Calculation of Carriage Cost as per SPR (2016) Guidelines

Rate of Transportation of Sand based on Mizoram-PWD Schedule of Rates 2016 from Quarry to Project Centre Chainage (Approximate Length is 20 km)

Cost of Carriage Distance Lead = 20 km (Quarry to Project Centre Chainage )


Distance (km) Rate Amount Remarks
a) Cost of Haulage (Unsurfaced Gravelled Road) 20 11.02 220.438
Refer SOR 2016
b) Loading & Unloading 219.00 (Mizoram) Chapter 1
Amount in Rs. per cum 439.44 (Page - 19)

Rate of Transportation of Cement based on Mizoram-PWD Schedule of Rates 2015 from Cement Procurement Area (Aizwal) to Project Centre Chainage (Approximate Length
is 260 km)

Cost of Carriage Distance Lead = 260 km (Cement Procurement Area to Project Centre Chainage )
Distance (km) Rate Amount Remarks
a) Cost of Haulage (Surfaced Road) 200 11.30 2260.000
b) Cost of Haulage (Unsurfaced Gravelled Road) 60 13.29 797.400
Refer SOR 2016
c) Loading & Unloading 376.00 (Mizoram) Chapter 1
Amount in Rs. per MT. 3433.40 (Page - 19)

Rate of Transportation of Aggregate based on Mizoram-PWD Schedule of Rates 2015 from Quarry to Project Centre Chainage (Approximate Length is 20 km)

Cost of Carriage Distance Lead = 20 km (Aggregate Procurement Area to Project Centre Chainage )

Distance (km) Rate Amount Remarks


a) Cost of Haulage (Unsurfaced Gravelled Road) 20 7.82 156.353
Refer SOR 2016
b) Loading & Unloading 219.00 (Mizoram) Chapter 1
Amount in Rs. per cum 375.35 (Page - 19)

Rate of Transportation of Steel based on Mizoram-PWD Schedule of Rates 2015 from Steel Procurement Area (Aizwal) to Project Centre Chainage (Approximate Length is
260 km)
Cost of Carriage Distance Lead = 260 km (Steel Procurement Area to Project Centre Chainage )
Distance (km) Rate Amount Remarks
a) Cost of Haulage (Surfaced Road) 200 11.30 2260.000
b) Cost of Haulage (Unsurfaced Gravelled Road) 60 13.29 797.400
Refer SOR 2016
c) Loading & Unloading 376.00 (Mizoram) Chapter 1
Amount in Rs. per MT. 3433.40 (Page - 19)