You are on page 1of 5

Part.

Template
MUSE ED Elevator Ctrl. No. MUSE ED-IM-01-0

FOD Page 1/6


Overseas Support Team
Installation Manual Date Mar. 2009

Template

‹ Revision History
Rev. Prepared Checked Approved
Date Revision Contents
No. by by by
30 Mar Harold
0 Release YS Kim DH Kim
2009 Lee
Part. Template
MUSE ED Elevator Ctrl. No. MUSE ED-IM-01-0

FOD Page 2/6


Overseas Support Team
Installation Manual Date Mar. 2009

Index

1. Templates _____________________________________________________________ 3
1.1. Making of entrance template _______________________________________________ 3

1.2. Making of Car and CWT templates _________________________________________ 3

2. Hoistway layout ________________________________________________________ 4


2.1. Check position ___________________________________________________________ 4

3. Setting of entrance template ______________________________________________ 5


3.1. Concept of template for scafold-less method __________________________________ 5

3.2. Rail gauge for scaffold less method __________________________________________ 6


Part. Template
MUSE ED Elevator Ctrl. No. MUSE ED-IM-01-0

FOD Page 3/6


Overseas Support Team
Installation Manual Date Mar. 2009

The installation of MUSE ED E/L can be performed with scaffold-less method.


So, the main concept of explanation for field installation in this manual is based on scaffold-less
method of construction.

1. Templates
1.1. Making of entrance template

Cutting of top entrance template

Cutting of bottom entrance template

1.2. Making of Car and CWT templates

CWT template
Cutting is not required
For CWT rail and
bracket alignment
RG/2 + 50mm

CWTistemplate
Cutting not required
Car template

RG/2 + 50mm

Car template

For main rail and bracket alignment

Safety
Part. Template
MUSE ED Elevator Ctrl. No. MUSE ED-IM-01-0

FOD Page 4/6


Overseas Support Team
Installation Manual Date Mar. 2009

2. Hoistway layout

CWT side

Wall finish line

Height
2500mm

Floor level
finish line

Detail checking of hoistway

2.1. Check position


a. The proper size of A is about 120~125mm .
b. The proper height of top template base is 2500mm from top floor level.
c. Find proper position by checking hoistway to avoid chipping for inside wall
d. Above A,B1,B2,C,D size must be measured and considered at all floors.

Access into hoistway after making provision of protection


Caution
! against fall down.
Part. Template
MUSE ED Elevator Ctrl. No. MUSE ED-IM-01-0

FOD Page 5/6


Overseas Support Team
Installation Manual Date Mar. 2009

3. Setting of entrance template

Fixing of Entrance

3.1. Concept of template for scafold-less method


a. To avoid car frame interruption, We, SIGMA use special rail gauge. So, the plumb line
position differs from scaffold method.

50mm

Plumb line for


rail alignment and
bracket setting

150mm

Plumb line for


rail alignment
Plumb line for
Bracket setting

Scaffold method Scaffold –less method of SIGMA