# 4 (RSLF - AC) Project - CQC COORDINATION PRODUCTION MEETING - 12 May 2019 Final Approved by MR PDF
# 4 (RSLF - AC) Project - CQC COORDINATION PRODUCTION MEETING - 12 May 2019 Final Approved by MR PDF
• Project Introduction.
• Health & Safety.
• Construction Program & Progress status.
• Progress photos.
• Quality Control
• Monthly invoice
• Challenges and Actions
Project Introduction
Introduction
Project duration: 01 Dec. 2018 TO 30 Nov 2020 (730 DAYS) (including Mobilization & Design)
© Arcadis 2015
Introduction
Al Yamama is to design and construct the Primary (Base Bid) at the RSLF-AC base as
identified below:
© Arcadis 2015
1. Health & Safety
Health & Safety
© Arcadis 2015
Health & Safety
Safety Toolbox Meeting conducted this week that focuses on safety topics related to
specific job such as,
1. Excavation Safety
2. Electrical Safety
3. Slips/Trips and Fall Hazards
4. Working at Height
5. Portable Power Hand tools
Safety induction conducted this week for the new arrival site personnel.
Total- 01 Person.
Daily inspection is conducted on daily bases for all the plant and equipment.
Two persons attended training course of Rigger -3 and certified by TUV institution.
Their license has been uploaded on RMS.
Four persons are under process of providing First Aid/CPR Training course and they
are waiting for training schedule.
© Arcadis 2015
3. Construction progress & schedule
Construction Program & Progress status.
12th May 2019 As Per BL-00
© Arcadis 2015
Construction Program & Progress status.
12th May 2019 As Per BL-01
© Arcadis 2015
Performance Index
50 60 50 60
40 70 40 70
30 80 30 80
20 90 20 90
10 100 10 100
Performance Index Performance Index
48% 90%
© Arcadis 2015
Actual Progress VS Planned Construction Progress “S: Curve
© Arcadis 2015
Accomplished work during This week
© Arcadis 2015
Accomplished work during This week
© Arcadis 2015
Causes of Delays
• Main Causes: According to the approved baseline, AYC should have had
start soil improvement activities. Because of soil improvement activities
delays, AYC is behind schedule. AYC can't start these activities until the
Fast Track 95% Design Package is approved.
© Arcadis 2015
Share of Delays
= -3.793%
© Arcadis 2015
Work suspensions during This week
© Arcadis 2015
3.1 Photos presentation
SITE LABORATORY BLOCK WORK WORKERS TOILET PLUMBING INSTALLATION
© Arcadis 2015
FENCE POST INSTALLATION CLIENT OFFICE
© Arcadis 2015
ELECTRICAL CABLE TERMINATION MOSQUE ELECTRICAL GROUNDNG CABLE
© Arcadis 2015
CONCRETING FOR GENERATOR PAD-2 CONCRETING FOR CAR PARK FOUNDATION
© Arcadis 2015
PLUMBING WORKS FOR WORKERS TOILET
© Arcadis 2015
4. Quality Control
1. Transmittals Status.
2. Quality Control Tests.
3. Three Phase Inspection.
4. Quality Control Deficiency.
TRANSMITTALS STATUS
Completed Transmittals Draft Transmittals Pending Government Receipt Transmittals in Review
0%
0%
5%
95%
© Arcadis 2015
QUALITY CONTROL TESTS
© Arcadis 2015
THREE PHASE INSPECTION
© Arcadis 2015
QUALITY CONTROL DEFICIENCY
© Arcadis 2015
8. Monthly invoice
Monthly invoice
• On the previous Payment Meeting that was held on 7th May 2019: USACE
asked AYC to assign CLIN for each activity in progress in the same
presented Spreadsheet that shows the actual completion percentage & then
send it to USACE via e-mail for their review.
• AYC & USACE will have Payment Meeting # 2 on 14th May 2019 to discuss
the actual completion percentage.
© Arcadis 2015
Challenges and Actions
Challenges Action by AYC
Overall Progress Delay • AYC & USACE should agree the actual
percentage of the project together in order to
prepare an accurate Updated – Modified -
Project Time schedule and submit it to
USACE as soon as possible.
© Arcadis 2015
Challenges Action by AYC
© Arcadis 2015
Challenges Action requested from USACE
Overall Progress Delay • AYC & USACE should agree the actual
percentage of the project together in order to
prepare an accurate Updated – Modified -
Project Time schedule and submit it to
USACE as soon as possible.
© Arcadis 2015
END