Project: ETAP Page: 1

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Electrical Transient Analyzer Program

Load Flow Analysis

Loading Category (1): Design

Generation Category (1): Design

Load Diversity Factor: None

Swing V-Control Load Total


Number of Buses: 2 0 5 7

Line/Cable/
XFMR2 XFMR3 Reactor Busway Impedance Tie PD Total
Number of Branches: 4 0 0 2 0 1 7

Method of Solution: Adaptive Newton-Raphson Method

Maximum No. of Iteration: 99

Precision of Solution: 0.0001000

System Frequency: 60.00 Hz

Unit System: English

Project Filename: LABOFLUJO

Output Filename: C:\ETAP 1811\LABOFLUJO\LAB SP 05.02.lfr


Project: ETAP Page: 2

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Adjustments

Apply Individual
Tolerance Adjustments /Global Percent

Transformer Impedance: Yes Individual

Reactor Impedance: Yes Individual

Overload Heater Resistance: No

Transmission Line Length: No

Cable / Busway Length: No

Apply Individual
Temperature Correction Adjustments /Global Degree C

Transmission Line Resistance: Yes Individual

Cable / Busway Resistance: Yes Individual


Project: ETAP Page: 3

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Bus Input Data

Load

Bus Initial Voltage Constant kVA Constant Z Constant I Generic

ID kV Sub-sys % Mag. Ang. MW Mvar MW Mvar MW Mvar MW Mvar

Bus1 13.800 1 100.0 0.0

Bus2 4.160 1 100.0 0.0 3.400 2.107 0.850 0.527

Bus3 4.160 1 100.0 0.0 3.400 2.107 0.850 0.527

Bus4 0.480 1 100.0 0.0 2.040 1.264 0.510 0.316

Bus6 0.480 1 100.0 0.0 2.040 1.264 0.510 0.316

Bus7 4.160 1 100.0 0.0

Bus8 4.160 1 100.0 0.0

Total Number of Buses: 7 10.880 6.743 2.720 1.686 0.000 0.000 0.000 0.000

Generation Bus Voltage Generation Mvar Limits

ID kV Type Sub-sys % Mag. Angle MW Mvar % PF Max Min

Bus1 13.800 Swing 1 100.0 0.0

Bus2 4.160 Swing 1 100.0 0.0

0.000 0.000
Project: ETAP Page: 4

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Line/Cable/Busway Input Data

ohms or siemens/1000 ft per Conductor (Cable) or per Phase (Line/Busway)

Line/Cable/Busway Length

ID Library Size Adj. (ft) % Tol. #/Phase T (°C) R X Y

Cable1 5.0MCUS3 750 200.0 0.0 1 75 0.022300 0.036400

Cable3 5.0MCUS3 750 200.0 0.0 1 75 0.022300 0.036400

Line / Cable / Busway resistances are listed at the specified temperatures.


Project: ETAP Page: 5

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

2-Winding Transformer Input Data

Transformer Rating Z Variation % Tap Setting Adjusted Phase Shift

ID Phase MVA Prim. kV Sec. kV % Z1 X1/R1 + 5% - 5% % Tol. Prim. Sec. %Z Type Angle

T1 3-Phase 20.000 13.800 4.160 6.00 17.00 0 0 0 0 0 6.0000 Dyn 0.000


T2 3-Phase 20.000 13.800 4.160 6.00 17.00 0 0 0 0 0 6.0000 Dyn 0.000

T3 3-Phase 5.000 4.160 0.480 5.75 11.41 0 0 0 0 0 5.7500 Dyn 0.000

T5 3-Phase 3.500 4.160 0.480 5.75 11.41 0 0 0 0 0 5.7500 Dyn 0.000


Project: ETAP Page: 6

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Branch Connections

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVA Base


ID Type From Bus To Bus R X Z Y

T1 2W XFMR Bus1 Bus2 1.76 29.95 30.00

T2 2W XFMR Bus1 Bus3 1.76 29.95 30.00

T3 2W XFMR Bus7 Bus4 10.04 114.56 115.00

T5 2W XFMR Bus8 Bus6 14.34 163.66 164.29

Cable1 Cable Bus2 Bus7 2.58 4.21 4.93

Cable3 Cable Bus3 Bus8 2.58 4.21 4.93

CB9 Tie Breakr Bus6 Bus4


Project: ETAP Page: 7

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

LOAD FLOW REPORT

Bus Voltage Generation Load Load Flow XFMR


ID kV % Mag. Ang. MW Mvar MW Mvar ID MW Mvar Amp %PF %Tap

* Bus1 13.800 100.000 0.0 5.720 3.787 0.000 0.000 Bus2 0.000 0.000 0.0 0.0

Bus3 5.720 3.787 287.0 83.4

* Bus2 4.160 100.000 0.0 7.833 5.005 4.250 2.634 Bus7 3.583 2.372 596.3 83.4

Bus1 0.000 0.000 0.0 0.0

Bus3 4.160 98.779 -1.0 0.000 0.000 4.229 2.621 Bus8 1.482 1.025 253.2 82.3

Bus1 -5.712 -3.646 952.0 84.3

Bus4 0.480 96.812 -2.3 0.000 0.000 2.518 1.561 Bus7 -3.559 -2.152 5168.0 85.6

Bus6 1.041 0.592 1488.3 86.9

Bus6 0.480 96.812 -2.3 0.000 0.000 2.518 1.561 Bus8 -1.477 -0.969 2194.1 83.6

Bus4 -1.041 -0.592 1488.3 86.9

Bus7 4.160 99.808 -0.1 0.000 0.000 0.000 0.000 Bus2 -3.578 -2.364 596.3 83.4

Bus4 3.578 2.364 596.3 83.4

Bus8 4.160 98.697 -1.0 0.000 0.000 0.000 0.000 Bus3 -1.481 -1.023 253.2 82.3

Bus6 1.481 1.023 253.2 82.3


* Indicates a voltage regulated bus ( voltage controlled or swing type machine connected to it)
# Indicates a bus with a load mismatch of more than 0.1 MVA
Project: ETAP Page: 8

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Bus Loading Summary Report

Directly Connected Load Total Bus Load

Bus Constant kVA Constant Z Constant I Generic


Percent
ID kV Rated Amp MW Mvar MW Mvar MW Mvar MW Mvar MVA % PF Amp Loading

Bus1 13.800 6.860 83.4 287.0


Bus2 4.160 3.400 2.107 0.850 0.527 9.296 84.3 1290.1
Bus3 4.160 3.400 2.107 0.829 0.514 6.776 84.3 952.0
Bus4 0.480 2.040 1.264 0.478 0.296 4.160 85.6 5168.0
Bus6 0.480 2.040 1.264 0.478 0.296 2.962 85.0 3680.5
Bus7 4.160 4.288 83.4 596.3
Bus8 4.160 1.800 82.3 253.2

* Indicates operating load of a bus exceeds the bus critical limit ( 100.0% of the Continuous Ampere rating).
# Indicates operating load of a bus exceeds the bus marginal limit (95.0% of the Continuous Ampere rating).
Project: ETAP Page: 9

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Branch Loading Summary Report

Transformer
CKT / Branch Busway / Cable & Reactor
Loading (input) Loading (output)
Ampacity Loading Capability
ID Type (Amp) Amp % (MVA) MVA % MVA %

* Cable1 Cable 453.58 596.30 131.47

Cable3 Cable 453.58 253.16 55.81

T1 Transformer 20.000

T2 Transformer 20.000 6.860 34.3 6.776 33.9

T3 Transformer 5.000 4.288 85.8 4.160 83.2

T5 Transformer 3.500 1.800 51.4 1.766 50.5

* Indicates a branch with operating load exceeding the branch capability.


Project: ETAP Page: 10

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Branch Losses Summary Report

Vd
From-To Bus Flow To-From Bus Flow Losses % Bus Voltage
% Drop

Branch ID MW Mvar MW Mvar kW kvar From To in Vmag

T1 0.000 0.000 0.000 0.000 100.0 100.0

T2 5.720 3.787 -5.712 -3.646 8.3 140.9 100.0 98.8 1.22

Cable1 3.583 2.372 -3.578 -2.364 4.8 7.8 100.0 99.8 0.19

Cable3 1.482 1.025 -1.481 -1.023 0.9 1.4 98.8 98.7 0.08

T3 -3.559 -2.152 3.578 2.364 18.5 211.5 96.8 99.8 3.00

T5 -1.477 -0.969 1.481 1.023 4.8 54.5 96.8 98.7 1.88

37.2 416.0
Project: ETAP Page: 11

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

Alert Summary Report

% Alert Settings
Critical Marginal
Loading
Bus 100.0 95.0

Cable / Busway 100.0 95.0

Reactor 100.0 95.0

Line 100.0 95.0

Transformer 100.0 95.0

Panel 100.0 95.0

Protective Device 100.0 95.0

Generator 100.0 95.0

Inverter/Charger 100.0 95.0

Bus Voltage
OverVoltage 105.0 102.0

UnderVoltage 95.0 98.0

Generator Excitation
OverExcited (Q Max.) 100.0 95.0

UnderExcited (Q Min.) 100.0

Critical Report

Device ID Type Condition Rating/Limit Unit Operating % Operating Phase Type

Cable1 Cable Overload 453.581 Amp 596.304 131.5 3-Phase

Marginal Report

Device ID Type Condition Rating/Limit Unit Operating % Operating Phase Type

Bus4 Bus Under Voltage 0.480 kV 0.465 96.8 3-Phase

Bus6 Bus Under Voltage 0.480 kV 0.465 96.8 3-Phase


Project: ETAP Page: 12

Location: 18.1.1E Date: 02-05-2019

Contract: SN: TECSUP02PL

Engineer: Revision: Base


Study Case: LF
Filename: LABOFLUJO Config.: Normal

SUMMARY OF TOTAL GENERATION , LOADING & DEMAND

MW Mvar MVA % PF

Source (Swing Buses): 13.553 8.792 16.155 83.89 Lagging

Source (Non-Swing Buses): 0.000 0.000 0.000

Total Demand: 13.553 8.792 16.155 83.89 Lagging

Total Motor Load: 10.880 6.743 12.800 85.00 Lagging

Total Static Load: 2.635 1.633 3.100 85.00 Lagging

Total Constant I Load: 0.000 0.000 0.000

Total Generic Load: 0.000 0.000 0.000

Apparent Losses: 0.037 0.416

System Mismatch: 0.000 0.000

Number of Iterations: 3