Grade of Steel, Fy = 415 Mpa Width of the Beam, b = 700 mm Overall depth of the Beam, D = 1300 mm Clear Cover to reinforcement = 50 mm Diameter of Bar used (in other direction) = 20 mm 314 Diameter of Bar used (Main reinforcement) = 20 mm 314 Diameter of Stirr up used = 10 mm 79
Provide Top Reinforcement : 7-25T + 2-25T (ALTH.) 2729 mm² Provide Shear Reinforcement : 4L-12T @ 150mm C/C. FOUNDATION BEAM DESIGN : C35 & C36 checked
Grade of Concrete, Fck = 20 Mpa
Grade of Steel, Fy = 415 Mpa Width of the Beam, b = 600 mm Overall depth of the Beam, D = 1300 mm Clear Cover to reinforcement = 50 mm Diameter of Bar used (in other direction) = 20 mm 314 Diameter of Bar used (Main reinforcement) = 20 mm 314 Diameter of Stirr up used = 10 mm 79
Provide Top Reinforcement : 6-25T + 2-25T (ALTH.) 3928 mm² Provide Shear Reinforcement : 4L-12T @ 150mm C/C. FOUNDATION BEAM DESIGN : C57 & C60 checked
Grade of Concrete, Fck = 20 Mpa
Grade of Steel, Fy = 415 Mpa Width of the Beam, b = 900 mm Overall depth of the Beam, D = 1300 mm Clear Cover to reinforcement = 50 mm Diameter of Bar used (in other direction) = 20 mm 314 Diameter of Bar used (Main reinforcement) = 20 mm 314 Diameter of Stirr up used = 10 mm 79
Provide Top Reinforcement : 5-20T + 4-16T (ALTH.) 2374 mm² Provide Shear Reinforcement : 7L-12T @ 150mm C/C. FOUNDATION BEAM DESIGN : C57 & C60 checked
Grade of Concrete, Fck = 20 Mpa
Grade of Steel, Fy = 415 Mpa Width of the Beam, b = 950 mm Overall depth of the Beam, D = 1350 mm Clear Cover to reinforcement = 50 mm Diameter of Bar used (in other direction) = 20 mm 314 Diameter of Bar used (Main reinforcement) = 20 mm 314 Diameter of Stirr up used = 10 mm 79