ESSAR BULK TERMINAL LIMITED - HAZIRA

HAZARD IDENTIFICATION AND RISK ASSESSMENT


Type of Harm Risk Assessment
Work Type of Damage /
Sl. No. R / NR Consequence Control Measures in place Injury / ill Probabil
Activity Hazard Loss of
Health ity
property
REV- Bunkering
02
EBTL/H NR Placing the Fire & Personal injury Skilled and experienced personnel are detailed for Y Y 2
AZ- Pump Explosion Watter Bunkering job.
HIRA/0 Hose Oil Pollution The personnel aware of the safety precautions.
09 Connection leakage Fire extinguishers are readily available in the area.
Earthing is
made properly

Good house keeping near bukering area,


All necessary PPE's worn by all personnel engaged
for Bunkering activity.
Emergency preparedness are available in ready to
use condition.
Tool box meeting conducted before start of job.
.
All safety precauitons
ensured to prevent oil leakage.
Necessary permission will be
obtained from the Port Caption/radio room before
bunkering starts.
DATE: 01/09/2012
Risk Assessment Addition
Legal l
Risk
Total Rating Complia Control
severity Code
nce Measure
s
3 6 B Oil SOP
Contigen
cy Plan.