Professional Documents
Culture Documents
Certificate of Industrial Training
Certificate of Industrial Training
Particulars of Supervisor:
Name:
Organization:
Designation: Contact Number:
Signature of Supervisor:
Office seal:
Date:
INTERNSHIP
a) SUB STRUCTURE:
It consists of foundations, pier, abutments, wing walls and approaches of a bridge. They
all support the super structure.
b) SUPER STRUCTURE:
It consists of trusses, girder, arches, decking, and railing etc.
CLASSIFICATION OF BRIDGES:
1) Length of span.
a) Minor bridges:
Bridges having total water way of less than 60 lineal feet.
b) Major bridges:
Bridges having total water 60 lineal feet or more.
c) Important bridges:
Bridges with maximum water way 600 lineal feet or more.
2) Angle of crossing.
a) Square bridges.
b) Skew bridges.
3) Material of construction.
a) Wooden bridges.
b) Masonry bridges.
c) Steel bridges.
d) Concrete bridges.
7) Intended life.
a) Permanent bridges.
b) Temporary
1) Foundation:
- It is the lower most part of a structure on which the structure rests.
- Foundation is provide to:
Distribute the load over larger area of supporting soil.
To transmit load on the underlying soil at uniform rate.
To increases stability of structure against overturning.
To provide level surface for the construction of structure.
Foundation design is based on the concept of bearing capacity of soil. The load or
pressure developed under the foundation should be well within the bearing capacity of soil.
a) Stresses in any part of foundation must not be exceed bearing capacity of soil under any
combination of load.
b) Axis of load must pass through center of area of foundation and must not be eccentric
beyond permissible limit of 1/6th of width of foundation.
1) Open foundation.
2) Raft foundation.
3) Grillage foundations.
4) Well foundation.
5) Pile foundation.
Experience gained during the 3 months
1) Site inspection.
2) Usage of level machine/theodolite
3) Determining the locations for provision culverts.
4) Understanding of bridge estimate.
5) Learn the layouts protection walls.
6) Understand of the bridge detailed architecture drawings.
7) Understand about the construction materials.
8) Understand about the bar bending schedule.
9) Understand about the detail and technical inspection of major and minor bridges.
10) Testing of steel girder bridges (Old and newly constructed).
11) Painting and scraping of steel structure.
12) Pre-stress and pre-cast concrete bridges.
Certificate of Industrial Training
For the fulfillment of Bachelor of Technology Degree
Particulars of Trainee:
Student’s Name: MUHAMMAD GHIYAS UDDIN
Particulars of Supervisor:
Name:
Organization:
Designation: Contact Number:
Signature of Supervisor:
Office seal:
Date:
INTERNSHIP
This certificate is awarded to Mr. Muhammad Ghiyas Uddin S/O Mashahoor khan
student of sarhad university of information and technology (Reg no: SUIT-12-
01-079-0199) in token of having successfully completed 03-Months
apprenticeship/field training with effect from January-15-2015 to April-25-2015.
During the period of apprenticeship/field training, we found him full time
Devoted, dynamic & learning with interest.
The word building is both a noun and a verb: the structure itself and the act of
making it. As a noun, a building is a structure that has a roof and walls and stands more or
less permanently in one place.
The definition of low - rise vs. a high-rise building is a matter of debate ,but
generally three storey’s or less is considered low –rise.
There are many type of buildings which are uses for different purposes e.g.
Residential building commercial building, educational building, industrial building ,military
building etc.
CLASSIFICATION OF BUILDINGS:
Building may either be single story or multi storey. Further they can be classified
according to their uses, some mentioned as following:
1. Residential
2. Commercial
3. Office buildings
4. Municipal building
5. Military building
Construction of building:
Orientation is a very important factor in the construction of a building. it means observing
the site and the direction of sunrise and sunset, direction of wind and determining the geodic
directions(north,south,east and west),these factors are involved in the construction of building for
making it more comfortable inside.
1) Foundation:
It is the underground structure Sub Structure of the building that distributes the
whole load of the building equally and then transmit that load to the solid ground
safely.Foundation proves to be the base of the building to support it all the external loads.
Foundation may either be shallow Breadth> 2Height or Deep(Breadth <2Heihgt). There
may be, RCC, stone or steel foundations.
2) Basement:
It is that part of building that is under the natural ground surface and used by the
Humans for different activities they may be storage or living purposes.
In single storey building there is only on roof over the ground level. In multi storey
building there are more than one roof over the ground. The most lower on the ground is
termed then 1st floor, 2nd floor, 3rd floor and so on, till top floor.
Beam and columns are the engineered structures that are built to support the live
and dead loads of the building of the distributing and transmitting them safely to the
foundation. Beams and columns are mostly constructed of R.C.C. They may also be
constructed from steel girders, stones are available materials recognized in engineering.
5) Walls:
2) According to the functions of materials, they can be divided into structural materials and
functional materials.
Structural Materials: mainly used as load-bearing members, such as the materials used for
beams, plates and columns.
Functional Materials: mainly possessing some special functions in construction, such as
waterproof, ornamental and heat-insulating functions etc..
MORTAR:
The paste prepared by the mixing of binding material, fine aggregate, course
aggregate and water in a suitable ratio is called mortar.
CONCRETE:
The artificial stone form from hardening a mixture of binding material, fine
aggregate, course aggregate and water in a suitable ratio.
It should be durable.
It should have good crushing strength.
The concrete should have minimum creep.
It should have good workability.
The concrete should be economical.
It should be sufficiently compacted having minimum voids.
It should be hard and provide resistance to the load.
It should be impermeable and will be resist the passage of water.
The concrete should be providing the required finish.
Slump Test:
The slump test is done for the following purposes.
i) The slump test is done to check the workability of concrete.
ii) To control the water cement ratio of concrete.
APPARATUS:
Procedure:
Take simple of concrete and fill the cone up to 3” and temped 25 times
through rod. The whole cone is filled by the applying of above method. After
filling the cone the concrete is leveled with the top of cone. After 5 to 7
seconds remove the cone slowly in vertical direction. Now immediately
measure the height of concrete after removing the cone give name H1. Also
note the height of cone H2. Now calculate the difference by subtracting H1
from H2.
This is required value of slump. This value range according to the following
requirement.
1) Cement:
i) The compressive strength should be not less than 2800psi.
ii) Initial setting time should be not less than 45minutes.
iii) Final setting time should be not less than 10 hours.
iv) The color of cement should be uniform, it should be grey.
v) When cement is touched or rubbed in between fingers, it should give a
smooth feeling.
vi) If a small quantity of cement is thrown in water, it should sink and not
float on the surface.
2) Sand:
i) It should be clean and free of silt and clay.
ii) All sand should be passed through sleve#4.
iii) It should be strong and durable.
iv) It should be free from salt.
v) No organic matter should be present.
vi) It should be chemically inert. (Non reactive).
vii) It should consist of course, angular, sharp and hard grain.
3) Course aggregate:
i) It should be chemically non reactive.
ii) It should be clean and free from salt.
iii) It must be angular in shape.
iv) It must be hard and durable.
v) It should be free from organic matter.
vi) It should not consist of elongated particle.
4) Water:
i) The water should be fresh.
ii) It should not contain any organic and inorganic substance.
iii) The water should be fit for drinking.
iv) It should have no color.
Experience gained in the 3 months
1) Understanding survey
2) Understanding the use of level Machines in a more reliable manner.
3) Gained knowledge on managing of site.
4) Understanding of site plan.
5) Recording the activities of labors and masons.
6) Reporting to the site engineer.
7) Progress and completion of on job on time.
8) Understanding of building estimates.
9) Learn the building layout.
10) Using Auto and CAD for civil Engineering purposes.
11) Draw cross sections, plans and elevations.
12) Understanding the orientation of a building to be determined.
13) Enhancing the ability to architecturally design a building in congested and less area.
Certificate of Industrial Training
For the fulfillment of Bachelor of Technology Degree
Particulars of Trainee:
Student’s Name: MUHAMMAD GHIYAS UDDIN
Particulars of Supervisor:
Name:
Organization:
Designation: Contact Number:
Signature of Supervisor:
Office seal:
Date:
INTERNSHIP
WATER QUALITY
Sources of water for buildings include public water supplies, groundwater, and surface
water. Each source requires careful study to determine if a sufficient quantity of safe water
is available for the building being designed.
WATER TREATMENT
To maintain water quality within acceptable limits (Art. 14.3), water supplied to a building
usually must undergo some form of treatment. Whether treatment should be at the source
or after transmission to the point of consumption is usually a question of economics,
involving hydraulic features, pumping energies and costs, and possible effects of raw water
on transmission mains. Treatment, in addition to disinfection, should be provided for all
water used for domestic purposes that does not fall within prescribed limits. Treatment
methods include screening, plain settling, coagulation and sedimentation, filtration,
disinfection, softening, and aeration. When treatment of the water supply for a building is
necessary, the method that will take the objectionable elements out of the raw water in the
simplest, least expensive manner should be selected. Softening of water is a process that
must be justified by its need, depending on use of the water. With a hardness in excess of
about 150 ppm, the cost of softening will be offset partly by the reduction of soap required
for cleaning. When synthetic detergents are used instead of soap
WASTEWATER PIPING
Human, natural, and industrial wastes resulting from building occupancy and use must be
disposed of in a safe, quick manner if occupant health and comfort are to be safeguarded.
Design of an adequate plumbing system requires careful planning and adherence to the
codes in effect and to state or municipal regulations governing these systems.
WASTEWATER DISPOSAL
There are three main types of wastewater:
Separate plumbing systems are generally required for each type.
1) Domestic.
Domestic wastewater is primarily spent water from the building water supply, to which
is added wastes from bathrooms, kitchens, and laundries. It generally can be disposed of
by discharge into a municipal sanitary sewer, if one is available.
2) Storm.
Storm water is primarily the water that runs off the roof or the site of the building. The
water usually is directed to roof drains or gutters. These then feed the water to
drainpipes, which convey it to a municipal or private storm-water sewer system. Special
conditions at some building sites, such as large paved areas or steep slopes, may require
the capture of storm water in retention areas or ponds to prevent the municipal storm
sewer systems from being overloaded.
3) Industrial.
Industrial waste may present special problems because (1) the flow volume may be
beyond the public sewer capacity, and (2) local regulations may prohibit the discharge
of industrial waste into public sewers
.
SEWERS
A sewer is a conduit for water carriage of wastes. For the purpose of this section, any
piping for wastewater inside a building will be considered plumbing or process piping;
outside the building, wastewater lines are called sewers. Sewers carry wastewater. And
a system of sewers and appurtenances is sewerage. Sanitary sewers carry domestic
wastes or industrial wastes. Where buildings are located on large sites, or structures
with large roof areas are involved, a storm sewer is used for fast disposal of rain and is
laid out to drain inlets located for best collection of runoff.
Determination of Runoff
For figuring rates of runoff to determine storm-sewer requirements, the so-called
rational method may be used. It employs the formula
Q _ CIA (14.5)
Where Q _ maximum rate of runoff, ft3/s
C _ runoff coefficient of the runoff area
I _ rainfall intensity, in/hr
A _ watershed area, acres
The runoff coefficient C indicates the degree of imperviousness of the land. It ranges from
0.6 to 0.9 for built-up areas and paved surfaces and from 0.30 to 0.50 for unpaved
surfaces, depending on the surface slope. In storm-sewer design, however, it is necessary
to know not only rate of runoff and total runoff, but also at what point in time after the
start of a storm the rate of runoff reaches its peak. It is this peak runoff for which pipe
must be sized and sloped. (The conduit designed to handle the peak runoff is for
conveyance of runoff volume only and should not be considered for storage.)
The following list constitutes basic design criteria that must be considered during the
design of gravity sanitary sewer lines within the Boxelder Sanitation District (District).
These are general criteria and may be altered in view of site specific conditions.
Planning Considerations:
1. Coordination:
It is desirable that the planners and engineers communicate with the District staff to field
verify the locations of existing manholes and lines, and also to discuss infrastructure
contemplated for installation in the proposed subdivision.
2. Planning:
It is advisable that the engineers meet with the District staff for a pre-design meeting and
review of conceptual plans for the site, as well as off-site collector line locations.
Flows, Populations:
1. Residential Per Capita Flows: A domestic wastewater flow rate of 100 gal/capita/day
(CDPHE Policy 96-1), and a residential population of 2.5 persons/dwelling unit (Larimer
county information) shall be used for sizing sanitary sewer lines.
2. Commercial Flows: The development engineer must consult with the District during the
design process to identify anticipated flows from commercial developments.
3. Peaking Factors: Peaking factors used for computed wastewater flow shall be in
accordance with ASCE MOP 60 (1982) or Wastewater Engineering (Metcalf and Eddy) or
other generally accepted engineering references.
Easements:
1. Permanent Easements: Permanent easement width of 30 ft. is required for all lines.
Exceptions are possible but must be approved by the District.
2. Access along Easements: All easements not within roadways must have a 12-ft wide
gravel access roadway installed for District maintenance vehicle access. The access road
should be level and be capable of supporting and accommodating a cleaning vehicle with an
18,000 lb axle weight. Security: All easements not within roadways must have gates
installed at all access points. Temporary Construction Easement (TCE): TCEs of at least 50
ft. are advisable for constructability. Location of TCE relative to the permanent easement to
be determined based on site conditions. TCEs of up to 100 ft. may be needed depending on
conditions. District standard templates are to be used for all easement document
preparation.
Sewer Line
1. Alignment: Sewer lines, between manholes, must be straight. Curved sewer lines will not
be accepted by the District.
2. Slope: Minimum slope in accordance with that recommended in Ten States Standards.
3. Flow Velocity: Minimum average velocity of flow in pipe shall be 2 ft/s.
4. Sewer Line Size: Minimum size of sanitary sewer line main is 8 in.
5. D/d Ratio for Design: In accordance with ASCE MOP 60 (1982), pipes up to 15 in.
diameter should be designed as flowing half full (d/D = 0.5) at peak design flow. Pipes of a
larger size should be designed as flowing ¾ full (d/D = 0.75) at peak design flow.
6. Cover: Lines should have a minimum cover of 3.5 ft. (BSD standards/specs.)
7. Line Location in Easements: Sewer lines should be centered within the easement(s).
Manholes:
1. Separation: Manholes must be no more than 400 ft. apart, except in some special cases.
This is due to limitations of the sewer line cleaning equipment.
2. Manhole Location: The sanitary sewer manholes shall, when possible, be located in the
middle of the street, preferably at the crown or reasonably close to it. Under no
circumstances shall the sanitary sewer manholes be sited in areas where stormwater may
flow into the manhole. Similarly, sides/banks of water courses are areas where location of
manholes should be avoided.
3. Minimizing Manholes: Whenever possible, the number of sanitary sewer manholes must
be kept to a minimum.
4. Terminal Manholes: Manholes at the end of lines must be designed with the potential to
serve adjacent properties which are currently not served by sanitary sewer.
5. Rim Elevations: Manhole covers must be at grade.
Service Lines:
1. Disconnect Valves: The District requires the use of service disconnection valves (e.g.,
Elder Valves™) to be placed in the service lines.
2. Cleanout: The District requires a cleanout be installed immediately downstream of each
Elder Valve.
3. Connections to Manholes: Service connections to manholes should be avoided. If,
however, that is not possible, such as in cul de sacs, service connections may be
established through manholes, but with the use of A-LOK gaskets cast in place.
4. Tracer Wire: Tracer wires are required to run along the service line to clean out location.
1. Depth:
Top of sewer line should, preferably, be at least 1.5 ft. below the bottom of water
lines at any crossing.
General Aspects:
1. The gravity sanitary sewer lines shall be constructed in accordance with the District’s
Construction Standards and Specifications
Experience gained in the 3 months
1) Understanding survey
2) Understanding the use of level Machines in a more reliable manner.
3) Gained knowledge on managing of site.
4) Understanding of site plan.
5) Recording the activities of labors and masons.
6) Reporting to the site engineer.
7) Progress and completion of on job on time.
8) Understanding of sewer line estimates.
9) Learn the sewer line layout.
10) Using Auto CAD for civil Engineering purposes.
11) Draw cross sections, plans and elevations sewer line, man hole and other.
12) Understanding how to provide gradient in sewer line.
Certificate of Industrial Training
For the fulfillment of Bachelor of Technology Degree
Particulars of Trainee:
Student’s Name: MUHAMMAD GHIYAS UDDIN
Particulars of Supervisor:
Name:
Organization:
Designation: Contact Number:
Signature of Supervisor:
Office seal:
Date:
INTERNSHIP
Switch control
Ballast
• Provides a hard and level bed for the sleepers
• hold the sleepers in place during the passage of train,
• transmit and distribute the load from the sleepers to
the formation,
• allows for maintaining correct track levels without
disturbing the rail road bed,
• Protect the surface of formation,
• Drain the water immediately, and
• keep the sleepers in dry condition and discourage the
growth of vegetation
Ballast
Ballast material selection
• The ballast material should be elastic and should
be provided in enough thickness such that to
uniformly distribute the weight of train on the
formation
• The material should have sufficient grip over the
sleepers to prevent their horizontal movement
• The material should not allow rain water to
accumulate but it should drain off water without
absorbing the moisture
Ballast
• Broken stone
• Gravel
• Ashes
• Sand
• Kankar
• Moorum
• Brickbats
• Selected earth
Ballast
• Ballast maximum size is 1.9 to 5.0 cm with some
reasonable proportion of intermediate sizes. It
should be spread up to the top of the sleepers
and not on top of sleepers
• The slope will be 1:1 or 1.5:1
• The depth/thickness of ballast should be 6 inch to
24 inches. The depth is measured from top of sub
grade to bottom of sleepers
• The ballast top should be 0.5 to 1.0 inch below
the rail bottom to allow rain water flow
Ballast
• On curves the ballast quantity will be slightly
more to cover super elevation
• Screening of ballast: The ballast should be
renewed from time to time, because due to
continuous hammering the ballast converted
into the powder form. This powder along with
dust , sand ashes from locomotive form an
impervious layer and prevent the ease flow of
water through ballast
Screening of ballast
• The ballast are constantly press in the
formation. This reduce the quantity of the
ballast and also the elasticity of the railway
track is affected. The ballast is cleaned
regularly by means of screening.