132,594.22 7.96%
F Steel Works lot 1 231,185.42 180,365.39 10.83%
75.00%
G Carpentry Works lot 1 137,684.36 107,418.07 6.45%
H Electrical Works lot 1 29,035.20 22,652.57 1.36%
I Doors and Windows lot 1 183,413.89 143,095.17 8.59%
J Painting Works lot 1 72,059.78 56,219.33 3.37%
BLDG. B
50.00%
B Masonry Works lot 1 29,847.73 23,286.49 1.40%
E Roofing Works lot 1 156,932.90 122,435.33 7.35%
F Steel Works lot 1 170,251.53 132,826.21 7.97%
G Carpentry Works lot 1 156,932.90 122,435.33 7.35%
H Electrical Works lot 1 27,715.03 21,622.61 1.30%
25.00%
I Doors and Windows lot 1 146,498.62 114,294.75 6.86%
J Painting Works lot 1 104,746.97 81,721.10 4.91%
1,673,007.89
Others 462,215.75 360,609.77 21.65%
TOTAL 1,953,988.65
0.00%
TOTAL 2,135,223.64 1,665,850.88 100.00%

22.55% 59.29% 18.15%


21.45% 78.34% 100.00%
PERIOD CASH FLOW 375,679.23 987,752.78 302,418.88
CASH FLOW
COMMULATIVE CASH FLOW 375,679.23 1,363,432.00 1,665,850.88

Prepared by:

Engr. Midelo D. Ocampo


Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 15
SCHOOLS: CAMBURANAN NHS, CANDELARIA ES
LOCATION: TAPAZ, CAPIZ

CONSTRUCTION SCHEDULE AND S-CURVE

CANDELARIA ELEMENTARY SCHOOL


ITEM NO. ITEM DESCRIPTION UNIT QUANTITY TOTAL TOTAL with DISCOUNT % Wt. 30 Days 60 Days 90 Days
100.00%
General Requirements 14,266.19 11,130.14 0.67%
BLDG. A
B Masonry Works lot 1 31,149.56 24,302.15 1.46%
E Roofing Works lot 1 178,700.60 139,417.97 8.37%
F Steel Works lot 1 224,387.50 175,061.81 10.51%
75.00%
G Carpentry Works lot 1 129,832.96 101,292.60 6.08%
H Electrical Works lot 1 28,427.69 22,178.61 1.33%
I Doors and Windows lot 1 160,856.46 125,496.40 7.53%
J Painting Works lot 1 63,530.86 49,565.27 2.98%
BLDG. B
50.00%
B Masonry Works lot 1 4,987.68 3,891.27 0.23%
E Roofing Works lot 1 62,666.05 48,890.57 2.93%
F Steel Works lot 1 77,811.78 60,706.91 3.64%
G Carpentry Works lot 1 47,260.75 36,871.72 2.21%
H Electrical Works lot 1 10,231.31 7,982.23 0.48%
25.00%
I Doors and Windows lot 1 53,478.36 41,722.55 2.50%
J Painting Works lot 1 29,746.32 23,207.37 1.39%
1,117,334.07
Others 310,739.45 242,431.55 14.55%
TOTAL 1,953,988.65
0.00%
TOTAL 1,428,073.52 1,114,149.12 66.88%

PERIOD ACCOMPLISHMENT 10.85% 35.30% 53.85%


SCHEDULE ACCOMPLISHMENT
CUMMULATIVE ACCOMPLISHMENT 21.45% 78.34% 100.00%
PERIOD CASH FLOW 120,911.91 393,263.82 599,973.38
CASH FLOW
COMMULATIVE CASH FLOW 120,911.91 514,175.74 1,114,149.12

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND
(B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

Equipment Utilization Schedule


Category 1-30 Days 31-60 Days 61-90 Days

Bar Cutter 1
Welding Machine 1 1
Water Truck
Dump Truck 1 1 1
Electric Drill 1 1 1

Prepared by:

Engr. Midelo D. Ocampo


Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND
(B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

Manpower Utilization Schedule


Category 1-30 Days 31-60 Days 61-90 Days

Project Engineer 1 1 1
Foreman 4 4 4
Carpenter 1
Electrician 1
Welder 2 2
Mason 1
Laborer 32 32 32
Painter 8
Steelman 4
Driver 1 1 1

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer
Project Title:
REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 15
SCHOOLS: CAMBURANAN NHS, CANDELARIA ES
LOCATION: TAPAZ, CAPIZ

CAMBURANAN NATIONAL HIGH SCHOOL

PERT/CPM
5 Doors & Windows 6
Electrical Works
Masonry
8
1 Gen. Req.
2

Steel Works Painting


Roofing Carpentry
3 4 7

Prepared by:

Engr. Midelo D. Ocampo


Contractor, Project Engineer
Project Title: REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 15
SCHOOLS: CAMBURANAN NHS, CANDELARIA ES
LOCATION: TAPAZ, CAPIZ

CANDELARIA ELEMENTARY SCHOOL

PERT/CPM
5 Doors & Windows 6
Electrical Works
Masonry
8
1 Gen. Req.
2

Steel Works Painting


Roofing Carpentry
3 4 7

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer
Project Title:
REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

INDAYAGAN PRIMARY SCHOOL

PERT/CPM
5 Doors & Windows 6
Electrical Works
Masonry
Carpentry 8
1 Gen. Req.
2
Concreting
Rebar Works Painting
Steel Works Roofing
3 4 7

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer
Project Title:
REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

MAALAN PRIMARY SCHOOL


PERT/CPM
5 Doors & Windows 6
Electrical Works
Masonry
8
1 Gen. Req.
2

Steel Works Painting


Roofing Carpentry
3 4 7

Prepared by:
Engr. Midelo D. Ocampo
Contractor, Project Engineer
Project Title:
REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

TAPULANG ELEMENTARY SCHOOL


PERT/CPM
5 Doors & Windows 6
Electrical Works
Masonry
8
1 Gen. Req.
2

Steel Works Painting


Roofing Carpentry
3 4 7
Prepared by:

Engr. Midelo D. Ocampo


Contractor, Project Engineer
Project Title:
REPAIR and REHABILITATION OF CLASSROOM under the CY 2017 BASIC EDUCATIONAL FACILITIES FUND (B.E.F.F.)- Lot 3
SCHOOLS: TAPULANG ES, BATABAT ES, INDAYAGAN PS and MAALAN PS
LOCATION: MAAYON, CAPIZ

BATABAT ELEMENTARY SCHOOL

PERT/CPM
5 Doors & Windows 8
Electrical Works
Masonry
Earthworks Concreting Carpentry 9
1 2
Gen. Req. 3 Formworks
Rebar Works Painting
Steel Works Roofing
4 6 7
Prepared by:

Engr. Midelo D. Ocampo


Contractor, Project Engineer