From: A.Thiyagarajan <atr@lntmailorg.

com>
Sent: Saturday, February 21, 2015 4:21 AM
To: Ramesh Vadivelu <vramesh@lntmailorg.com>
Cc: K. Balamurugan <kbmlt@lntmailorg.com>; Bhoothalingam <bhoothalingam@lntmailorg.com>
Subject: VAriation Items

Sir,
Venkatesan CTS spoke to me yesterday and conveyed that Variation items are approved for 62 Cr. (additional 2 Mn $). He asked us
to submit items.
I have prepared the summary as follows. Statutory Approval Cost of 22 Cr needs to be accounted in other Items. Also this
additional 12 Cr. is towards enrichment of interior Items.
 
This needs to be forwarded to CTS before afternoon. Kindly confirm.
Regards
ATR
        1  Main Switch Room - Gas Suppression system 35.35

        2  Modular UPS 202.57

        3  Changes in Switch Room Rack Loads 263.97

        4  ELCOT KITS campus - External road drain cover slab 57.65
(Outside Plot Area)

        5  MLCP - Addl. CCTV cameras 100.00

        6  SDB 2 - Video booths in waiting Lounge area  46.80

        7  SDB-3 Corporate floor 806.71

        8  Battery monitoring system for all building UPS system 60.24

        9  Online monitoring system for WTP 27.00

     10  LPG leak detection system at Gas bank 25.00

     11  OSR Land - Landscape Development 518.57

     12  SDB 3 - Landscape terrace works ( Kiosks, screening wall 750.00


& allied works.)

     13  SDB 2 - Training rooms 28.60

     14  Epoxy flooring - Addl. Requirement  205.33

     15  Delta cost for dining area graphic scheme with respect 145.13
to wall tiles, SDB 1 & SDB2 office area graphics 

3272.92
  Increase in Cost of Granite Cladding - Due to Closure of 445.00
Granite Quarries

     

  Specification Enrichment in Interiors. 2450.00

    6167.92