CONSTRUCTION ISSUE REPORT Date: 14-Aug-19

ISSUE ISSUE RAISED


Sr.No. Area ISSUES ACTION PRIORITY ISSUE STATUS ISSUE CLOSED ON HINDRANCE LOCATION PICTURE
OPENED ON BY

AS PER THE LATEST PLOT PLAN THE IMMEDIATE AREA BEHIND THE RO
DM STORAGE PLANT HAS BEEN COMPLETTELY REDESIGNED. THE
RO-DM STORAGE
DRAWING IS ALSO NOT FINALIZED. AS OF NOW, IF WE BEGIN RO-DM
11 RO & DM STORAGE TANK 15-Aug-19 NUBERG NUBERG HIGH OPEN FOUNDATION WORK WILL BE
STORAGE FOUNDATION, IT WILL CUT OFF THE AREA FOR THE
HAMPERED
FOUNDATIONS BEHIND THIS. DRAWING FOR THIS PART NEEDS TO BE
CLEARED IMMEDIATELY

CONSTRUCTION JOINT & PAPER JOINT NEEDS TO BE SHOWN IN THE


FLOOR WALL FOR HCL SYNTHESIS DYKE WALL AS FLOOR WALL FOR CASTING OF HCL SYNTHESIS
10 HCL SYNTHESIS CAUSTIC SODA TANK WHICH IS ITS EXTENSION, IS CARRIED OUT AT A 7-Aug-19 NUBERG NUBERG HIGH OPEN FLOOR WALL ON HOLD TILL
LATER DATE. AFTER MODIFICATION DRAWING TO BE SUBMITTED TO THIS IS CLEARED
CLIENT FOR APPROVAL VIA TRANSMITTAL

UNABLE TO START
9 CHIMNEY CLIENT INSISTS THAT CHIMNEY LOCATION IS NOT FINALIZED/APPROVED 29-Jul-19 SACHLO NUBERG HIGH OPEN
CONSTRUCTION WORK

WORK UNABLE TO START DUE TO CONFINED TANKER ACCESS (NEAR TO


UNABLE TO START
8 HARMONIC FILTER WEIGH BRIDGE , MAIN GATE & NEW WEIGH BRIDGE CONSTRUCTION 1-Aug-19 NUBERG SACHLO/NUBERG LOW OPEN
CONSTRUCTION WORK
WORK)

RO PLANT, DM PLANT, N2PSA, SACHLO FINAL PRODUCT STORED IN THIS AREA - TO BE SHIFTED AND IFC DRAWING ALSO NOT
7 ADU & COMPRESSOR (inside AREA TO BE HANDED OVER BY SACHLO (SACHLO HAS CLEARED THE AREA 29-Jul-19 NUBERG SACHLO MEDIUM OPEN RELEASED TO START.CIVIL
existing storage shed) BY 90%) WORK

AREA READY FOR CONSTRUCTION - NUBERG MANAGEMENT ADVICED


UNABLE TO START
6 COOLING TOWER TO HOLD THIS AREA. THIS AREA TO BE USED FOR STORING THE 1-Aug-19 SACHLO HIGH CLOSED 14-Aug-19
CONSTRUCTION WORK
MATERIAL DURING ERECTION OF HCL BUILDING

Page 1 of 2
CONSTRUCTION ISSUE REPORT Date: 14-Aug-19

ISSUE ISSUE RAISED


Sr.No. Area ISSUES ACTION PRIORITY ISSUE STATUS ISSUE CLOSED ON HINDRANCE LOCATION PICTURE
OPENED ON BY

FLAKING STORAGE SHED


EXISTING RO PLANT SHED & SUMP PIT FALLS ON 60 % OF CCU BUILDING SINCE CANNOT BE STARTED SINCE
5 CCU BUILDING FOUNDATION - HENCE CIVIL WORK CANNOT START UNTIL RO PLANT IS EXECUTION - NUBERG HIGH OPEN THE FOUNDATION IS
SHIFTED TO NEW LOCATION START COMBINED WITH NEW CCU
BUILDING

SINCE
- EXISTING EQUIPMENT TO BE SHIFTED TO CHEMICAL DOSING UNABLE TO START
4 POLISH FILTER EXECUTION - NUBERG HIGH OPEN
- EXISTING STEEL STRUCTURE TO BE DISMANTLED CONSTRUCTION WORK
START

SINCE
- EXISTING EQUIPMENT TO BE SHIFTED TO CHEMICAL DOSING UNABLE TO START
3 ANTHRACITE FILTER EXECUTION - NUBERG HIGH OPEN
- EXISTING STEEL STRUCTURE TO BE DISMANTLED CONSTRUCTION WORK
START

SINCE ANOLYTE & CATHOLYTE


- EXISTING TANK TO BE SHIFTED TO NEW CAUSTIC INTERMEDIATE TANK
2 ANOLYTE & CATHOLYTE EXECUTION - NUBERG HIGH OPEN CONSTRUCTION WORK
FOUNDATION
START DELAYED

FLAKING STORAGE SHED UNABLE TO START


1 DRAWING NOT RELEASED FOR CONSTRUCTION 29-Jul-19 NUBERG NUBERG HIGH OPEN AREA IS OPEN
(9642) CONSTRUCTION WORK