PERENCANAAN PENGENDALIAN PROYEK

FAKULTAS TEKNIK JURUSAN SIPIL


UNIVERSITAS MUHAMMADIYAH PALEMBANG

I. Work Breakdown Structure


1. Pekerjaan Sloof Beton 15/ 20

d.10
Sk.6

 Perhitungan Besi Beton


4 bh x 1,00 x d.10 (0,616 kg/m’) = 2,464 kg/m’

 Perhitungan Sengkang
100
(12,5 = 8 bh)
8 bh x 0,6 x d.6 (0,222) = 1,065 kg/m’ sloof
3,529 kg/m’ sloof

3,529/ 0,15 x 0,20


3,529/ 0,03 = 117,63 m3 beton
117,63 m3 beton + 10 % waste
117,63 + 11,763 = 129,393 kg/m3 beton
= 129 kg/m3 beton

 Perhitungan M3 beton bertulang (sloof)


1. Beton = Rp. 4.000.000
2. Besi = Rp. 2.000.000 x 1,29
= Rp. 2.580.000
= Rp. 6.580.000

2. Pekerjaan Balok Beton 12/ 20

d.10
Sk.6

 Perhitungan Besi Beton


4 bh x 1,00 x d.10 (0,616 kg/m’) = 2,464 kg/m’

 Perhitungan Sengkang
100
(12,5 = 8 bh)
8 bh x 0,54 x d.6 (0,222) = 0,959 kg/m’ balok
3,423 kg/m’ balok
PERENCANAAN PENGENDALIAN PROYEK
FAKULTAS TEKNIK JURUSAN SIPIL
UNIVERSITAS MUHAMMADIYAH PALEMBANG

3,423/ 0,12 x 0,20


3,423/ 0,024 = 142,625 m3 beton
142,625 m3 beton + 10 % waste
142,625 + 14,262 = 156,887 kg/m3 beton
= 157 kg/m3 beton

 Perhitungan M3 beton bertulang (balok)


1. Beton = Rp. 4.000.000
2. Besi = Rp. 2.000.000 x 1,57
= Rp. 3.140.000
= Rp. 7.140.000

3. Pekerjaan Kolom Beton 12/ 12

d.10
Sk.6

 Perhitungan Besi Beton


4 bh x 1,00 x d.10 (0,616 kg/m’) = 2,464 kg/m’

 Perhitungan Sengkang
100
(12,5 = 8 bh)
8 bh x 0,38 x d.6 (0,222) = 0,675 kg/m’ kolom
3,139 kg/m’ kolom

3,139/ 0,12 x 0,12


3,139/ 0,0144 = 217,986 m3 beton
3
217,986 m beton + 10 % waste
217,986 + 21,7986 = 239,784 kg/m3 beton
= 240 kg/m3 beton

 Perhitungan M3 beton bertulang (kolom)


1. Beton = Rp. 4.000.000
2. Besi = Rp. 2.000.000 x 2,40
= Rp. 4.800.000
= Rp. 8.800.000