Detail Estimate
Name of Project :-Timure School
Location:- Rainas-3
S.N. Description of work Nos. length(m) Breadth(m) Height(m) Quantity units Remarks
1 E/W in excavation 13.32 m3
for column footing 2.0 1.829 1.83 1.829 12.24 m3
for beam(9"*9")+wall 1.0 2.870 0.33 1.143 1.08 m3
2 Soling 0.80 m3
soling below footing 2.0 1.524 1.52 0.152 0.70 m3
soling below wall 1.0 2.870 0.33 0.102 0.10 m3
3 PCC 0.52 m3
PCC below footing(1:3:6) 2.0 1.524 1.52 0.102 0.47 m3
pcc below wall 1.0 2.870 0.33 0.051 0.05 m3
4 9" Wall 0.50 m3
Brick wall(1:4) 1.0 2.870 0.23 0.762 0.50 m3
5 PCC for RCC 2.37 m3
pcc for rcc(1:1.5:3)
footing pad 2.0 1.524 1.52 0.356 1.65 m3
column(9*9) 2.0 3.962 0.23 0.229 0.42 m3
beam 2.0 2.870 0.23 0.229 0.30 m3
6 Reinforcement 201.92 kg
for column 8.0 5.814 1.578 73.40 kg
for beam 8.0 3.710 0.888 26.36 kg
reinforcement for footing pad @6" c/c 44.0 1.626 0.888 63.53 kg
stirrups
for beam 46.0 0.893 0.395 16.23 kg
for column 68.0 0.834 0.395 22.40 kg
7 Metal Gate
Metal gate with painting 1.0 5.686 m2
200.000 kg
`
Norms no 5,1 Kha,2 Norms Unit 1.00 CU.M.
Items Description : Brick masonry work including 30 m lead in cement mortar 1:4 with 1
nos chimney brick
Description Quantity Unit Rate Amount
Skilled 1.50 md 1090.00 1635.00
Labour
Unskilled 2.20 md 790.00 1738.00
Brick 560.00 Nos 14.69 8226.40
Materials Cement 0.10 M.T. 19210.00 1921.00
Sand 0.28 Cu.m. 1870.00 523.60
Total 14044.00
Rate per unit 14044.00
Item No :-
Description :- Gabion ( 10 gauge) supply
Unit:- 1 kg
Rate of 1 kg. Gabion (10 gauge) at Bhotewodar 85.00
transportation from bhoteodar to
Nepaldanda by vehicle 0.114 0.11
transportation from Nepaldanda to
site by vehicle 0.15 0.15
Load/Unload 0.24 0.24
13 % VAT 11.05
Total per kg 96.55
Item No :-
Description :- Gabion (12 gauge) supply
Unit:- 1 kg
Rate of 1 kg. Gabion (12 gauge) at Bhotewodar 86.00
transportation from bhoteodar to
Nepaldanda by vehicle 0.114 0.11
transportation from Nepaldanda to
site by vehicle 0.15 0.15
Load/Unload 0.24 0.24
13% VAT 11.18
97.68