Rate Analysis

Based on MSR'2017
Name of work:-Impvt of Ayangpalli road(1.83-3.055km)
Item - 1 7.5 cm thick bituminous built up, spray grout macadam using 0.50 cum of stone aggregate of 25 mm nominal size per 10 sqm of road surface spread
and roller over a tack coat at the rate of 10 kg of bitumen per 10 sqm. for the first coat and 0.50 cum of 25 mm nominal size stone aggrt. per 10 sqm
spread and rolled immediately after spreading hot bitumen at 15 kg per 10 sqm for the 2nd coat and applying a binder coat of 0.13 cum of key stone
aggrt. 12.5 mm nominal size per 10 sqm spread broomed and immediately after spraying of bitumen binder of approved quality at 15 kg per 10 sqm
complete.Using Bitumen (80/100)
p/170 Carriage charge = Rs.716.60 / sqm
Carriage charge
a) Stone metal below 40mm 0.1130 cum x Rs.707.39 /cum = Rs.79.93 / sqm
b) Bitumen 0.004 Mt x 210.634 /Mt = Rs.0.84 / sqm
Rs.797.38 / sqm
Add 12% GST = Rs. 95.69 / sqm
Add 1%Labour Cess = Rs. 7.97 / sqm
Rs. 901.04 / sqm
Item - 2 Providing 25mm thick semi-dense carpeting course aggregate fine aggregate and filler required grading conforming to Table 500.11 of IRC
specification in sufficient to yield specified thickness after compaction including through dressing of surface, screening and cleaning of stone materials
making component including coarse aggregate, fine aggregate and filler to obtain homogeneous mixture with requisite quantity of binder @ 5.50% by
weight to mix, mixing the quantity in hot mix plant conforming to IS 3066 and laying the mixture uniformly to specified grade line and cross section over
the existing surface. 15.28.2 Using Bitumen (80/100)

p/166 = Rs.333.90 / sqm


i/c Preparing surface by brushing with wire brushes for remaining caked mud etc. Sweeping with brooms and
finally fanning the cleared surface with gunny bags to removed all loose dirt etc.b).Black topped surface.

p/166 = Rs.15.80 / sqm

i/c P/A primer evenly a priming/tack coat with bitumen (80/100) 15.14.1. - 5kg/10sqm
p/166 1 x Rs.33.60 /sqm = Rs.33.60 / sqm
Transportation charges (Quarry toMixing yard)
a) Stone metal below 40mm 0.03400 cum/sqm@ Rs.645.17 /cum = Rs.21.94 / sqm
b) Bitumen
i) Carriage charge (Source to W/site)
( 0.5 / 1000 ) MT/sqm x Rs.210.63 = Rs.0.11 / sqm
ii) Carriage charge (Source to mixing yard)
( 316.25 )/ (1000 x100) MT/sqm x Rs.174.13 = Rs.0.55 / sqm
iii) Mixed material from yard to site
= 2.3MT/CUM' 0.0575 x Rs.210.63 = Rs.12.11 / sqm
Rs.418.00 / sqm
Add 12% GST = Rs. 50.16 / sqm
Add 1%Labour Cess = Rs. 4.18 / sqm
Rs. 472.34 / sqm
Section Officer,
Imphal East Divn.,
PWD, Manipur.
Assistant Engineer-II,
Imphal East Divn..
PWD, Manipur