BRADAMA INTERNATIONAL

ZAKHEM CONSTRUCTION NIGERIA LIMITED

NNPC
DAILY CONCRETE SADDLE INSTALLATION REPORT
Date: 28/12/2018 Report #: LGPP-ZCNL/QC/DCSR- 01 Section: E, Lekki
PROJECT: Lekki Gas Pipeline Project From 36'' ELP Line at Kp292 Tie-in to Fertilizer Plant At LFTZ
Weather: Rainy Cloudy Sunny Dusty

From Weld KP4 W56 To Weld No. KP4 W82

Total Meter(m) 336.965M Cum. 336.965M


No. Of Concrete Saddle Installed = 18 Cum. Concrete Saddle Installed = 18

Pipe O.D. 36"Ø Wall Thick. (mm) 19.05


Manpower Equipment
Engineer 0 Excavator 1
Safety Officer 1 Wheel Loader 0
Foreman 1 Tipper 0
Operator 3 Side Boom 2
Driver 1 Pick-Up 1
Skilled Labour 1 Truck 0
Labour 3
Security 0
Helper 2

Total 12

REMARK:

ZAKHEM DFL / ZEL NGPTC


NAME: BARRY OKOYO NAME: NAME:

SIGN: SIGN: SIGN:

DATE: DATE: DATE: