You are on page 1of 1

SCHEDULE OF 15.0M GANTRY FOR 50.0M STRECTH WITHOUT REINFORCEMENT ‐   MONTHLY PROGRESS AS PER THIS SCHEDULE= 291.

89 m
ACTIVITIES DURATION FOR 45.0M OF CONCRETE LINING
S.NO DESCRIPTION
1 Cleaning, Mud Mat &  Setting time plush pump shifing 24.00 Hrs
2 Curb‐Shuttering (15.0m)
Gantry de‐shuttering alignment fixing & bulk  6.0 Hrs 6.0 Hrs 6.0 Hrs
4
heading (9.0m)

5 Concrete Pouring ‐ 9.0m.  (During Concrete pouring of overhead after 
it, the curb will be poured) 15.0 Hrs 15.0 Hrs 15.0 Hrs
6 Pump alignment & Placement of pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
7 Pump cleaning  1.00 Hrs 1.00 Hrs 1.0 Hrs
8 Invert Cleaning
9 Invert Concreting 12.0 Hrs
10 Deberis cleaning for every 3 gantry 9.0 Hrs
Thus, 45.0m (3Nos of gantry) completes in  4.63 Days
NOTE: REQUIREMENT OF MACHINARY
           1. Small TM ‐(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
           2.  Hydraulic Gantry
           3. Vibrators
           4. Welding Machine ‐ 3 Nos (1nos Spair) in proper working condition.
           5. De‐watering Pumps ‐2 Nos (1 Nos Spair) in proper working condition.
           6. 
        : Manpower 
          1.  There should be 5nos of gangs for cleaning, Gnatry Alignmnet, Concrete Pouring . Aprox. total numbers of labours should be 40 to 50 
nos.  ( including cleaning gangs, concreting gangs)
          2. Days shift and Night Shift
          2.1 Foreman / Supervisor ‐2Nos for each shift.
          2.2 Electrician ‐2Nos for each shift.
          3. Surveyor ‐1Nos (Call duty)
          4. Mechanic & helper ‐1 Nos for each shift.
          5. All drivers should be on call duty.
         6. Face‐Incharge ‐ Nos. 
       :HURDLE/OBSTRUCTION
          1.  Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as      mentioned 
above.
          2.    It is assumed that labours shall be paid regularly.