You are on page 1of 7

Premier Cement Mills Limited.

VRM Project Steel Structural works.


1st R/A Bill Measurement.

FABRICATION & ERECTION OF HOT ROLLED


01. Silo -01 Internal Stair works:
Column: Channel(150x75x8mm)= 12.335mx4.0 nosx18.84 kg/m = 929.565 Kg
= 13.80m x 2.0 nos x 18.84 kg/m = 519.984 Kg
= 12.25m x 2.0 nos x 18.84 kg/m = 461.58 Kg
Base Plate (16mm thick.) = 0.30m x 0.30m x 4nos x125.60kg/m2= 45.216 Kg
Top Plate (16mm thick.) = 0.15m x 0.15m x 3nosx125.60 kg/m2= 8.478 Kg
Landing-01:Channel(200x75x10mm)=3.20mx2.0nosx27.475 kg/m = 175.84 Kg
=1.0m x 4.0nos x 27.475 kg/m = 109.90 Kg
Channel(250x75x10mm)=2.05m x 1.0nos x31.40 kg/m =64.37 Kg
Channel(100x50x5mm)= 0.80m x 4.0nos x 7.85 kg/m = 25.12 Kg
Angle (75x75x6mm)= 0.80m x 18.0nos x 7.065 kg/m = 101.736 Kg
Checker Plate (5mm thick.) = 0.80m x 0.25m x 9nos x 42.72kg/m2 = 76.896 Kg
= 1.04m x 1.94m x 1nos x 42.72kg/m2 =86.191 Kg
Landing-02:Channel(200x75x10mm)=2.10mx2.0nosx27.475 kg/m = 115.395 Kg
=1.01m x 4.0nos x 27.475 kg/m = 110.999 Kg
Channel(250x75x10mm)=2.05m x 1.0nos x 31.40 kg/m =64.37 Kg
Channel(100x50x5mm)= 0.80m x 4.0nos x 7.85 kg/m = 25.12 Kg
Angle (75x75x6mm)= 0.80m x 12.0nos x 7.065 kg/m = 67.824 Kg
Checker Plate (5mm thick.) = 0.80m x 0.25m x 6nos x 42.72kg/m2 = 51.264 Kg
= 1.06m x 1.94m x 1nos x 42.72kg/m2 =87.849 Kg
Landing-03:Channel(200x75x10mm)=2.07mx2.0nosx27.475 kg/m = 113.746 Kg
=1.0m x 4.0nos x 27.475 kg/m = 109.90 Kg
Channel(250x75x10mm)=2.05m x 1.0nos x 31.40 kg/m= 64.37 Kg
Channel(100x50x5mm)= 0.80m x 2.0nos x 7.85 kg/m = 12.56 Kg
Angle (75x75x6mm)= 0.80m x 14.0nos x 7.065 kg/m = 79.128 Kg

Page # 1
Checker Plate (5mm thick.) = 0.80m x 0.25m x 6nos x 42.72kg/m2 = 51.264 Kg
= 1.08m x 1.94m x 1nos x 42.72kg/m2 =89.506 Kg
Landing-04:Channel(200x75x10mm)=2.10mx2.0nosx27.475 kg/m = 115.395 Kg
=1.0m x 4.0nos x 27.475 kg/m = 109.90 Kg
=1.6m x 1.0nos x 27.475 kg/m = 43.96 Kg
Channel(250x75x10mm)=1.36m x 1.0nos x 31.40 kg/m= 42.704 Kg
=2.05m x 1.0nos x 31.40 kg/m= 64.37 Kg
Channel(100x50x5mm)= 1.0m x 3.0nos x 7.85 kg/m = 23.55 Kg
Angle (75x75x6mm)= 0.80m x 16.0nos x 7.065 kg/m = 90.432 Kg
Checker Plate (5mm thick.) = 0.80m x 0.25m x 6nos x 42.72kg/m2 = 51.264 Kg
= 1.07m x 1.92m x 1nos x 42.72kg/m2 =87.763 Kg
= 1.51m x 1.05m x 1nos x 42.72kg/m2 =67.732 Kg
Landing-05:Channel(200x75x10mm)=2.95mx2.0nosx27.475 kg/m = 162.102 Kg
=0.85m x 4.0nos x 27.475 kg/m = 93.415 Kg
Channel(250x75x10mm)=2.05m x 1.0nos x 31.40 kg/m= 64.37 Kg
Angle (75x75x6mm)= 0.80m x 22.0nos x 7.065 kg/m = 124.344 Kg
Checker Plate (5mm thick.) = 0.80m x 0.25m x 9nos x 42.72kg/m2 = 76.896 Kg
= 1.95m x 0.92m x 1nos x 42.72kg/m2 =74.674 Kg
Landing-06:Channel(200x75x10mm)=2.97mx2.0nos x 27.475 kg/m = 163.201 Kg
=1.65m x 1.0nos x 27.475 kg/m = 45.333 Kg
=0.9m x 4.0nos x 27.475 kg/m = 98.910 Kg
Channel(250x75x10mm)=2.05m x 1.0nos x 31.40 kg/m= 64.37 Kg
=1.36m x 1.0nos x 31.40 kg/m= 42.704 Kg
Channel(100x50x5mm)= 0.8m x 3.0nos x 7.85 kg/m = 18.84 Kg
Angle (75x75x6mm)= 0.80m x 22.0nos x 7.065 kg/m =124.344 Kg
Checker Plate (5mm thick.) = 0.80m x 0.25m x 9nos x 42.72kg/m2 = 76.896 Kg
= 3.42m x 0.96m x 1nos x 42.72kg/m2 =140.258 Kg
Landing-07:Channel(200x75x10mm)=2.12mx2.0nos x 27.475 kg/m = 116.494 Kg
=1.0m x 3.0nos x 27.475 kg/m = 82.425 Kg
Channel(250x75x10mm)=2.05m x 1.0nos x 31.40 kg/m= 64.37 Kg
Page # 2
Channel(100x50x5mm)= 0.8m x 2.0nos x 7.85 kg/m = 12.56 Kg
Angle (75x75x6mm)= 0.80m x 14.0nos x 7.065 kg/m =79.128 Kg
Checker Plate (5mm thick.) = 0.80m x 0.25m x 6nos x 42.72kg/m2 = 51.264 Kg
= 1.87m x1.07m x 1nos x 42.72kg/m2 =85.478 Kg
Landing-08:Channel(200x75x10mm)=2.92mx2.0nos x 27.475 kg/m = 160.454 Kg
=1.21m x 2.0nos x 27.475 kg/m = 66.489 Kg
Angle (75x75x6mm)= 0.80m x 16.0nos x 7.065 kg/m =90.432 Kg
Checker Plate (5mm thick.) = 0.80m x 0.25m x 7nos x 42.72kg/m2 = 59.808 Kg
= 1.20m x0.93m x 1nos x 42.72kg/m2 =47.675 Kg
Reeling (Out Dia=60mm, Thick.=4mm) = 53.10m x 5.90 kg/m = 313.29 Kg
Reeling (Out Dia=60mm, Thick.=4mm) = 75.00m x 5.90 kg/m = 442.50 Kg
Reeling (Out Dia=48mm, Thick.=3mm) = 116.20m x 3.55 kg/m = 412.510 Kg
TOTAL = 7800.775 Kg

Page # 3
02. CCR Building Stair works:
Column: Channel(150x75x8mm)= 21.80mx4.0 nosx18.84 kg/m = 1642.848 Kg
Gusset Plate (10mm thick.) = 0.60mx0.345mx13nosx78.50kg/m2= 211.243 Kg
= 0.30mx0.32mx4nosx78.50kg/m2= 30.144 Kg
Base Plate (10mm thick.) = 0.30m x 0.30m x 1nos x78.50kg/m2= 7.065 Kg
Base Plate (20mm thick.) = 0.35m x 0.35m x 2nos x157.0kg/m2= 38.465 Kg
Base Plate (10mm thick.) = 0.50m x 0.35m x 1nos x78.50kg/m2= 13.737 Kg
Top Plate (16mm thick.) = 0.15m x 0.15m x 2nosx125.60 kg/m2= 5.652 Kg
Tie between stair & wall :
Angle (100x100x10mm) = 4.53m x 2.0nos x 15.70 kg/m = 142.242 Kg
= 7.80m x 5.0nos x 15.70 kg/m = 612.30 Kg
= 6.0m x 8.0nos x 15.70 kg/m = 753.60 Kg
Landing-01:Channel(200x75x10mm)=6.265mx2.0nos x 27.475 kg/m = 344.261 Kg
=0.15m x 2.0nos x 27.475 kg/m = 8.242 Kg
=1.20m x 4.0nos x 27.475 kg/m = 131.88 Kg
Channel(250x75x10mm)=1.785m x 1.0nos x 31.40 kg/m = 56.049 Kg
Channel(100x50x5mm)= 0.70m x 4.0nos x 7.85 kg/m = 21.98 Kg
Angle (75x75x6mm)= 0.70m x 42.0nos x 7.065 kg/m = 207.711 Kg
Checker Plate (5mm thick.) = 0.70m x 0.25m x 21nos x 42.72kg/m2 = 156.996 Kg
= 1.28m x 1.71m x 1nos x 42.72kg/m2 =93.505 Kg
Landing-02:Channel(200x75x10mm)=5.57mx2.0nos x 27.475 kg/m = 344.261 Kg
=1.20m x 4.0nos x 27.475 kg/m = 131.88 Kg
Channel(250x75x10mm)=1.785m x 1.0nos x 31.40 kg/m = 56.049 Kg
Channel(100x50x5mm)= 0.70m x 8.0nos x 7.85 kg/m = 43.96 Kg
Angle (75x75x6mm)= 0.70m x 38.0nos x 7.065 kg/m = 187.929 Kg
Checker Plate (5mm thick.) = 0.70m x 0.25m x 19nos x 42.72kg/m2 = 142.044 Kg
= 2.075m x 1.065m x 1nos x 42.72kg/m2 =94.405 Kg
Landing-03:Channel(200x75x10mm)=5.29mx2.0nos x 27.475 kg/m = 290.685 Kg
=1.20m x 4.0nos x 27.475 kg/m = 131.88 Kg
Channel(250x75x10mm)=1.785m x 1.0nos x 31.40 kg/m = 56.049 Kg
Page # 4
Channel(100x50x5mm)= 0.70m x 4.0nos x 7.85 kg/m = 21.98 Kg
Angle (75x75x6mm)= 0.70m x 34.0nos x 7.065 kg/m = 168.147 Kg
Checker Plate (5mm thick.) = 0.70m x 0.25m x 17nos x 42.72kg/m2 = 127.097 Kg
= 1.275m x 1.71m x 1nos x 42.72kg/m2 = 93.140 Kg
Landing-04:Channel(200x75x10mm)=5.37mx2.0nos x 27.475 kg/m = 295.081 Kg
=1.20m x 4.0nos x 27.475 kg/m = 131.88 Kg
Channel(250x75x10mm)=1.785m x 1.0nos x 31.40 kg/m = 56.049 Kg
Channel(100x50x5mm)= 0.70m x 8.0nos x 7.85 kg/m = 43.96 Kg
Angle (75x75x6mm)= 0.70m x 36.0nos x 7.065 kg/m = 178.038 Kg
Checker Plate (5mm thick.) = 0.70m x 0.25m x 18nos x 42.72kg/m2 = 134.568 Kg
= 2.075m x 1.76m x 1nos x 42.72kg/m2 = 156.013 Kg
Landing-05:Channel(200x75x10mm)=5.59mx2.0nos x 27.475 kg/m = 307.170 Kg
=1.20m x 4.0nos x 27.475 kg/m = 131.88 Kg
Channel(250x75x10mm)=1.785m x 1.0nos x 31.40 kg/m = 56.049 Kg
Channel(100x50x5mm)= 0.70m x 4.0nos x 7.85 kg/m = 21.98 Kg
Angle (75x75x6mm)= 0.70m x 34.0nos x 7.065 kg/m = 168.147 Kg
Checker Plate (5mm thick.) = 0.70m x 0.25m x 17nos x 42.72kg/m2 =127.092 Kg
= 1.72m x 1.275m x 1nos x 42.72kg/m2 =93.684 Kg
Landing-06:Channel(200x75x10mm)=5.45mx2.0nos x 27.475 kg/m = 299.477 Kg
=2.0m x 4.0nos x 27.475 kg/m = 219.80 Kg
Channel(250x75x10mm)=1.785m x 1.0nos x 31.40 kg/m = 56.049 Kg
Channel(100x50x5mm)= 0.70m x 8.0nos x 7.85 kg/m = 43.96 Kg
Angle (75x75x6mm)= 0.70m x 36.0nos x 7.065 kg/m = 178.038 Kg
Checker Plate (5mm thick.) = 0.70m x 0.25m x 18nos x 42.72kg/m2=134.568 Kg
= 1.73m x 2.075m x 1nos x 42.72kg/m2 = 153.354 Kg
Landing-07:Channel(200x75x10mm)=5.31mx2.0nos x 27.475 kg/m = 291.784 Kg
=1.2m x 4.0nos x 27.475 kg/m = 131.88 Kg
Channel(250x75x10mm)=1.785m x 1.0nos x 31.40 kg/m = 56.049 Kg
Channel(100x50x5mm)= 0.70m x 4.0nos x 7.85 kg/m = 21.98 Kg
Angle (75x75x6mm)= 0.70m x 36.0nos x 7.065 kg/m = 178.038 Kg
Checker Plate (5mm thick.) = 0.70m x 0.25m x 18nos x 42.72kg/m2=134.568 Kg
Page # 5
= 1.025m x 1.285m x 1nos x 42.72kg/m2 = 56.267 Kg
Landing-08:Channel(200x75x10mm)=5.26mx2.0nos x 27.475 kg/m =289.037 Kg
=2.0m x 2.0nos x 27.475 kg/m = 131.88 Kg
Channel(250x75x10mm)=1.785m x 1.0nos x 31.40 kg/m = 56.049 Kg
Channel(100x50x5mm)= 0.70m x 4.0nos x 7.85 kg/m = 21.98 Kg
Angle (75x75x6mm)= 0.70m x 36.0nos x 7.065 kg/m = 178.038 Kg

Checker Plate (5mm thick.) = 0.70m x 0.25m x 18nos x 42.72kg/m2=134.568 Kg


= 2.05m x 0.88m x 1nos x 42.72kg/m2 = 77.066 Kg
TOTAL = 11113.444 Kg
Total Hot Rolled works of 1st R/A bill (7800.775+11113.444)=18914.219 Kg.
= 18.914 Ton

03. Dismantling works:


Silo -01 Inner stair railing horizontal pipe (Out Dia=60mm, Thick.=4mm)
= 75.00m x 5.90 kg/m = 442.50 Kg
= 0.442 Ton

Page # 6
FABRICATION & ERECTION WORKS
I-Beam (332x200x16x10mm)
C1 = 5.50m x 2 nos x 73.79 Kg/m = 811.690 Kg.
C1 = 6.00m x 2 nos x 73.79 Kg/m = 885.480 Kg.
C1 = 7.50m x 2 nos x 73.79 Kg/m = 1106.850 Kg.
C1 = 8.00m x 2 nos x 73.79 Kg/m = 1180.640 Kg.
C1 = 10.50m x 2 nos x 73.79 Kg/m = 1549.590 Kg.
I-Beam (400x200x14x10mm)
SB = 5.236m x 4 nos x 73.16 Kg/m = 1532.263 Kg.
SB = 5.240m x 1 nos x 73.16 Kg/m = 383.358 Kg.
I-Beam (270x156x10x8mm)
SB = 3.268m x 6 nos x 40.192 Kg/m = 788.08 Kg.
SB = 8.944m x 6 nos x 40.192 Kg/m = 2156.863 Kg.
I-Beam (270x200x10x8mm)
SB = 10.50m x 4 nos x 47.10 Kg/m = 1978.20 Kg.
SB = 7.00m x 4 nos x 47.10 Kg/m = 1318.80 Kg.
20mm thick. Base plate :
= 0.40m x 0.40m x 10 nos x 157 Kg/m2 = 251.20 Kg.
16mm thick. Pad plate :
= 0.40m x 0.20m x 10 nos x 125.6 Kg/m2 = 100.48 Kg.
TOTAL = 14043.494 Kg
= 14.043 Ton

Page # 7