You are on page 1of 1

REPORT No.

LOGO LEAK TESTING REPORT FOR ABOVE


GROUND STORAGE TANK; (PMS)

Project: INTEGRITY ASSESSMENT OF PMS TANK Quality Control Form:


Client: Report
AREAS OF INSPECTION: TANK BOTTOM AND ANNULAR WELD JOINTS Date:
CODE FOR INSPECTION: API653 AND API650 MATERIAL: CARBON STEEL
PROCEDURE:
1. PROPERLY CLEAN AND PREPARE ALL WELDMENTS.
2. APPLY LEAN QUANTITY OF FOAMY LIQUID & SET VACUUM BOX
DIRECTLY ON WELDMENT TO BE TESTED, AND THEN APPLY
COMPRESSED AIR.
TEST PRESSURE; 300BAR (4.4Psi)
3. THE PRESSURE BUILD UP, WILL SEAL THE WELDMENT SURFACE AND
VACUUM BOX DIMENSIONS: 70cm
ALLOW VACUUM OF MAXIMUM OF 300 BAR TO EXIST WITHIN THE
x25cmX8cm
BOX FOR 10 MINS.
4. FINALLY, CAREFULLY AND PATIENTLY OBSERVE INSIDE THE VACUUM
BOX THROUGH THE GLASS FOR ANY CONTINOUS BUBBLE. WHICH
CAN BE INDICATIVE OF A LEAK ALONG ANY WELDMENT UNDER TEST

Area: TANK BOTTOM & ANNULAR


Category: NA Thickness (Average): 9.5mm & 5.5mm
PLATE
Welding process: NOT REQUIRED Material: A283 GRADE C; Size: NOT REQUIRED
State of Examination Prepared edge X As weld After PWHT
X Base Metal Other Repair
Surface Preparation Grinding X Brushing As weld Other
ACCEPTANCE
EQUIPMENT CONSUMABLES LIGHTING IN TANK Temperature
CRITERIA
GAMMATEC FOAMY LIQUID API653 100LUX AMBIENT
TEST RESULT
CML JUDGMENT
Date of
BOTTOM DEFECTS Remarks
ANNULAR PLATE Accept Reject Inspection
PLATE
OK AS OF DATE
TOP SIDE TOP SIDE NIL OK -
OF INSPECTION
INTERNAL & OK AS OF DATE
INTERNAL NIL OK -
EXTERNAL OF INSPECTION

REPORT SUMMARY FOR PMS TANK 31;


NO BUBBLE WAS OBSERVED DURING THE VACUUM BOX TEST. THE TANK BOTTOM STEEL PLATE AND
ANNULAR PLATE WELDMENTS MEET THE ACCEPTABLE CRITERIA OF API653 & API650 AS AT THIS DAY OF

PROJECT REVIEWED BY APPROVED BY CLIENT


SUPERVISORS
1.
API INSPECTOR &
2.
ENGINEER

You might also like