CLIENT:
VARANASI
DESIGN OF COMPONENT:
ANALYSIS & DESIGN OF RCC DOUBLE BOX(TOP SLAB, WALL & BOTTOM SLAB)
CONSULTANT :
M/S KGS
DHADHA BUZURAG,HATA, KUSHINAGAR-274207(U.P)
KATKA-MADHOSINGH:Box Design calculations for 25T-2008 Loading:
SINGLE BOX 3.06 m x 2.755 m
Materials
Grade of concrete M 30 Select from Dropdown List
Grade of steel Fe 500 Select from Dropdown List
Max aggregate size,mm 20 Select from Dropdown List
Soil Ø, Degrees 30 Enter Value
Soil δ, Degrees 10
Soil density, Kn/m³ 18 Enter Value
Dimensions (Input)
Clear span of box, m 3.060 m
Clear height of box, m 2.755 m
Barrel Length of bridge 7.85 m
Ballast cushion 300 mm
Earth cushion 1929 mm
Clear Cover top 50 mm
Clear Cover side 60 mm
Thickness of wearing coat 150 mm
Dimensions (Output) B G C
Thickness of top & Bottom slab 0.45
Thickness of side walls 0.3
Effective span 3.36
Effective height 3.36
E E'
Overall span of bridge 3.66
Overall height of bridge 3.805
Size of haunch 300
Dispersion width 2.745+Bst cu+le/2 6.65
A F D
25t-2008 Loads
EUDL for bending moment fm table 456.85 KN
EUDL for shear from table 619.18 KN
Derailment Load
For BM 4.92
For Shear 6.67
Earth pressure Ka
Cos 2
Sin Sin
2
Cos 2 Cos 1
Cos Cos
Ka= 0.3085
Ka-rest= 0.5
Active earth pressure Ka rest
At top 13.63 22.086
At Bottom 32.25 52.281
Earth pressure due to live & dead load surcharge Base 3
S, live t/m 137.00
V, dead t/m 43.68
Surcharge pressure
2
At top 18.58 kN/m
2
At Bottom 10.52 kN/m
Earth pressure (with load factors)
At top 23.16 kN/m2
At Bottom 54.83 kN/m2
Earth pressure & Surcharge Pressure (with load factors)
2
At top 54.75 kN/m
At Bottom 72.71 kN/m2
Moment
R/c Rod Case-I Case-II Case-III Design BM
at
Btm U R/c MA -91.35 -93.29 -77.05 -93.29 - 'Ve Tension outside
Top U R/c MB -81.12 -82.38 -66.14 -82.38
Btm I R/c MF 185.22 193.83 103.61 193.83 + 'Ve Tension inside
Top I R/c MG 168.50 177.79 87.57 177.79
Side O R/c ME 0.00 -11.88 0.00 -11.88
Side I R/c ME' 3.43 1.83 18.07 18.07
Reinforcement Calculation
RDSO sym Position Moment Ast Req Dia req spacing Dia pro Ast pro
b Top slab mid span 177.79 1124.56 11.97 100 12 1131
d Bottom slab mid span 193.83 1232.72 12.53 100 12 1131
c Bottom U Rod 93.29 675.00 13.11 200 16 1005
a1 Side outer 11.88 600.00 12.36 200 12 565
a2 Top U-Rod 82.38 675.00 13.11 200 16 1005
e Side inner 18.07 600.00 12.36 200 12 565
h2 Distribution side NA 360.00 8.29 150 10 524
h1 Distribution top/btm NA 540.00 10.16 150 12 754
f1 Top Haunch NA 616.36 12.53 200 12 565
f2 Bottom Haunch NA 616.36 12.53 200 12 565
Total 7040.01 Total 7812